About this file

This document is a Task Assignment (TA) under Contract Number HW687 between the State of Florida Department of Environmental Protection (FDEP) and Terracon Consultants, Inc. The task assignment, numbered BF01A, was executed on May 20, 2022, with an effective completion date of August 19, 2022. The work is being conducted at the Former Rose Printing Company site located at 2503 Jackson Bluff Road, Tallahassee, Leon County, Florida (Site ID ERIC_18047). Services are being funded through federal funds from the State & Tribal Response Program (SRP) cooperative agreement administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA). The Department Project Manager is Megan Johnson (850.245.8994), and the Contractor's Project Manager is Tom Lewis (850.692.7194).

The task assignment authorizes Terracon to conduct a Supplemental Site Assessment comprising four subtasks: (1) Project Management at a cost of $1,252.52; (2) Development of a Quality Assurance Project Plan (QAPP), Workplan, and Health and Safety Plan (HASP) at a cost of $2,652.73, with deliverable due June 1, 2022; (3) Groundwater sampling and analysis at fourteen locations using direct push technology (DPT), including deeper aquifer sampling to approximately 45 feet below ground surface, with laboratory analysis for BTEX, PAHs, lead, and TRPH at a cost of $14,235.49, with deliverable due June 24, 2022; and (4) Preparation of a Supplemental Site Assessment Report at a cost of $3,639.06, with final deliverable due July 18, 2022. The total Task Assignment value is $21,779.80 on a fixed unit rate basis. Invoicing is structured in three phases corresponding to departmental approval of each deliverable component.

View the file

Other files

File Type Posted
CN-370000-HW687-BF01B.pdf PDF
CN-370000-HW687-BF02A.pdf PDF
CN-370000-HW687-BF04A.pdf PDF
CN-370000-HW687-BF04ACO3.pdf PDF
CN-370000-HW687-BIL01B.pdf PDF
CN-370000-HW687-BIL02B.pdf PDF
CN-370000-HW687-BIL03B.pdf PDF
CN-370000-HW687-BIL1BCO2.pdf PDF
CN-370000-HW687-BIL2CCO2.pdf PDF
CN-370000-HW687-CSS02.pdf PDF
CN-370000-HW687-CSS03.pdf PDF
CN-370000-HW687-DC002A.pdf PDF
CN-370000-HW687-DC002G.pdf PDF
CN-370000-HW687-DC006C.pdf PDF
CN-370000-HW687-DC008B.pdf PDF
CN-370000-HW687-DC008D.pdf PDF
CN-370000-HW687-DC009B.pdf PDF
CN-370000-HW687-DC010C.pdf PDF
CN-370000-HW687-DC012A.pdf PDF
CN-370000-HW687-DC014B.pdf PDF
CN-370000-HW687-DC014D.pdf PDF
CN-370000-HW687-DC014H.pdf PDF
CN-370000-HW687-DC015D.pdf PDF
CN-370000-HW687-DC016C.pdf PDF
CN-370000-HW687-DC01ACO9.pdf PDF
CN-370000-HW687-DC021A.pdf PDF
CN-370000-HW687-DC021C.pdf PDF
CN-370000-HW687-DC022A.pdf PDF
CN-370000-HW687-DC023B.pdf PDF
CN-370000-HW687-DC023D.pdf PDF
CN-370000-HW687-DC024B.pdf PDF
CN-370000-HW687-DC024E.pdf PDF
CN-370000-HW687-DC024F.pdf PDF
CN-370000-HW687-DC027A.pdf PDF
CN-370000-HW687-DC028A.pdf PDF
CN-370000-HW687-DC028D.pdf PDF
CN-370000-HW687-DC029C.pdf PDF
CN-370000-HW687-DC02ACO1.pdf PDF
CN-370000-HW687-DC02HCO2.pdf PDF
CN-370000-HW687-DC030A.pdf PDF
CN-370000-HW687-DC031A.pdf PDF
CN-370000-HW687-DC035A.pdf PDF
CN-370000-HW687-DC037A.pdf PDF
CN-370000-HW687-DC03CCO2.pdf PDF
CN-370000-HW687-DC044A.pdf PDF
CN-370000-HW687-DC045B.pdf PDF
CN-370000-HW687-DC049A.pdf PDF
CN-370000-HW687-DC054A.pdf PDF
CN-370000-HW687-DC056A.pdf PDF
CN-370000-HW687-DC057A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW687

BF01A Completion August 19, 2022

The Department approves this Task Assignment (TA) based upon the Cost Proposal and Level of Effort (CP/LOE) for the completion of a Supplemental Site Assessment submitted to the Department on May 18, 2022, revised May 19, 2022 by Terracon Consultants, Inc., for the below referenced site. The final deliverable will be a Supplemental Site Assessment Report received by the Department no later than July 18, 2022.

