This Task Assignment (TA) is a contract document executed between the State of Florida Department of Environmental Protection (FDEP) and Terracon Consultants, Inc. The TA represents a work authorization under the overarching Contract Number HW687, with the primary parties being the State of Florida FDEP (through Department Project Manager Dean Cox) and contractor Terracon Consultants, Inc. (through Project Manager Donna Cline). The project is located at 13541 North Florida Avenue, Tampa, Hillsborough County, Florida, at the Fabricare Cleaners (former) facility (ERIC_4741).
The Task Assignment authorizes costs for preparation of an Interim Source Removal (ISR) Workplan for a Soil Vapor Extraction (SVE) System with a fixed unit rate of $7,505.43. The scope includes two subtasks: Subtask 1 (Project Management) and Subtask 2 (ISR Workplan and Construction Drawings). The work encompasses evaluation of existing Modified Active Gas Survey (MAGS) results, preparation of the ISR Workplan including FDEP RAP Checklist, design calculations, emissions treatment procedures, operation and maintenance protocols, construction schedule, and cost estimates, along with signed and sealed construction drawings. The deliverable is due October 31, 2022, with invoice due upon FDEP approval of the ISR Workplan. The total contract value is $7,505.43, representing 65.47 hours of labor at negotiated rates, which includes a cost reduction of $1,127.16 compared to the original proposal. An SVE Presumptive Remedy Approval Form was signed by the WSCS Professional Engineer on August 2, 2022, and the property access agreement was confirmed current.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW687
DC022A Completion November 30, 2022
This TA authorizes costs for preparation of an Interim Source Removal (ISR) Workplan, based on the Terracon proposal letter submitted 7/27/22 and cost estimate/CEF-LOE submitted 8/3/2022. All costs are fixed unit rate.
Dean Cox 850-245-8969 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Terracon Consultants, Inc.
Terracon Consultants, Inc.
Donna Cline 813-321-0340
ERIC_4741
13541 N. Florida Ave., Tampa (Hillsborough)
Fabricare Cleaners (former)
✔ $ 7,505.43
$ 7,505.43
Scope of Work
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.08.08 10:53:18 -04'00'
N/A dlcline Typewriter Donna Cline Senior Remediation Engineer dlcline Typewriter 8/8/2022
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
ISR Workplan (Subtask 1 Project Management and Subtask 2 ISR Workplan & Construction Drawings) 10/31/2022
FDEP approval of ISR Workplan (Subtask 1 Project Management and Subtask 2 ISR Workplan & Construction Drawings) $ 7,505.43
$ 7,505.43
HW687
DC022A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: HW687 Contract File FROM: Dean Cox, Contract Manager SUBJECT: Fabricare ISR Workplan – DC022A
DATE: 8/8/2022
This TA authorizes costs for preparation of an Interim Source Removal (ISR) Workplan, based on the Terracon proposal letter submitted 7/27/22 and cost estimate/CEF-LOE submitted 8/3/2022. The total TA cost is $7,505.43 with 65.47 hours of labor. All costs are fixed unit rate.
Labor was negotiated with Terracon. There are in 8.67 fewer hours in this TA compared to the original Terracon TA proposal. This reduced labor resulted in a $1,127.16 cost reduction/savings.
An SVE system is planned for installation at the site – an SVE Presumptive Remedy Approval Form was signed by the WSCS PE on 8/2/22. The facility has closed, been purchased, and is being reconfigured as a boating-related business. Terracon is working with the new tenant regarding placement of the system and preservation of the wells and MAGS. The property access agreement was confirmed current.
FDEP COST ESTIMATE
Contractor: Terracon
Date: 8/3/2022 Task #: HW687 DC005B SubTask 1 Project Management SubTask 6
Site: Fabricare Cleaners & Laundry ERIC_4741 SubTask 2 ISR Workplan and Construction Drawings SubTask 7 Activity/Phase: ISR Workplan and Construction Drawings SubTask 3 SubTask 8
Project Manager: Dean Cox SubTask 4 SubTask 9 SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$64.50 Project Manager Donna Cline 4.47 4.47 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$22.25 CADD Specialist Andy Schifano 9.00 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Environmental Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$64.50 Senior Engineer Donna Cline 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$29.33 Staff Engineer Ricker Lamphier 38.00 38.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 65.47 4.47 61.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $2,506.10 $288.31 $2,217.79 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 116.00% $2,907.08 $334.44 $2,572.64 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $1,409.93 $162.20 $1,247.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,823.11 $784.95 $6,038.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 1
FDEP COST ESTIMATEContractor: Terracon Date: 8/3/2022
Task #: HW687 DC005B SubTask 1 Project Management SubTask 6 Site: Fabricare Cleaners & Laundry ERIC_4741 SubTask 2 ISR Workplan and Construction Drawings SubTask 7
Activity/Phase: ISR Workplan and Construction Drawings SubTask 3 SubTask 8 Project Manager: Dean Cox SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,823.11 $784.95 $6,038.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $682.32 $78.50 $603.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $7,505.43 $863.45 $6,641.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Fabricare Cleaners & Laundry ERIC_4741 SUBTASK 2: ISR Workplan and Construction Drawings
PROPOSAL NO. PH4227316
DATE: 8/3/2022
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Prepare ISR Plan and Construction Drawings, Signed and Sealed by a Professional Engineer
Staff Engineer RL Evaluate MAGS and prepare SVE remediation design calculations 6 Staff Engineer RL Prepare ISR workplan 10 Staff Engineer RL Develop summary tables 2 Staff Engineer RL Develop Exhibits/Construction Drawings (trench details, SVE cross sections, treatment 10 system layout, P&ID, electrical detail, equipment list, and components) Staff Engineer RL Evaluate remedial equipment to be used and determine design details after discussions with 4 owner/tenant and power company Staff Engineer RL Prepare FDEP RAP Checklist 2 Staff Engineer RL Discussions / technical pre-design meeting with DEP 4
Senior Engineer DC Evaluate calculations 2 Senior Engineer DC Evaluate ISR Workplan written portion 4 Senior Engineer DC Evaluate for completion Exhibits/Construction Drawings 3 Senior Engineer DC Sign and seal ISR Workplan and Construction Drawings 1 Senior Engineer DC Discussions / technical pre-design meeting with DEP 4
Cadd Support AS ISR Workplan - Create and prepare final Exhibits and Construction Drawings 9
TOTAL LABOR 61
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE -$
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM -$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
TOTAL -$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC #IDW
TOTAL LAB -$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT -$
| DC022A memo.pdf |
| HW687 DC022A.pdf |
| DC022A.pdf |
| DC022A CEF-LOE 220803.pdf |
| Cost Estimate |
| LOE Subtask 2 |
| DC022A proposaLetter220727_Page_4.pdf |
| DC022A proposaLetter220727_Page_5.pdf |
File details come from the government source that posted it. Updated .