This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Terracon Consultants, Inc. for site assessment work at Alpine Cleaners (ERIC_3987) located at 5240 NW 34th Street in Gainesville, Alachua County, Florida. The TA is executed under Contract Number HW687, a statewide Waste Cleanup Program (WCP) indefinite delivery vehicle. The task assignment was effective June 30, 2023, with a completion date of December 31, 2023. Dean Cox serves as the FDEP Project Manager, and Donna Cline is the Contractor's Project Manager.
The scope of work encompasses six subtasks: (1) Project Management; (2) Sewer Line Inspections, Geophysical Survey, Piezometer and Interior Well Installations, Lithological Profiling, and Groundwater Profile Assessment; (3) Soil Sampling and Modified Active Gas Sampling (MAGS); (4) Monitoring Well Installation and Groundwater Sampling; (5) Investigative Derived Waste (IDW) Management; and (6) Site Assessment Report preparation. The total TA value is $104,429.79 on a fixed unit rate basis. Invoicing is contingent upon FDEP approval at three milestones: $71,457.82 for approved monitoring well and soil/groundwater analytical reports; $30,794.71 for the approved Site Assessment Report; and $2,177.26 for submittal of investigation derived waste manifests. The deliverables include monitoring well boring and construction logs, groundwater sampling logs, analytical reports, and a comprehensive Site Assessment Report, with primary deliverable due dates of August 31, 2023, and September 30, 2023.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW687
DC028B Completion December 31, 2023
This TA authorizes costs associated with site assessment. The total cost of this TA is $104,429.79 and all costs are fixed unit rate.
Dean Cox 850-245-8969 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Terracon Consultants, Inc.
Terracon Consultants, Inc.
Donna Cline 813-321-0340
ERIC_3987
5240 NW 34th Street, Gainesville (Alachua County)
Alpine Cleaners
✔ $ 104,429.79
$ 104,429.79
Scope of Work
Tom Lewis
Principal
Lewis, Tom E Digitally signed by Lewis, Tom E Date: 2023.06.30 14:50:05 -04'00'
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.06.30 14:14:54 -04'00'
6/30/2023
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Monitoring well boring & construction logs, litho boring log, groundwater sampling logs, screen point logs, MAGS litho logs & test results/calcs, certified soil and groundwater analytical reports, and field notes (Subtask 2 and Subtask 3).
08/31/2023
Site Assessment Report (Subtask 1 and Subtask 4 and Subtask 6).
09/30/2023
DEP approval of monitoring well boring & construction logs, litho boring log, groundwater sampling logs, screen point logs, MAGS litho logs & test results/calcs, soil and groundwater analytical reports, and field notes (Subtask 2 and Subtask 3).
$ 71,457.82
DEP approval of Site Assessment Report (Subtask 1 and Subtask 4 and Subtask 6).
$ 30,794.71
Submittal of investigation derived waste manifests (Subtask 5).
$ 2,177.26
$ 104,429.79
HW687
DC028B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Negotiation Summary
TO: HW687 Contract File FROM: Dean Cox, Contract Manager SUBJECT: DC028B Alpine Cleaners ERIC_3987 Site Assessment
DATE: 6/30/23
This TA authorizes costs associated with site assessment. The total cost of this TA is $104,429.79 and all costs are fixed unit rate. This TA was negotiated - the total cost is $5,060.83 or 5% less than originally proposed. Site access was confirmed.
The PM discussed the scope of this TA with the WSCS PG. The site screening samples were above associated cleanup target levels, at moderate concentrations. This site was approved for remediation and provided to Terracon in December 2022 (site access confirmed).
FDEP COST ESTIMATE
Contractor: Terracon
Date: 6/30/2023 Task #: SubTask 1 Project Management SubTask 6 Site Assessment Report
Site: Alpine Cleaners Eric_3987 SubTask 2 Sewer Line Inspections, Geophys Survey, Piezometer Installs, Litho SubTask 7 Activity/Phase: Site Assessment Workplan Investigation SubTask 3 Soil Sampling, MAGS SubTask 8
Project Manager: Dean Cox SubTask 4 Monitoring Well Installation and Groundwater Sampling SubTask 9 SubTask 5 IDW Soil and GW Management SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$57.45 Project Manager Luke Davis 30.14 30.14 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$32.50 CADD Specialist Chelsea Fugate 17.00 0.00 0.00 0.00 0.00 17.00 0.00 0.00 0.00 0.00 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$25.24 Field Scientist Nicole Kovach 14.50 9.00 0.00 0.00 5.50 0.00 0.00 0.00 0.00 0.00 $31.01 Field Scientist Darryl Williams 159.00 55.25 42.50 34.25 0.00 27.00 0.00 0.00 0.00 0.00 $22.88 Field Scientist Roy Starr 98.75 44.75 22.00 13.00 1.00 18.00 0.00 0.00 0.00 0.00 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$69.71 Senior Engineer Chad Northington 35.00 0.00 29.00 0.00 0.00 6.00 0.00 0.00 0.00 0.00 $57.45 Senior Geologist Luke Davis 32.50 16.50 0.00 0.00 0.00 16.00 0.00 0.00 0.00 0.00 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$47.60 Senior Scientist Sid O'Neal 19.00 0.00 19.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 405.89 30.14 125.50 112.50 47.25 6.50 84.00 0.00 0.00 0.00 0.00
Direct Labor $15,051.43 $1,731.58 $3,912.27 $4,747.28 $1,359.53 $161.70 $3,139.07 $0.00 $0.00 $0.00 $0.00
Overhead 116.00% $17,459.64 $2,008.63 $4,538.23 $5,506.84 $1,577.05 $187.57 $3,641.32 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $8,467.93 $974.19 $2,201.04 $2,670.82 $764.87 $90.97 $1,766.04 $0.00 $0.00 $0.00 $0.00 Total Labor $40,979.00 $4,714.40 $10,651.54 $12,924.94 $3,701.45 $440.24 $8,546.43 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 1
FDEP COST ESTIMATEContractor: Terracon Date: 6/30/2023