Megan Johnson 850.245.8994 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Terracon Consultants, Inc.

Terracon Consultants, Inc.

Tom Lewis 850.692.7194

ERIC_18047

2503 Jackson Bluff Road, Tallahassee, Leon County

Former Rose Printing Company

✔ $ 21,779.80

$ 21,779.80

Scope of Work

Donna Cline, P.E.

Senior Remediation Engineer

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2022.05.20 14:43:05 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

QAPP/Work Plan and HASP 06/01/2022

Field notes, photographic log, chain of custody, groundwater sampling logs 06/24/2022

Project Management and Supplemental Site Assessment Report 07/18/2022

Department approval of QAPP/ Work Plan and HASP (Subtask 2) $ 2,652.73

Department approval of field notes, photographic log, chain of custody, and groundwater sampling logs (Subtask 3) $ 14,235.49

Department approval of Project Management and Supplemental Site Assessment Report (Subtasks 1 and 4) $ 4,891.58

$ 21,779.80

HW687

BF01A

www.FloridaDEP.gov

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Terracon Consultants, Inc., HW687 Contract File

FROM: Megan Johnson, Contract Manager

DATE: May 20, 2022

SUBJECT: Negotiation Summary – SRP18 Task Assignment (TA) BF01A

Former Rose Printing Company – Site ID # ERIC_18047 Supplemental Site Assessment Activities

This TA is intended for conducting Supplemental Site Assessment activities at the Former Rose Printing Company site, located at 2503 Jackson Bluff Road, Tallahassee, Leon County, Florida 32304. The services under this task are being conducted using federal funds from the State & Tribal Response Program (SRP) cooperative agreement that is administered by the Department on behalf of the U.S. Environmental Protection Agency (EPA).

Subtask 1: Project Management This subtask is a percentage of the overall project fees and has been negotiated as a contract rate. It includes project management, overhead, general and administrative, and fringe. The agreed upon cost of this subtask is $1,252.52.

Subtask 2: QAPP/Work Plan and Health and Safety Plan In accordance with an EPA directive, this subtask includes the completion of a Quality Assurance Project Plan (QAPP)/Work Plan and a Health and Safety Plan (HASP). The QAPP/Work Plan will provide a brief summary of the scope of work, tables and figures showing the proposed sampling locations, and laboratory and field quality assurance measures and procedures. The agreed upon cost of this subtask is $2,652.73.

Subtask 3: Supplemental Site Assessment Activities Under this subtask, Terracon will conduct direct push technology (DPT) groundwater profiling, sampling at fourteen select locations on site. One boring inside the building and one boring outside the building will additionally be advanced to approximately 45 feet below ground surface for collection of deeper aquifer sample for vertical profiling. Collected groundwater samples will be laboratory analyzed for benzene, toluene, ethylbenzene and xylene (BTEX) by EPA Method 8260, polycyclic aromatic hydrocarbons (PAHs) by EPA Method 8270, lead by EPA Method 6010, and total recoverable petroleum hydrocarbons (TRPH) by FL PRO. The agreed upon cost of this subtask is $14,235.49.

Subtask 4: Supplemental Site Assessment Report A Supplemental Site Assessment Report will be prepared detailing the field and laboratory results. This report will also include figures, maps, tables, and conclusions and recommendations for any future work. The agreed upon cost of this subtask is $3,639.06.

http://www.floridadep.gov/

Negotiation Summary – Task Assignment (TA) BF01A Former Rose Printing Company

ERIC_18047

May 20, 2022 www.FloridaDEP.gov

Summary The Department’s SRP Contract Manager and Terracon’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $21,779.80. Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) Form and CP/LOE narrative provided by Terracon on May 18, 2022, revised May 19, 2022 and the Task Assignment Form for BF01A prepared by the Department. The final deliverable must be received by the Department no later than July 18, 2022.

