This document is a Task Assignment (TA) issued under Contract HW687 between the State of Florida Department of Environmental Protection (FDEP) and Terracon Consultants, Inc. The task assignment, numbered DC021C, authorizes work at the Village Laundry and Dry Cleaners site located at 10235 Lake Carroll Way, Tampa, Hillsborough County, Florida (Project ERIC_4743). The FDEP Project Manager is Patrick McGrane, and Terracon's Project Manager is Donna Cline. The task assignment is effective December 4, 2024, with a completion date of April 25, 2025.

Terracon will prepare a Remedial Alternative Evaluation (RAE) to address volatile organic hydrocarbon (VOH) groundwater contamination at the site. The scope of work includes a historical summary of site background, summary of site assessment data, development of a conceptual site model, evaluation of groundwater remediation technologies, development of a remedial alternative evaluation screening matrix, and a teleconference meeting with FDEP technical staff. The total task assignment value is $9,318.24, comprising 59.95 total labor hours allocated across project management (7.95 hours at $357.95) and remedial alternative evaluation (52 hours at $7,496.57), with overhead, fringe benefits, and a completion fee included. Payment is based on a fixed unit rate structure, and Terracon may invoice upon submittal and FDEP approval of the remedial alternative evaluation report, with the single deliverable due January 24, 2025.

View the file

Other files

File Type Posted
CN-370000-HW687-BF01ACO1.pdf PDF
CN-370000-HW687-BF03ACO1.pdf PDF
CN-370000-HW687-BIL01A.pdf PDF
CN-370000-HW687-BIL2ACO1.pdf PDF
CN-370000-HW687-BIL2BCO1.pdf PDF
CN-370000-HW687-BIL2CCO1.pdf PDF
CN-370000-HW687-BIL3ACO2.pdf PDF
CN-370000-HW687-BIO1ACO1.pdf PDF
CN-370000-HW687-DC001A.pdf PDF
CN-370000-HW687-DC003A.pdf PDF
CN-370000-HW687-DC003D.pdf PDF
CN-370000-HW687-DC005D.pdf PDF
CN-370000-HW687-DC006A.pdf PDF
CN-370000-HW687-DC006B.pdf PDF
CN-370000-HW687-DC008C.pdf PDF
CN-370000-HW687-DC010A.pdf PDF
CN-370000-HW687-DC010B.pdf PDF
CN-370000-HW687-DC011F.pdf PDF
CN-370000-HW687-DC011H.pdf PDF
CN-370000-HW687-DC012D.pdf PDF
CN-370000-HW687-DC013C.pdf PDF
CN-370000-HW687-DC015A.pdf PDF
CN-370000-HW687-DC015C.pdf PDF
CN-370000-HW687-DC019A.pdf PDF
CN-370000-HW687-DC01ACO2.pdf PDF
CN-370000-HW687-DC020A.pdf PDF
CN-370000-HW687-DC020B.pdf PDF
CN-370000-HW687-DC020C.pdf PDF
CN-370000-HW687-DC020D.pdf PDF
CN-370000-HW687-DC023C.pdf PDF
CN-370000-HW687-DC025B.pdf PDF
CN-370000-HW687-DC025C.pdf PDF
CN-370000-HW687-DC025F.pdf PDF
CN-370000-HW687-DC027B.pdf PDF
CN-370000-HW687-DC027C.pdf PDF
CN-370000-HW687-DC02BCO1.pdf PDF
CN-370000-HW687-DC02CCO2.pdf PDF
CN-370000-HW687-DC02DCO1.pdf PDF
CN-370000-HW687-DC02HCO1.pdf PDF
CN-370000-HW687-DC032A.pdf PDF
CN-370000-HW687-DC034A.pdf PDF
CN-370000-HW687-DC034C.pdf PDF
CN-370000-HW687-DC034D.pdf PDF
CN-370000-HW687-DC035F.pdf PDF
CN-370000-HW687-DC036A.pdf PDF
CN-370000-HW687-DC03CCO1.pdf PDF
CN-370000-HW687-DC041C.pdf PDF
CN-370000-HW687-DC041D.pdf PDF
CN-370000-HW687-DC048A.pdf PDF
CN-370000-HW687-DC048B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW687

DC021C April 25, 2025

This Task Assignment authorizes Terracon to prepare a Remedial Alternative

Evaluation (RAE) for the Village Laundry and Dry Cleaners site in accordance with the October 16, 2024 Scope of Work and Cost Estimate.