Task #: SubTask 1 Project Management SubTask 6 Site Assessment Report Site: Alpine Cleaners Eric_3987 SubTask 2 Sewer Line Inspections, Geophys Survey, Piezometer Installs, Litho SubTask 7
Activity/Phase: Site Assessment Workplan Investigation SubTask 3 Soil Sampling, MAGS SubTask 8 Project Manager: Dean Cox SubTask 4 Monitoring Well Installation and Groundwater Sampling SubTask 9
SubTask 5 IDW Soil and GW Management SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle charge $2,360.00 800.00$ 960.00$ 480.00$ 120.00$ $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $3,817.00 2,149.00$ 1,260.00$ 408.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $6,177.00 $2,949.00 $2,220.00 $888.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) - GPI/EDS $28,837.00 10,993.50$ 10,993.50$ 6,850.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying - SSMC $2,150.00 $0.00 $0.00 2,150.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin Remediation $1,430.00 $0.00 $0.00 $0.00 1,430.00$ $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Geoview $1,300.00 1,300.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Camera Line (Sunshine) $750.00 750.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $34,467.00 $13,043.50 $10,993.50 $9,000.00 $1,430.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $3,446.70 $1,304.35 $1,099.35 $900.00 $143.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $37,913.70 $14,347.85 $12,092.85 $9,900.00 $1,573.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $9,865.00 3,504.00$ 5,704.00$ 657.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $590.00 150.00$ 330.00$ 110.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $10,455.00 $3,654.00 $6,034.00 $767.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $612.00 266.00$ 173.00$ 173.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $650.00 650.00$ $0.00 -$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,148.20 420.00$ 2,320.00$ 408.20$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $347.00 347.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $50.00 50.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $4,807.20 $1,733.00 $2,493.00 $581.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $100,331.90 $4,714.40 $33,335.39 $35,764.79 $15,837.65 $2,133.24 $8,546.43 $0.00 $0.00 $0.00 $0.00 Completion Fee $4,097.89 $471.44 $1,065.15 $1,292.49 $370.15 $44.02 $854.64 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $104,429.79 $5,185.84 $34,400.54 $37,057.28 $16,207.80 $2,177.26 $9,401.07 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Alpine Cleaners Eric_3987
SUBTASK 2:
PROPOSAL NO. PHF237059
DATE: 6/30/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Task Planning and Pre-Drilling Tasks Field Scientist RS 1.00 Senior Geologist LD 2.00
Field Scientist NK 9.00
Senior Geologist LD 1.00 Senior Geologist LD 1.00
Interior Well, Piezometer Well Installation and Deep Lithological Boring
Time Duration: 2 days Field Scientist DW Load/unload equipment (0.75 hour/day) 1.50 Field Scientist RS Direct work, daily safety debrief, perform OVA screening of lithological/piezometer/monitoring well borings 13.00 Field Scientist DW Oversee piezometer installs & development, record MW logs 9.00 Field Scientist DW 4.00 Senior Geologist LD 4.00 Field Scientist DW Containerize IDW (0.5/hours per day) 1.00 Field Scientist RS Prepare well construction and boring logs and field notes for PM evaluation (0.75 hr/day) 1.25
Groundwater Sampling
Time Duration: 1 day Field Scientist DW Load/unload equipment (0.75 hour/day) 0.75 Field Scientist DW Collect water levels (1 interior well, 3 piezometers, 10 minutes/well) 0.75 Field Scientist DW Containerize IDW (0.5 hrs/day) 0.50 Field Scientist DW Collect groundwater samples for VOHs ( wells, 1.5 hours each) 4.00 Field Scientist DW Collect soil and groundwater IDW samples from the 55-gallon drums 1.00 Field Scientist DW Prepare gw sampling and calibration logs and field notes for PM evaluation (1 hr/day) 1.00
Direct Push Boring with Screen Point Sampling
Time Duration: 3 days Field Scientist DW Load/unload equipment (0.75 hour/day) 2.25 Field Scientist RS Direct work, daily safety debrief, boring logs, assist with sample collection 24.00 Field Scientist DW Collect samples, record field notes, oversee borehole grouting, complete COC 24.00 Senior Geologist LD 4.50 Field Scientist DW Containerize IDW (0.5/hours per day) 1.50 Field Scientist RS Prepare boring logs and field notes for PM evaluation (0.5 hr/day) 1.50 Senior Geologist LD Review gw screening data, communicate with FDEP (0.5 hr/day) 0.00
Mobilization / Demobilizations Senior Geologist LD 4.00 Field Scientist RS CN 4.00 Field Scientist DW 0.00 4.00
Personnel: RS DW LD NK SO Hours: 44.75 55.25 16.50 9.00 0.00 TOTAL LABOR 125.50
VEHICLE TYPE RATE UNIT USEAGE
Car 320.00$ week 1 320.00$ Truck 480.00$ week 1 480.00$ Truck 480.00$ week 0 -$
TOTAL VEHICLE 800.00$
PER DIEM STAFF RATE UNIT USEAGE
Lodging Luke Davis $150.00 days 3 450.00$ Meals Luke Davis $36.00 days 4 144.00$ Lodging Darryl Williams $150.00 days 4 600.00$ Meals Darryl Williams $36.00 days 5 180.00$ Lodging Roy Starr $150.00 days 4 600.00$ Meals Roy Starr $35.00 days 5 175.00$
TOTAL PER DIEM 2,149.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
Sunshine Plumbing Sewer video camera work 750.00$ each 1 750.00$ GPRS or Geoview GPR and EM Survey 1,300.00$ 1 1 1,300.00$ GPI Piezometer, Lithology, GW Screen 10,993.50$ each 1 10,993.50$
TOTAL SUBCONTRACTOR 13,043.50$
Sewer Line Inspections, Geophys Survey, Piezometer Installs, Litho Log, GW Screening
Contact owner and conduct pre-drilling site walk with property owner, current tenants, drilling contractor, and FDEP. Designate IDW staging areas, decon pad location, and truck staging areas.
