CN-370000-HW687-DC023B.pdf
PDF 1 MB Posted
- Contract number
- HW687
- Issued by
- Florida
About this file
This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Terracon Consultants, Inc. for environmental remediation work at the Dadeland Cleaners site (ERIC_4461) located at 8695 S. Dixie Highway in Miami, Dade County, Florida. The TA is authorized under Contract Number HW687 and is designated as TA Number DC023B. The Department's Project Manager is Dean Cox (850-245-8969), and the Contractor's Project Manager is Donna Cline (813-321-0340). The TA became effective on March 22, 2023, with a completion date of August 31, 2023.
The scope of work authorizes costs for the development of an Interim Source Removal (ISR) Workplan for a Soil Vapor Extraction (SVE) system. The deliverables include a comprehensive ISR Workplan incorporating a summary of existing Site Assessment Report data, a FDEP Remedial Action Plan (RAP) checklist, contaminant mass calculations, system design and construction drawings, startup and operations and maintenance (O&M) procedures, construction schedule, and cost estimates. The workplan and drawings must be signed and sealed by a Professional Engineer. The total TA value is $8,260.24 on a fixed unit rate basis, representing a 16 percent reduction from the original proposal price of $9,792.36. The work was negotiated to reflect a lower cost while maintaining scope. Payment is contingent upon FDEP approval of the completed ISR Workplan with all required components. The original due date was May 31, 2023, with the final TA completion date set for August 31, 2023.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW687
DC023B Completion August 31, 2023
This TA authorizes costs for an Interim Source Removal (ISR) Workplan for a Soil Vapor Extraction (SVE) system. The total cost of this TA is $8,260.24 and this entire cost is fixed unit rate.
Dean Cox 850-245-8969 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Terracon Consultants, Inc.
Terracon Consultants, Inc.
Donna Cline 813-321-0340
ERIC_4461
8695 S. Dixie Highway, Miami
Dadeland Cleaners (former)
✔ $ 8,260.24
$ 8,260.24
Scope of Work
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.03.22 11:51:50 -04'00'
N/A
Cline, Donna L Typewriter Donna Cline
Sr. Remediation Engineer
03/22/23
Cline, Donna L Typewriter
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
ISR Workplan, with SAR summary, RAP checklist, contaminant mass calcs, system design/drawings and start-up & O&M procedures, and schedule (Subtask 1 Project Management and Subtask 2 ISR Workplan & Construction Drawings).
05/31/2023
DEp approval of ISR Workplan, with SAR summary, RAP checklist, contaminant mass calcs, system design/drawings and start-up & O&M procedures, and schedule (Subtask 1 Project Management and Subtask 2 ISR Workplan & Drawings).
$ 8,260.24
$ 8,260.24
HW687
DC023B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: HW687 Contract File FROM: Dean Cox, Contract Manager SUBJECT: DC023B Dadeland Cleaners (ERIC_4461) ISR (SVE) Workplan
DATE: 3/21/23
This TA authorizes costs for an Interim Source Removal (ISR) Workplan for a Soil Vapor Extraction (SVE) system. The total cost of this TA is $8,260.24 and this entire cost is fixed unit rate. This TA was negotiated - the total cost is $1,532.12 or 16% less than originally proposed. Site access was confirmed current.
The purpose of this TA is the creation and submittal of an SVE ISR Workplan. SVE is being installed based on SA soil (13 ug/kg max) and MAGS (2.25 mg/m3 max) data.
The WSCS PG’s SAR approval memo indicates some vadose zone impacts beneath the former drycleaner and recommends engineering review regarding ISR. The WSCS PE subsequently indicated SVE ISR was needed, and approved the associated PRA form.