http://www.floridadep.gov/

3559 Timberlane School Rd

Tallahassee, FL 32312

P (850) 692-7185

F (850) 692-7186

Terracon.com

May 19, 2022

Florida Department of Environmental Protection

Waste Cleanup Program-Waste Management Division

2600 Blair Stone Road

Tallahassee, Florida 32399-2400

Attn: Ms. Megan R. Johnson, Environmental Consultant

Brownfields and CERCLA Site Screening Section

E: Megan.R.Johnson@floridadep.gov

W: 850-245-8994

Re: Proposal for Supplemental Site Assessment

Former Rose Printing Company

2503 Jackson Bluff Road

Tallahassee, Leon County, Florida

Terracon Proposal No. PHF227047

Task # BF01A

Dear Ms. Johnson:

Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the

Florida Department of Environmental Program (FDEP) Waste Cleanup Section to conduct a

Supplemental Site Assessment for the Former Rose Printing Company facility located at 2503 Jackson

Bluff Road in Tallahassee, Florida. These activities will be performed as approved by both FDEP and the U.S. Environmental Protection Agency (U.S. EPA) for utilizing Targeted Brownfield Assessment/Site

Specific Activities (TBA/SSA) federal funding administered by FDEP.

Scope of Services

(see Section 2.0 of attached

Proposal Detail)

◼ Develop a Workplan / Quality Assurance Project Plan (QAPP) and

Health and Safety Plan (HASP) and two (2) days of direct push groundwater profiling inside building and north of building at fourteen

(14) locations.

◼ Review data and prepare a Supplemental Site Assessment Report with tables and concentration exhibits sealed by a Professional

Geologist.

See attached LOE for details

Schedule

(see Section 4.0 of attached

Proposal Detail)

Deliverable of Workplan and QAPP within 5 business days of authorization;

Deliverable of field notes, photolog, and chain of custody within 2 business days of completion of field work;

Deliverable Supplemental Site Assessment within 20 business days following receipt of laboratory results.

Compensation

(see Section 4.0 of attached

Proposal Detail)

See attached CEF for details.

mailto:Megan.R.Johnson@floridadep.gov

Proposal for Supplemental Site Assessment and Preparation of Report

Former Rose Printing Company ■ Tallahassee, FL

May 19, 2022 ■ Terracon Proposal No. PHF227047

PROJECT INFORMATION

Prior to being redeveloped as a printing shop in the late 1950s, the site was occupied by the Dale

Mabry Army Airfield during the 1940s and 1950s to train pilots and air crews during World War II.

During site operations as Dale Mabry Army Airfield, the area of the site served as location for bunkered underground storage tanks (USTs) that transported fuel in an underground pipeline to a fuel depot adjacent to a runway northwest of the site.

According to the Final Site Assessment Report - Site Assessment and Pipeline Abandonment Former

Dale Mabry Army Airfield Tallahassee, Leon County, Project No. I04FL0117-01, dated May 2016, prepared by Aerostar SES, LLC (Aerostar), this specific area of the fueling operations was identified as

“Site B”. Site B consisted of thirteen (13) 25,000-gallon USTs. It is believed that the north portion of this former tank area is north of the former Rose Printing Building and under the northwest corner of the former Rose Printing Building. Prior assessments performed at the site confirmed exceedances above the FDEP Cleanup Target Levels for soil and groundwater have been identified in this area. The reports reviewed suggest that the USTs and the pipeline were abandoned sometime prior to the site being occupied by Rose Printing. Only benzene, toluene, ethylbenzene, xylenes (BTEX) and lead were analyzed for in this prior groundwater assessment.

In a May 19, 2017 letter from FDEP to the U.S. Army Corp of Engineers (USACE), FDEP did not concur with the USACE recommendation for Site B and indicated the USACE “needs to conduct additional assessment activities at the site, and fully characterize and define the site’s groundwater plume, before the Department can determine if Site B qualifies for non-eligibility status”. This investigation was not performed.

In the fall of 2019, utilizing funds available from their US EPA Community Brownfield Assessment grant, the City of Tallahassee (City) contracted Terracon to perform Phase I and II Environmental Site

Assessment (ESA) activities prior to acquiring the site for redevelopment. Direct push sampling inside the building indicated significant groundwater impacts extended south of the former tank area under the building.

On March 3, 2022, FDEP approved the City’s application for further assessment and cleanup of this former airfield site. This following scope has been prepared to provide both an update to current onsite monitoring well data as well as perform additional horizontal and vertical extent profiling of the impacts to groundwater underneath the building and on the north portion of the site. The goal of this study is to provide an update to the original May 19, 2017 request by FDEP to the USACE and serve as an initial remedial planning tool for additional assessment and cleanup approaches to be implemented after the building’s demolition later in 2022.