Prepare Health and Safety Plan
Attend initial site visit and oversee camera work and geophysical survey for boring, groundwater screening locations (geophysical subcontractor estimated a full day of labor) Attend initial site visit to meet with owner, review technical approach to groundwater Investigation Prepare soil logging and well construction materials
Senior geologist oversight of deep lithological boring, records lithological descriptions Survey top of casing elevation of piezometers and assess gw flow direction
Senior geologist oversight / technical QA/QC of operations (1.5 hours/day)
2 Days, (2 hour/day from Jacksonville) 2 Days, (2 hour/day from Jacksonville)
2 Days, (2 hour/day from Jacksonville)
Scope: 9 Locations to 55 ft bls, collect screen point samples @ 15-19, 25-29, 35-39, 45-49, and 51-55 ft bgs, total of 45 screen point samples
Scope: Interior well to a depth of 25 ft bgs / 3 Piezometers wells to a depth of 25 ft bgs and one deep litho borings to 50 feet depth
Scope: 3 Wells (includes 1 interior monitoring well/pz, 2 exterior/piezometer)
SUBTASK 2:
PROPOSAL NO. PHF237059
DATE: 6/30/2023
Sewer Line Inspections, Geophys Survey, Piezometer Installs, Litho Log, GW Screening
LABORATORY COSTS
PARAMETER RATE # SAMPLES
Halocarbons EPA 8260 73.00$ 48 3,504.00$ Sample Shipping Large Cooler (overnight) 150.00$ 1 150.00$
TOTAL LAB 3,654.00$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables Expendables 40.00$ day 6 240.00$
Ice (Sample Preservation) 6.50$ each 4 26.00$ Drilling related Monitoring Well Installation Kit 325.00$ day 2 650.00$ Analytical related YSI 105.00$ day 4 420.00$ IDW related (Drums provided by Diller)
Groundwater Sampling Kit 290.00$ day 1 290.00$ Tubing, HDPE 0.30$ ft 150 45.00$ Tubing, silicon (3/16 x 3/8) 3.00$ ft 4 12.00$
Other Total Survey Station 50.00$ day 1 50.00$
TOTAL EQUIPMENT 1,733.00$
SUBTASK 3: Soil Sampling, MAGS
PROPOSAL NO. PHF237059
DATE: 6/30/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Task Planning Senior Engineer CN 0.50 Senior Engineer CN 0.50 Soil Sampling / Oversee MAGS Well Installation Scope: 8 MAGS well Time Duration: 2 day Field Scientist DW Load/unload equipment (0.75 hour/day) 1.50 Field Scientist DW Direct work, daily safety debrief, record lithological descriptions, oversee MAGS well install 18.00 Field Scientist RS Collect one sample at 0.5, 2, 4, 6, 8 and 10 ft bgs for laboratory analysis (SPLP and VOCs) 17.00 Field Scientist RS Containerize IDW (0.5 hours/day) 1.00 Field Scientist DW Finalize field notes at end of day for PM evaluation (0.5 hour/day) 1.00 MAGS Test Time Duration: 2 Days Senior Engineer CN Attend Pre Task Planning meeting and review technical approach to MAGS 1.00 Field Scientist DW Deliver and set up MAGS System 3.00 Senior Engineer CN Perform and direct MAGS sampling test (6 points x 1.5 hr/point = 9, oversee set up / calibration) 15.00 Field Scientist DW Collect vacuum/pressure and OVA screening measurements, collect samples for lab analysis 15.00 Senior Scientist SO Maintain system operation of the MAGS system, reduce vacuum / flows as directed by Engineer / 15.00
Maintain hoses / decon as appropriate between MAGS wells Senior Engineer CN Finalize field notes at end of day (1 hour/day) 2.00 Senior Engineer CN Interpret field data, perform calculations, and provide update to FDEP (6 hrs) 6.00
Mobilization / Demobilizations Senior Engineer CN 4.00 Senior Scientist SO 2 Days, (2 hour/day from Tallahassee) 4.00 Field Scientist RS 4.00 Field Scientist DW 2 Days, (2 hour/day from Jacksonville) 4.00
Personnel: RS SO DW NK CN Hours: 22.00 19.00 42.50 0.00 29.00 TOTAL LABOR 112.50
VEHICLE TYPE RATE UNIT USEAGE
Truck 480.00$ week 1 480.00$ Truck 120.00$ days 3 360.00$ Truck 120.00$ days 1 120.00$ Car 80.00$ days 0 -$
TOTAL VEHICLE 960.00$
PER DIEM STAFF RATE UNIT USEAGE
Lodging Darryl Williams $150.00 days 3 450.00$ Meals Darryl Williams $36.00 days 4 144.00$ Lodging Roy Starr $150.00 days 1 150.00$ Meals Roy Starr $36.00 days 2 72.00$ Lodging Sid O'Neal $150.00 days 1 150.00$ Meals Sid O'Neal $36.00 days 2 72.00$ Lodging Chad Northington $150.00 days 1 150.00$ Meals Chad Northington $36.00 days 2 72.00$
TOTAL PER DIEM 1,260.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
GPI-Drill Pro 10,993.50$ each 1 10,993.50$
TOTAL SUBCONTRACTOR 10,993.50$
2 Days, (2 hour/day from Jacksonville)
2 Days, (2 hour/day from Tallahassee)
Concrete coring, advance hand auger, and MAGS well installations
Develop soil installation SOW and drilling safe right procedures Prepare soil logging materials and finalize day-of logistics for investigation
SUBTASK 3: Soil Sampling, MAGS
PROPOSAL NO. PHF237059
DATE: 6/30/2023
LABORATORY COSTS
PARAMETER RATE # SAMPLES
Halocarbons EPA 8260 73.00$ 48 3,504.00$ VOCs (soil-prep) 5035 prep 7.00$ 48 336.00$ SPLP Bottle Extraction Method 1312 -$ 0 (to be submitted as WCD) -$ VOCs Soil Vapor- Full ScaTO-15 200.00$ 8 1,600.00$
Summa Canister 33.00$ 8 264.00$ Sample Shipping Small Cooler (overnight) 110.00$ 3 330.00$
TOTAL LAB 6,034.00$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables Expendables 40.00$ day 4 160.00$