FDEP COST ESTIMATE
Contractor: Terracon
Date: 3/21/2023 Task #: HW687 DC023B SubTask 1 Project Management SubTask 6
Site: Dadeland Cleaners ERIC_4461 SubTask 2 ISR Workplan and Construction Drawings SubTask 7 Activity/Phase: ISR Workplan and Construction Drawings SubTask 3 SubTask 8
Project Manager: Dean Cox SubTask 4 SubTask 9 SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$48.08 Project Manager Shawn Ouellette 6.60 6.60 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$31.25 CADD Specialist Chelsea Fugate 13.00 13.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Environmental Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$64.50 Senior Engineer Donna Cline 10.00 10.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$40.87 Staff Engineer Michael Mui 34.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 63.60 6.60 57.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $2,758.14 $317.31 $2,440.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 116.00% $3,199.44 $368.08 $2,831.36 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $1,551.73 $178.52 $1,373.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $7,509.31 $863.91 $6,645.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 1
FDEP COST ESTIMATEContractor: Terracon Date: 3/21/2023
Task #: HW687 DC023B SubTask 1 Project Management SubTask 6 Site: Dadeland Cleaners ERIC_4461 SubTask 2 ISR Workplan and Construction Drawings SubTask 7
Activity/Phase: ISR Workplan and Construction Drawings SubTask 3 SubTask 8 Project Manager: Dean Cox SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $7,509.31 $863.91 $6,645.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $750.93 $86.39 $664.54 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $8,260.24 $950.30 $7,309.94 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Dadeland Cleaners, Inc., ERIC_4461 SUBTASK 2: ISR Workplan and Construction Drawings
PROPOSAL NO. PHD237021
DATE: 3/21/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Prepare ISR Plan and Construction Drawings, Signed and Sealed by a Professional Engineer
Senior Scientist/Engineer MM Evaluate MAGS and prepare SVE remediation design calculations 6 Senior Scientist/Engineer MM Prepare ISR workplan 8 Senior Scientist/Engineer MM Develop summary tables 1 Senior Scientist/Engineer MM Develop Exhibits/Construction Drawings (trench details, SVE cross sections, treatment 10 system layout, P&ID, electrical detail, equipment list, and components) Senior Scientist/Engineer MM Evaluate remedial equipment to be used and determine design details after discussions with 4 owner/tenant and power company Senior Scientist/Engineer MM Prepare FDEP RAP Checklist 2 Senior Scientist/Engineer MM Discussions / technical pre-design meeting with DEP 3
Senior Engineer DC Evaluate calculations 2 Senior Engineer DC Evaluate ISR Workplan written portion 2 Senior Engineer DC Evaluate for completion Exhibits/Construction Drawings 3 Senior Engineer DC Sign and seal ISR Workplan and Construction Drawings 1 Senior Engineer DC Discussions / technical pre-design meetings with CVS and DEP 2
Cadd Support CF ISR Workplan - Create and prepare final Exhibits 4 Cadd Support CF Preparation of Construction Drawings 9
Personnel: MM DC CF Hours: 34.00 10.00 13.00
TOTAL LABOR 57
5463 West Waters Avenue
Tampa, FL 33634
P (813) 221-0050 F (813) 221-0051
Terracon.com
March 9, 2023
Florida Department of Environmental Protection Waste Cleanup Program, Waste Management Division 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Attn: Mr. Dean Cox, Environmental Consultant E: Dean.Cox@FloridaDep.gov W: 850-245-8969 M: 727-686-6502
Re: Proposal for Interim Source Removal Workplan and Construction Drawings for Soil
Vapor Extraction System Dadeland Cleaners, Inc.
8695 S. Dixie Highway Miami, Dade County, Florida 33143
ERIC_4461
Task Assignment HW687 DC023B Terracon Proposal No. PHD237021
Dear Mr. Cox:
Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the Florida Department of Environmental Program (FDEP) Waste Cleanup Section to prepare an Interim Source Removal (ISR) Workplan for a Soil Vapor Extraction (SVE) System for the Dadeland Cleaners (Former) (ERIC_4461) located at 8695 S. Dixie Highway in Miami, Dade County, Florida.
Evaluate existing Modified Active Gas Survey (MAGS) results in the Site Assessment Report (SAR) Revision 1.0 prepared by Tetra Tech.
Utilize the existing MAGS wells and the MAGS test data collected in the SVE system design.
Prepare an ISR Workplan, to include a brief summary of the results from the SAR Revision 1 (Tetra Tech, Inc., 2021), the FDEP RAP checklist, calculations for contaminant mass, system design and emissions treatment, procedures for system startup and routine operation and maintenance (O&M), anticipated construction schedule, and general cost estimate for construction and O&M; and Preparation of Construction Drawings.
See attached LOE for details
Schedule Deliverable is an ISR Workplan and Construction Drawing, completed by May 30, 2023.
Compensation See attached CEF for details.
mailto:Dean.Cox@FloridaDep.gov
Proposal for ISR Workplan and Construction Drawings Dadeland Cleaners, ERIC_4461 | Miami, FL March 9, 2023 | Terracon Proposal No. PHD237021
DELIVERABLES
The ISR Workplan will provide an SVE system design based on available MAGS data. The ISR Workplan will provide a brief summary of results from the Site Assessment Report Revision 1.0 (Tetra Tech, Inc, June 24, 2021) to support the design basis of the proposed SVE system. The ISR Workplan will also include FDEP RAP Checklist; calculations for contaminant mass, system design and emissions treatment; procedures for system startup and routine operation and maintenance (O&M); anticipated construction schedule; general cost estimate for construction and O&M; and Construction Drawings.
The ISR Workplan and the Construction Drawings will be signed and sealed by a Professional Engineer.
SCHEDULE
The ISR Workplan will be completed within 20 – 30 business days of receipt of Task Assignment, with a suggested due date of May 30, 2023 based on Task Authorization within one week of the submitted proposal.
CLOSING REMARKS
Terracon services will be conducted in accordance with the terms and conditions, contained within DEP Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.
We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact either of the undersigned at 813-221-0050.
Sincerely, Terracon Consultants, Inc.
Shawn Ouellette, P.G. Donna Cline, P.E.
Senior Geologist Senior Engineer
Attachments: Cost Spreadsheet Level of Effort
| DC023B.pdf |
| DC023B memo.pdf |
| CEF-LOEproposed230310_DEPcomments230310.pdf |
| Cost Estimate |
| LOE Subtask 2 |
| Proposal230309.pdf |
| deliverables |
| Schedule |
| closing remarks |