Patrick McGrane 850-245-8899 Terracon Consultants, Inc.

Donna Cline 904-479-7415

ERIC_4743

10235 Lake Carroll Way, Tampa, Hillsborough County

Village Laundry and Dry Cleaners

$ 9,318.24

$ 9,318.24

Scope of Work

Terracon Consultants, Inc.

Donna Cline

Senior Associate / Remediation Engineer

12/04/2024

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.12.03 12:11:57 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

BWC TAFORM 01/18

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton

Secretary

Memorandum

TO: Negotiation File Village Laundry and Dry Cleaners

Tampa, Hillsborough County

ERIC_4743

FROM: Patrick McGrane, Project Manager

SUBJECT: Negotiation Summary Task Assignment DC021C (HW687)

DATE: October 23, 2024

This Task Assignment authorizes Terracon Consultants, Inc. (Terracon) to prepare and present a

Remedial Alternative Evaluation (RAE) for the Village Laundry and Dry Cleaners site. In order to address groundwater contamination onsite, Terracon recommended the preparation of a RAE in the March 15, 2024, Supplemental Site Assessment Report. This recommendation was approved in a review memo from

Robert Huckaby, dated May 21, 2024.

The total cost for this project is $9,318.24 with 60 total labor hours. All work is to be completed in accordance with the October 16, 2024, Scope of Work and Cost Estimate.

Terracon may invoice according to the included schedule.

FDEP COST ESTIMATE

Contractor: Terracon

Date: 10/23/2024

Task #: HW687 SubTask 1 Project Management

Site: Village Laundry and DC (ERIC_4743) SubTask 2 Remedial Alternative Evaluation (RAE)

Activity/Phase: Remedial Alternatives Evaluation SubTask 3

Project Manager: Patrick McGrane SubTask 4

SubTask 5

Totals 1 2 3 4 5 6

Labor Rate Category

$45.00 Project Manager Michael Mui 7.95 7.95

$45.00 Senior Scientist Michael Mui 28.00 28.00 0.00 0.00 0.00 0

$72.36 Senior Engineer Chad Northington 14.00 14.00 0.00 0.00 0.00 0

$70.14 Senior Engineer Donna Cline 4.00 4.00 0.00 0.00 0.00 0

$33.31 CADD Specialist Chelsea Fugate 6.00 6.00 0.00 0.00 0.00 0

Total Hours 59.95 7.95 52.00 0.00 0.00 0.00 0

Direct Labor $3,111.41 $357.95 $2,753.46 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $3,609.23 $415.22 $3,194.01 $0.00 $0.00 $0.00 $0.00

Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 56.26% $1,750.48 $201.38 $1,549.10 $0.00 $0.00 $0.00 $0.00

Total Labor $8,471.12 $974.55 $7,496.57 $0.00 $0.00 $0.00 $0.00

Travel

Vehicle Rental $0.00 -$ $0.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $0.00 -$ $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Initiation Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $0.00 -$ $0.00 $0.00 $0.00 $0.00

Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $8,471.12 $974.55 $7,496.57 $0.00 $0.00 $0.00 $0.00

Completion Fee $847.12 $97.46 $749.66 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $9,318.24 $1,072.01 $8,246.23 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 1

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Village Laundry and Dry Cleaners

SUBTASK 2: Remedial Alternative Evaluation (RAE)

Proposal No: PH4246000

DATE: 10/23/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

RAE Preparation

Senior Scientist MM 24.00

Senhor Engineer CN 12.00

CADD Specialist CF Prepare RAE exhibits 6.00

RAE meeting with FDEP

Senior Scientist MM 4.00

Senhor Engineer DN 4.00

Senhor Engineer CN Teleconference meeting with FDEP 2.00

MM DN CN CF

Hours: 28.00 4.00 14.00 6.00 TOTAL LABOR 52.00

Preparation and teleconference meeting with FDEP

Preparation and teleconference meeting with FDEP

Review RAE text, tables and figures, review remedial cost estimates, evaluate the GW remedial alternatives, prepare recommendation