Ice (Sample Preservation) 6.50$ each 2 13.00$ Analytical related Encore Sampler 16.00$ each 48 (SPLP samples - hold) 768.00$
Terra Core Sampler 11.00$ each 48 (VOH samples) 528.00$ Hand Auger 12.00$ day 2 24.00$ MAGS Investigation Kit 500.00$ day 2 1,000.00$
IDW related (Drums provided by Diller)
TOTAL EQUIPMENT 2,493.00$
SUBTASK 4: Monitoring Well Installation and Groundwater Sampling
PROPOSAL NO. PHF237059
DATE: 6/30/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Task Planning and Pre-Drilling Tasks (Primarily included in LOE 2) Field Scientist RS 1.00
Monitoring Well Installation Scope: 4 Wells to a proposed depth of 25 ft bgs (3) and 45 ft bgs (1) Time Duration: 2 days Field Scientist DW Load/unload equipment (0.75 hour/day) 1.50 Field Scientist RS Direct work, daily safety debrief, oversee subcontracted surveyor 8.00 Field Scientist DW Oversee well installation, well development, record on MW Install Log 14.00 Field Scientist DW Containerize IDW (0.5 hrs/day) 1.00 Field Scientist DW Prepare draft well and boring logs and field notes for PM evaluation (0.5 hr/day) 1.00
Groundwater Sampling
Time Duration: 2 days Field Scientist DW Load/unload equipment (0.75 hour/day) 0.00 Field Scientist DW Collect water levels (7 wells, 10 minutes/well) 1.00 Field Scientist DW Containerize IDW (0.5 hrs/day) 0.50 Field Scientist DW Collect groundwater samples for VOHs (7 wells, 1.5 hours each) 9.50 Field Scientist DW Collect soil and groundwater IDW samples from the 55-gallon drums 0.75 Field Scientist DW Prepare gw sampling and calibration logs and field notes for PM evaluation (1 hr/day) 1.00
Mobilization / Demobilizations Field Scientist DW 4.00 Field Scientist RS 4.00
Personnel: RS DW Hours: 13.00 34.25 TOTAL LABOR 47.25
VEHICLE TYPE RATE UNIT USEAGE
Truck 480 week 1 480.00$
TOTAL VEHICLE 480.00$
PER DIEM STAFF $0.00 UNIT USEAGE
Lodging Darryl Williams $150.00 days 2 300.00$ Meals Darryl Williams $36.00 days 3 108.00$
TOTAL PER DIEM 408.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
EDS MW Installation 6,850.00$ lump sum 1 6,850.00$ Geoline Surveying Survey, Location and Elevation 2,150.00$ lump sum 1 2,150.00$
TOTAL SUBCONTRACTOR 9,000.00$
LABORATORY COSTS
PARAMETER RATE # SAMPLES IDW
Halocarbons EPA 8260 73.00$ 7 657.00$ Sample Shipping Small Cooler (overnight) 110.00$ 1 110.00$
TOTAL LAB 767.00$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables Expendables 40.00$ day 4 160.00$
Ice (Sample Preservation) 6.50$ each 2 13.00$ Drilling related Monitoring Well Installation Kit 325.00$ day 0 -$ Analytical related Groundwater Sampling Kit 290.00$ day 1 290.00$
Tubing, HDPE 0.30$ ft 334 100.20$ Tubing, silicon (3/16 x 3/8) 3.00$ ft 6 18.00$
IDW related (Drums provided by Diller)
TOTAL EQUIPMENT 581.20$
2 Days,(2 hour/day from Jacksonville)
Prepare monitoring well installation materials and well installation kit.
Scope: 7 New Monitoring Wells (includes 1 interior monitoring well/pz, 2 piezometer wells, 4 new wells)
2 Days,(2 hour/day from Jacksonville)
SUBTASK 5: IDW Soil and GW Management
PROPOSAL NO. PHF237059
DATE: 6/30/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Coordinate IDW T&D Staff Scientist RS 1.00 Field Scientist NK 5.50
TOTAL LABOR 6.50
VEHICLE TYPE RATE UNIT USEAGE
Truck (IDW management) 120 day 1 120.00$
TOTAL VEHICLE 120.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
Erwin Remediation 110.00$ each 13 1,430.00$
TOTAL SUBCONTRACTOR 1,430.00$
IDW Disposal (soil / groundwater excluding haz mat)
Coordinate IDW T&D: Mobilize to site, meet transporter to sign manifests (four hour round trip) Prepare waste characterization/Generator Profile (potential for hazardous waste)
SUBTASK 6: Site Assessment Report
PROPOSAL NO. PHF237059
DATE: 6/30/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Report Deliverable Staff Scientist RS 12.00 Staff Scientist RS Summarize data into report tables 5.00 Senior Geologist LD QA/QC field and laboratory data 3.00 Senior Engineer CN Develop MAGS results, includes charts, calculations, and summary table of results, and recommend 6.00 Field Scientist DW 11.00
Senior Geologist LD 3.00
Senior Geologist LD Water Quality Parameters Summary Evaluation 2.00 Senior Geologist LD Groundwater Analytical Results and Summary Evaluation 3.00 Senior Geologist LD Evaluate data in report text, raw data, summary tables and exhibits 4.00 Senior Geologist LD Sign and Seal the Site Assessment Report 1.00
Field Scientist DW 16.00 CADD Specialist CF Prepare base figures and Exhibits (site setting, potable wells, groundwater flow, cross sections, 14.00 and concentrations maps) CADD Specialist CF Provide simplistic 2-D models that CSM supporting exhibits 4.00
Personnel: CF DW LD RS CN Hours: 18.00 27.00 16.00 17.00 6.00 TOTAL LABOR 84.00
Prepare boring logs (9 DPT Screen points, 8 soil locations, 1 lithological), to include well
Prepare boring logs, well construction diagrams, lithological descriptions, and cross sections (1 hour per well)
Prepare draft report introduction, site history, recent activities summary, and discussion of results
Forensic chemistry and analysis of reported COCs. Develop CSM based on potential fate and transport of COCs.