SCOPE OF SERVICES

Based on prior discussions on phone and email, the proposed scope of services consists of four subtasks involving Project Management, developing a Workplan / QAPP and HASP, two-days of direct push technology (DPT) groundwater profiling, and producing a Supplemental Site Assessment Report:

Subtask Description

Subtask 1: Project Management This scope is provided for in the template worksheets

Subtask 2:

Workplan/QAPP/HASP

Develop a Workplan and Quality Assurance Project Plan and Health and

Safety Plan prior to field work for approval by FDEP

Subtask 3. Groundwater

Sampling and Analysis

▪ Mobilization to the site for two consecutive days.

▪ Supervise DPT groundwater sampling at eight (8) locations north of the building and six (6) locations within the building (estimated water is 20 feet below ground surface). One (1) boring inside the building and one (1) boring outside the building will be advanced to approximately 45 feet below ground surface for collection of deeper aquifer sample for vertical profiling.

▪ Collected groundwater samples will be laboratory analyzed for benzene, toluene, ethylbenzene and xylene (BTEX) by EPA Method

8260, polycyclic aromatic hydrocarbons (PAHs) by EPA Method

8270, lead by EPA Method 6010 and Total Recoverable Petroleum

Hydrocarbons (TRPH) by FL PRO. The analysis will be performed using a National Environmental Laboratory Accreditation Conference

(NELAC) approved laboratory.

Subtask 4. Supplemental Site

Assessment Report

▪ Prepare a Supplemental Site Assessment Report with site history, methodology, conclusions, recommendations, tables, sample locations and concentration exhibits, sealed by a Professional

Geologist

SCHEDULE

It is estimated that the workplan, QAPP, and HSP can be submitted within five days of authorization and the DPT groundwater profiling can be implemented by mid-June 2022. A Supplemental Site

Assessment Report can be issued within 20 business days of receipt of laboratory analytical results.

CLOSING REMARKS

Terracon services will be conducted in accordance with the terms and conditions, contained within DEP

Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.

We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact either of the undersigned at 850-692-7185.

Sincerely, Terracon Consultants, Inc.

for Donna Cline, P.E. Tom Lewis, P.G.

Senior Remediation Engineer Principal

Attachments: Exhibit 1

Cost Spreadsheet

Level of Effort

Drill Bids

EXHIBIT 1 – WELLS AND PROPOSED SAMPLING LOCATIONS

FDEP COST ESTIMATE

Contractor: Terracon

Date: 5/19/2022 Task #: BF01A SubTask 1 Project Management SubTask 6

Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7 Activity/Phase: TBA and Reporting SubTask 3 Groundwater Sampling and Analysis SubTask 8

Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9 SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$70.19 Project Manager Tom Lewis 6 6.0 $20.50 Administrative Ashley Miller 1 1 0 0 0 0 0 0 0 0 $69.71 Brownfield Consultant Belinda Richard 4 3 0 1 0 0 0 0 0 0 $20.50 CADD Specialist Oscar Encalada 4 0 0 4 0 0 0 0 0 0 $0.00 Data Analyst & Visualization Specialist 0 0 0 0 0 0 0 0 0 0 $0.00 Environmental Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Field Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Field Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 GIS Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Principal Consultant 0 0 0 0 0 0 0 0 0 0 $0.00 Project Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Project Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$26.92 Project Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Engineer 0 0 0 0 0 0 0 0 0 0

$70.19 Senior Geologist Tom Lewis 4 1 0 3 0 0 0 0 0 0 $0.00 Senior GIS Analyst 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$45.19 Senior Scientist Sid O'Neal 35 1 18 16 0 0 0 0 0 0 $0.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0

$21.63 Staff Scientist Tommy Grey 45 25 14 6 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 99 6 31 32 30 0 0 0 0 0 0

Direct Labor $3,635.32 $418.22 $885.76 $1,116.24 $1,215.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $4,216.98 $485.14 $1,027.48 $1,294.84 $1,409.52 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $2,045.24 $235.29 $498.33 $628.00 $683.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $9,897.54 $1,138.65 $2,411.57 $3,039.08 $3,308.24 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 1

FDEP COST ESTIMATEContractor: Terracon Date: 5/19/2022

Task #: BF01A SubTask 1 Project Management SubTask 6 Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7