8001 Baymeadows Way Ste 1
Jacksonville, FL 32256
P (904) 900-6494
F (850) 268-5255
Terracon.com
June 27, 2023
Florida Department of Environmental Protection
Waste Cleanup Program
Waste Management Division
2600 Blair Stone Road
Tallahassee, Florida 32399-2400
Attn: Mr. Dean Cox, Environmental Consultant
E: Dean.Cox@FloridaDep.gov
W: 850-245-8969
M: 727-686-6502
Re: Proposal for Site Assessment Work Plan Implementation
Alpine Cleaners
5240 NW 34th Boulevard
Gainesville, Florida 32605
ERIC_3987
Task Assignment DC036A
Terracon Proposal No. PEQ237242
Dear Mr. Cox:
Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the
Florida Department of Environmental Program (FDEP) Waste Cleanup Program (WCP) to implement the proposed FDEP Site Assessment Workplan (SAWP) dated March 30, 2023 for Alpine Cleaners
(ERIC_3987) located at 5240 NW 34th Boulevard, Gainesville, Florida. The objective of this site assessment is to assess the horizontal and vertical extent of on-site chlorinated solvent contamination.
Scope of Services
◼ Subtask 1. Project Management
◼ Subtask 2. Sewer Line Inspections, Geophysical Survey, Piezometers and Interior Well Installations, Lithological Profiling, and Groundwater Profile Assessment
◼ Subtask 3. Soil Sampling and Modified Active Gas Sampling
(MAGS)
◼ Subtask 4. Monitoring Well Installation and Groundwater
Sampling
◼ Subtask 5. Investigative Derived Waste Management
◼ Subtask 6. Preparation of Site Assessment Report
See attached LOE for details
Schedule
Submit Site Assessment Report of on-site activities within 30 business days following receipt of laboratory results.
Compensation
See attached CEF for details.
mailto:Dean.Cox@FloridaDep.gov
Proposal for Site Assessment Workplan Investigation
Alpine Cleaners (Eric_3987) ■ Gainesville, FL
June 27, 2023 ■ Terracon Proposal No. PEQ237242
SCOPE OF SERVICES
Subtask 1 – Project Management
Luke Davis, P.G will serve as the Project Manager during the field investigation and will be involved throughout the project, serving as Authorized Project Reviewer.
Subtask 2 – Sewer Line Inspections, Geophysical Survey, Exterior Monitoring Wells and
Interior Well Installations, Lithological Profiling, and Groundwater Profile Assessment
Sewer Line Inspections, Piezometer and Interior Well Installations, Lithological Profiling, and
Groundwater Profile Assessment
Prior to subsurface investigations, Terracon will oversee sewer line inspections for potential cracks that could provide contaminant pathways to the subsurface. At this time, Sunshine Plumbing and Gas will provide a sewer line inspection using a camera. In addition, prior to subsurface investigations, Terracon will subcontract the services of a subsurface geophysical survey company to identify potential subsurface utilities or obstructions. Geoview and GPRS were the low bidders and both estimated that the work will take one day to complete. Terracon will pick based on schedule and availability. The geophysical survey bids are attached.
Following sewer line inspections and geophysical survey, using a track mounted direct-push rig, three
(3) lithological soil boring will be advanced across the Alpine Cleaners site.
In order to assess groundwater flow direction, monitoring wells located in potential source areas including the drycleaning machine, backdoor, and chemical storage area will be installed. The building interior shallow groundwater monitoring well will be installed using a dolly DPT rig or small track mounted rig in proximity to the area of the former PCE dry cleaning machine. The interior well will be constructed with 1” diameter Schedule 40 PVC with 10 to 25 feet of prepacked screen that will intersect the groundwater table. The groundwater sample collected from this interior monitoring well will be sampled for full list VOCs by EPA Method 8260 for standard turnaround. Each exterior shallow monitoring well will be screened using an OVA/PID and lithology descriptions and installed using a direct-push drill rig equipped with augers. Each exterior well will be constructed of 2-inch diameter
Schedule 40 PVC to approximately 25 ft bls with 15 ft of Schedule 40 PVC well screen with 0.01-inch slots. A 20/30 sand pack will be completed to two feet above the screen. A 30/65 filter pack will be applied above the screen pack and completed with a Type I/II Portland cement to approximately six inches below ground surface. Each shallow monitoring well will be flush-mounted to land surface in a 2 foot by 2 foot concrete pad and 8-inch diameter manhole. Groundwater samples will be collected for full list VOCs by EPA Method 8260. These groundwater samples will be submitted for standard turnaround time.
DPT Groundwater Profile Assessment
The objective of the DPT groundwater profile assessment is to evaluate the extent and magnitude of drycleaning contaminants of interest within the on-site property boundary. Terracon anticipates advancing up to 9 DPT groundwater borings and collecting groundwater samples from the following intervals: 15 to 19, 25 to 29, 35 to 39, and 45-49, and 51 to 55, or until refusal at each location. The groundwater samples will be submitted to the laboratory for analysis of full list VOCs. Duplicate groundwater samples are also proposed at GWP locations, as appropriate, for real time analysis by field screening the samples a portable gas chromatograph to better assist with the subsequent selection of actual locations and depth intervals of the GWP activities and field assessment efforts
Based on the number of proposed boring locations and depth intervals, Terracon will collect up to 45 groundwater samples. Additional details are summarized in the SAWP (Terracon, March 30, 2023).
Subtask 3 - Soil Sampling and Modified Active Gas Sampling (MAGS)
Pre-Task Planning will also be performed to prepare for field investigations. Terracon will prepare a site-specific health and safety plan.
Soil Investigation
Terracon will collect soil samples via hand-auger from 8 MAGS locations as described in SAWP
(Terracon 2022). Terracon will collect soil samples from 0.5, 2, 4, 6, 8 and 10 feet (ft) below ground surface (bgs), or to the top of the water table, via hand auger at each soil boring location. Terracon has contracted with GPI-Drill Pro to perform the concrete coring and complete the soil borings.
Terracon personnel will also field screen the soils with an OVA-PID, document the lithology observed at each of these soil boring locations, and will record the Global Positioning System (GPS) coordinates of completed borings. Based on the number of proposed boring locations and depth intervals, Terracon will collect up to 48 soil samples for “full list” Volatile Organic Compounds via EPA Method 8260 and
Synthetic Precipitation Leaching Procedure (SPLP) via EPA 1311. The SPLP samples will remain on hold until the results from the full list VOC results are received. SPLP extraction and VOC analysis will be performed with FDEPs discretion on those samples that report concentrations exceeding the respective
Soil Cleanup Target Level. This additional analysis will be considered a Work Change Directive/Task
Assignment Change Order. The approximate sampling locations, depth intervals, matrices, analytes and laboratory methods, rationale, and screening criteria are summarized in the SAWP (Terracon, 2022). As detailed in the SAWP, all (8) soil borings will be completed as MAGS wells. The MAGS wells are proposed to a depth of 14 ft BGS, with 5-ft of 2-inch diameter 10 slot screen. Each well will be completed flush to ground surface. The interior MAGS wells will be temporarily covered with a neat cement grout at surface to allow for their later use in a Soil Vapor Extraction system. The exterior
MAGS wells will be completed within an 8-inch manhole set within a 2x2 ft pad.
Modified Active Gas Survey (MAGS)
The MAGS test will be performed over a period of 2 days.
Subtask 4 -Monitoring Well Installation and Monitoring Well Sampling
Monitoring Well Installation
As a separate event after review of the soil, MAGS, and GWP data, Terracon will oversee the installation of four (4) monitoring wells. The proposed locations for the monitoring wells are shown in the SAWP (Terracon, March 30, 2023). Terracon will advise with FDEP on the proposed locations, and the monitoring wells will not be installed unless the locations are agreed on by FDEP.
Three of the proposed permanent monitoring wells will be installed to a depth of approximately 25 feet bgs using a track-mounted direct push technology (DPT) rig with auger attachments and constructed with 2” diameter Schedule 40 PVC with 15 feet of 0.01-inch slotted screen. One of the monitoring wells will be installed to a depth of approximately 45 feet bgs using a track-mounted direct push technology (DPT) rig with auger attachments and constructed with 2” diameter Schedule 40 PVC with
10 feet of 0.01-inch slotted screen. Once installed groundwater samples will be collected from the monitoring wells via FDEP Standard Operating Procedures (DEP-SOP-001/01) and analyzed for VOCs via EPA Method 8260 on standard turnround
Monitoring Well Sampling
Groundwater samples will be collected from the one (1) interior well, two (2) piezometers, and the four additional wells, in accordance with the FDEP SOPs. Prior to monitoring well sampling, Terracon will collect depth-to-water measurements. The analytes and laboratory methods are summarized in the SAWP (Terracon, 2022), and will include full list VOCs and PFAS analysis.
As a cost saving measure, no additional mobilization costs will be incurred as the specific purpose survey by SSMC. will begin the same day as groundwater sampling activities.
Subtask 5 –Investigation Derived Waste
Decontamination activities will take place at a designated staging and laydown area. The soil and water IDW will be containerized in 55-gallon drums and staged on-Site at a designated location. It is estimated that 13 drums of IDW will be generated in Subtasks 2, 3 and 4, and the transportation and disposal costs for the drums are included under Subtask 5.
Terracon recommends subcontracting Erwin Remediation, Inc. for IDW transportation and disposal.
Terracon will provide oversight of the IDW pickup, and sign waste manifests as an agent of FDEP.
Subtask 6 –Site Assessment Report
Terracon will prepare a Site Assessment Report that will detail and summarize the groundwater sampling activities, field observations, and results of soil and groundwater analysis and will include data tables and exhibits of groundwater flow and soil and groundwater concentrations. Conclusions and recommendations will include a summary of results and recommendations for future sampling or remedial activities.
SCHEDULE
It is estimated that the drilling activities may be completed within a 10-day period. Due to the expedited schedule while performing work at an active commercial drycleaning facility, Terracon recommends having three Terracon personnel on-site. Daily updates of activities will be uploaded within 24 hours on the Terracon website Compass, to allow FDEP access to the site activities, and groundwater and soil analytical and investigative results. Terracon anticipates the deliverable of site assessment activities within 30 business days of receipt of analytical results.
CLOSING REMARKS
Terracon services will be conducted in accordance with the terms and conditions, contained within DEP
Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.
We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact either of the undersigned at 813-221-0050.
Sincerely, Terracon Consultants, Inc.
Tom Lewis, P.G. for Donna Cline, P.E.
Senior Geologist Senior Environmental Engineer
Attachments: Cost Spreadsheet
Level of Effort
Quotes Subtask 2 thru 5
QUOTES – Subtask 2 and 3
Proposal Date
6/1/2023
Estimate #
15070
Bill To
Terracon 8001 Baymeadows Way, Suite 1, Jacksonville Fl.
Sunshine Plumbing and Gas, LLC 5510 SW 41st Blvd Suite 101 Gainesville, Fl. 32608
352.339.5791 P
P.O. Number Terms Rep F.O.B. Project
Phone #
352-339-5791
Fax #
352-372-7773
E-mail info@sunshineplumbingandgas.com
Web Site www.sunshineplumbingandgas.com
Total
Signature_________________________________
Full Name________________________________
Date____________________________________
By signing I accept this proposal In the event of litigation relating to the subject matter of this Agreement, the prevailing party shall be entitled to receive from the other party its reasonable attorneys' fees and costs.