Activity/Phase: TBA and Reporting SubTask 3 Groundwater Sampling and Analysis SubTask 8 Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $300.00 $0.00 $300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $300.00 $0.00 $300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $4,335.00 $0.00 $4,335.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $200.00 $0.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $4,535.00 $0.00 $4,535.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $453.50 $0.00 $453.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $4,988.50 $0.00 $4,988.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $4,336.00 $0.00 $4,336.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $140.00 $0.00 140.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $4,476.00 $0.00 $4,476.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $70.00 $0.00 $70.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $80.00 $0.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $978.00 $0.00 $978.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,128.00 $0.00 $1,128.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $20,790.04 $1,138.65 $2,411.57 $13,931.58 $3,308.24 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $989.76 $113.87 $241.16 $303.91 $330.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $21,779.80 $1,252.52 $2,652.73 $14,235.49 $3,639.06 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Former Rose Printing SUBTASK 2: QAPP and HASP

PROPOSAL NO. PHF227047

DATE: 5/19/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

HASP

Senior Scientist SO 1.00 Staff Scientist TG 3.00

QAPP

Staff Scientist TG 22.00 Senior Geologist TL 1.00

Brownfields Consultant BR QA/QC and Review 3.00

Admin Admin AM Project files set-up 1

TOTAL LABOR 31

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Review Prepare Health and Safety Plan

Prepare QUAPP Review

SUBTASK 3: GW Sampling

PROPOSAL NO. PHF227047

DATE: 5/19/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning and Groundwater Sampling Senior Scientist SO 3.00

Staff Scientist TG 2 days loading/unload mobilization 2.00 Senior Scientist SO 2 days loading/unload mobilization 2.00 Staff Scientist TG Two days of DPT groundwater sampling oversite 14 locations 11.00 Senior Scientist SO Two days of DPT groundwater sampling oversite 14 locations 11.00

Coordinate IDW T&D Senior Scientist SO 2.00 Field Scientist TG 1.00

TOTAL LABOR 32

VEHICLE TYPE RATE UNIT USEAGE

Truck (sampling) 120 day 2 $240.00 Truck (IDW pickup) 120 day 0.5 $60.00

TOTAL VEHICLE $300.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin Remediation IDW Disposal 100.00$ each 2 $200.00 JSA DPT 4,335.00$ each 1 $4,335.00

TOTAL $4,535.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Aromatic VOCs EPA 8260D 60.00$ 16 0 0 $960.00

PAHS EPA 8270 110.00$ 16 $1,760.00

TRPH FL PRO 88.00$ 16 $1,408.00

Lead EPA 6010 13.00$ 16 $208.00 Sample Shipping Large Cooler (2 day) 70.00$ 2 $140.00

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

Prepare waste characterization/Generator Profile Coordinate IDW T&D: Meet transporter to unlock secure area for pickup

SUBTASK 2: GW Sampling

PROPOSAL NO. PHF227047

DATE: 5/19/2022

Sample Shipping -$ 0 $0.00

TOTAL LAB $4,476.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Shallow groundwater sampling kit290.00$ day 2 $580.00 Tubing, HDPE 0.30$ ft 430 $129.00 Tubing, silicon (3/16 x 3/8) 3.00$ ft 23 $69.00 PPE 35.00$ day 2 $70.00 Expendables 40.00$ day 2 $80.00 Multimeter (YSI ProPlus) 105.00$ day 0 $0.00 Turbidimeter (Hach) 27.00$ day 0 $0.00 water level indicator 25.00$ day 0 $0.00 Pump, peristaltic 30.00$ day 0 $0.00 Lock, key operated 7.00$ ea 0 $0.00 55-gallon drum, new 100.00$ drum 2 $200.00

$0.00

TOTAL EQUIPMENT $1,128.00

SUBTASK 3: GW Sampling

PROPOSAL NO. PHF227047

DATE: 5/19/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning Senior Scientist SO 1.00 Senior Geologist TL 1.00

Deliverable Field Scientist TG 6.00 Senior Scientist/Geologist SO Review and Summarize Water Quality Parameters 3.00 Senior Scientist/Geologist SO Review and Summarize Groundwater Analytical Results 2.00 Senior Scientist SO 10.00

QA/QC and Review Brownfields Consultant BR QA/QC 1.00 Senior Scientist/Geologist TL Review and Seal Report 2.00

CADD

Project Scientist OE Create updated exhibits 4.00

TOTAL LABOR 30.00

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE -$

PER DIEM STAFF RATE UNIT USEAGE

$0.00 -$

TOTAL PER DIEM -$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL -$

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS

TOTAL LAB -$

* No charge for trip blanks, only one duplicate

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT -$

Review data Review data

Data reduction/evaluation/Tables

Prep of Report

File details come from the government source that posted it. Updated .