Item Code DescriptionQuantity Price Each Total
Camera Inspection Camera Inspection of sewer main Provide video if any issues are present.
1 750.00 750.00
5240 NW 34th Boulevard in Gainesville
$750.00
Camera Line Services – sent at 4pm on 05/31/2023
1. First Choice Plumbing - plumbingofgainesville@gmail.com, (352) 377-9447
a. Cost: Disconnected phone, no email back
2. Sunshine Plumbing & Gas - info@sunshineplumbingandgas.com, (352) 339-5791
a. Cost: $750 (use email: Admin2@sunshineplumbingandgas.com)
3. Titletown Plumbing - info@titletownplumbing.com, (352) 318-8782
a. Cost: Labor rate is ($120/hr., camera charge is $75)
4. Separate web-based email interfaces to the following plumbing companies:
a. Premier Plumbing & Leak Detection, LLC
b. Quality Plumbing of Gainesville, Inc.
c. Scarborough Plumbing, LLC
d. JW Freeman Plumbing LLC
e. Fletcher Plumbing, Inc.
Good Afternoon, We are seeking a proposal for a sewer line investigation using a camera down a single drain at a former drycleaning site at 5240 NW 34th Boulevard in Gainesville. We will also need a video with any breaks should we find them. We’d like to receive a proposal by the end of this week, if possible. Please let me know if you have any additional questions. Thank you!
Cline, Donna L Typewriter 3.) personnel of 2, $960+75=$1035
Cline, Donna L Typewriter Low Bid
FDEP Waste Cleanup Program
COMPETITIVE BID WORKSHEET
Project Name/Address: Alpine Cleaners Eric_3987 5240 NW 34th BLVD Gainesville, FL Date: 6/26/23
Detailed description of goods or services required (including total quantity, size, delivery requirements, and all other specifications): Subtask 2
Perform Ground Penatrating Radar and Electromagnetic survey at the subject site address.
Vendor Name: Quantity / Description Trinity GPRS Geoview Contact Name: Matt Yoder Matt Piper Chris Taylor Contact Number: 302-333-2608 720-618-8453 727-209-2334
Written Quote (yes/no): Yes Yes Yes Telephone Quote (yes/no): No No No
Estimated Days Day to Completion 1.00 1.00$ 1.00$ Scope of work see detailed description above 1,700.00$ 1,300.00$ 1,300.00$
Service/Good Cost:
Taxes (7.5%):
Shipping:
Handling/Drop Fees:
TOTAL COST: 1,700.00$ 1,300.00$ 1,300.00$
VENDOR SELECTED: GPRS or Geoview Basis of Selection: Lowest bid
Note: All items costing $1,000 or more will be 3-bid. More than three bids will be necessary if any vendor no-bids a request.
If adequate bids cannot be obtained, a full explanation must be included with this bid form.
Davis, Luke
From: Steve Scruggs <sscruggs@geoviewinc.com> Sent: Wednesday, June 7, 2023 12:50 PM To: Davis, Luke Subject: RE: Request for Proposal - 5240 NW 34th Blvd, Gainesville, FL
I’d budget a full day to clear these borings. $1,300
Let me know if you need anything else.
Thanks!
Steve Scruggs, P.G.
GeoView, Inc.
Direct: 904 261-4933 Cell: 904 556-9595
From: Davis, Luke <Luke.Davis@terracon.com> Sent: Wednesday, June 7, 2023 11:49 AM To: Steve Scruggs <sscruggs@geoviewinc.com> Subject: FW: Request for Proposal - 5240 NW 34th Blvd, Gainesville, FL
Steve, I sent this to Chris Taylor last week and neve received a response. Could you provide a cost estimate for this work?
Thank you.
Luke
From: Davis, Luke Sent: Wednesday, May 31, 2023 4:17 PM To: Chris Taylor <ctaylor@geoviewinc.com> Subject: Request for Proposal - 5240 NW 34th Blvd, Gainesville, FL
Good Afternoon, We are seeking a proposal to clear boring locations at the former Alpine Cleaners site at 5240 NW 34th Boulevard in Gainesville. I have attached the applicable drawings for your response. Please note some locations are within the tenant space that is currently occupied by a professional photographer studio.
We’d like to receive a proposal by the end of this week, if possible. Please let me know if you have any additional questions. Thank you!
Luke A. Davis, P.G.
Group Manager – Environmental Registered Geologist in FL, GA, LA, MS, NC
8001 Baymeadows Way, Suite 1, Jacksonville, Florida 32256 P (904) 900 6494 | D (904) 900 6466 | M (904) 383 2142 luke.davis@terracon.com|Terracon.com
Te
Terracon
June 2, 2023 Submitted By:
Matt Piper
720.618.8453
Matt.piper@gprsinc.com
Client: Terracon
Attn: Luke Davis
Luke.Davis@terracon.com, 904.900.6466
Project: 5240 NW 34th Boulevard, Gainesville, Florida 32605
GPRS appreciates the opportunity to provide this proposal. I encourage you to visit our website (www.gprsinc.com) and contact any of the numerous references listed. Our insurance certificate and W-9 can also be downloaded here. Please feel free to contact me if you have any questions, or if you need additional information. Visit www.simspec.org for an overview of our industry-leading best practices that will be applied to this project.
SCOPE OF WORK
We understand the scope to be to search for underground utilities within a radius of approximately 10’ around up to 27 soil boring locations. We will attempt to trace any utilities for which there are structures visible from the work area. Utilities will be marked on the surface using paint, flags, or other appropriate means. The client will be responsible to provide drawings or notify GPRS of any utilities known to be entering the work area for which there are no apparent surface features or structures that are visible from the work area. The areas should be laid out, marked, and cleared of obstructions prior to our arrival in order to avoid additional charges.
EQUIPMENT
• Underground Scanning GPR Antenna. The antenna frequencies range from 250 MHz-450 MHz is mounted in a stroller frame which rolls over the surface. The surface needs to be reasonably smooth and unobstructed in order to obtain readable scans. Obstructions such as curbs, landscaping, and vegetation will limit the feasibility of GPR. The data is displayed on a screen and marked in the field in real time. The total depth achieved can be as much as 8’ or more with this antenna but can vary widely depending on the types of materials being scanned through. Some soil types such as clay may limit maximum depths to 3’ or less. As depth increases, targets must be larger in order to be detected and non-metallic targets can be especially difficult to locate. Depths provided should always be treated as estimates as their accuracy can be affected by multiple factors. For more information, please visit: Link
• Concrete Scanning GPR Antenna. The antenna is handheld and rolls over the surface. The antenna needs a reasonably smooth, unobstructed surface for scanning and is not able to scan within 2”-4” of obstructions such as walls and metal tracks unless they are removed prior to our work. The data is displayed on a screen during the scanning and marked on the surface in real time. The total depth achieved can be as much as 18” or more with this antenna but can vary widely depending on the types of materials being scanned through and other factors such as the spacing of the reinforcing. Depth accuracy depends on the ability to obtain an accurate depth calibration for the concrete. No harmful radiation is emitted and the work can be performed at any time with people in close proximity. For more information, please visit: Link
• Electromagnetic Pipe Locator. The EM locator can passively detect the signals from live AC power or radio signals travelling along some conductive utilities. It can also be used in conjunction with a transmitter to connect directly to accessible, metallic pipes, risers, or tracer wires. A current is sent through the pipe or tracer wire at a specific frequency and the resulting signal can then be detected by the receiver. A utility’s ability to be located depends on a variety of factors including access to the utility, conductivity, grounding, interference from other utilities, and many others. Depths provided should always be treated as estimates as their accuracy can be affected by multiple factors. For more information, please visit: Link
• Traceable Rodder. The rodder has a copper wire encased in fiberglass. The line is pushed through accessible pipes before placing a current on the wire and the signal is then traced from the surface. The maximum traceable depth is 10’ depending on the soil conditions and the maximum distance is 200’. The line can be pushed through a pipe with direct access such as a sewer line at a cleanout or a storm drain catch basin. It may not be able to be pushed through deeper pipes within manholes. Electrical conduits will not be accessed by GPRS. The signal cannot be located through metallic pipes. For more information, please visit: Link
• GPS. This handheld GPS unit offers accuracy down to 4 inches, however, the accuracy achieved will depend on the satellite environment at the time of collection and should not be considered to be survey-grade. Features can be collected as points, lines, or areas and then exported as a KML/KMZ or overlaid on a CAD drawing. For more information, please visit: Link
Soil Borings+ http://www.gprsinc.com/ https://www.gp-radar.com/downloadable-forms-and-certificate-of-insurance http://www.simspec.org/ https://www.gp-radar.com/350-400-mhz-gpr-antenna https://www.gp-radar.com/1600-2000-2300-2700-MHz-GPR-Antenna https://www.gp-radar.com/rd-8100-spec-sheet https://www.gp-radar.com/Duct-Hunter-Traceable-Rodders.html https://www.gp-radar.com/gprs-data-sheets
MAP OF SCAN AREA
PROJECT COSTS
SERVICE DESCRIPTION PRICE
SCANNING/FIELD MARKINGS Described on Page 2 $1,300
MOBILIZATION Included Included
JOB SUMMARY PDF document with brief description of equipment used, findings, limitations, site photos sent at conclusion of every job.
Included
GPS MAP Findings will be collected with GPS and displayed with an aerial image background.
Results are not survey-grade accuracy. See example: Link Included
TOTAL *$1,300
This price assumes that we will be given access to perform the work during normal, weekday business hours (7am-5pm). Hours outside of these times are typically billed at time and a half.
As-builts and any other applicable drawings should be made available to GPRS prior to the project if possible.
A thorough utility search can only be completed if GPRS is given access to all utility structures, interior and exterior. This service is never a replacement for the use of the state One Call system (811).
All of our technicians have OSHA-10 safety training or greater. Site-specific safety training is not included in this quote. Please notify us if this project requires additional safety training.
These rates assume that there are no certified payroll requirements. GPRS has not been notified of any PLA, DIR, or Certified Payroll requirements. If GPRS receives notice that any of these conditions exist, there will be additional costs
This proposal is subject to the General Terms and Conditions for Services of Ground Penetrating Radar Systems, LLC posted at Link (the “Terms and Conditions”) and is hereby incorporated by reference into and made a part of this proposal. Customer acknowledges it has read and agrees to be bound by such Terms and Conditions. In the event of any conflict between the terms of this proposal and the Terms and Conditions, the Terms and Conditions will prevail. Customer also acknowledges that Ground Penetrating Radar Systems, LLC may, from time to time and at its discretion, modify the Terms and Conditions and Customer agrees to be bound by such Terms and Conditions as modified.
PROPOSAL-SPECIFIC TERMS & CONDITIONS
1. Customer agrees to meet and perform all requirements described in this document and has fully read and understands all items listed within this document.
2. It is the customer’s responsibility to prepare the site for scanning, including clearly identifying areas to be scanned, securing access to all areas required for scanning, and keeping these areas clear and free of obstructions. Delays caused by customer’s failure to do so may result in an increased price.
3. GPRS does not conduct an investigation, analysis, or interpretation of soil composition, soil/concrete conditions, or geophysical, geological, engineering, or land surveying information. Customer acknowledges it understands that we are merely reporting retrieved data and that we do NOT provide geophysical, geological, engineering, or land surveying services. Customer should contact a professional in those fields if such services are needed.
4. If any work to be performed is within a road or street, unless specifically included by GPRS within this proposal, it is the customer’s responsibility to provide adequate traffic control to allow GPRS’ personnel to safely and efficiently work in the road/street.
5. If this proposal is not accepted within 90 days of the date shown on Page 1 then the pricing may be subject to review.
6. If for some reason the technician arrives on site and the work is cancelled there will be a charge of…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .