This is a Task Assignment (TA) issued under Florida Department of Environmental Protection (FDEP) Waste Cleanup Program Contract Number HW687, executed between the State of Florida Department of Environmental Protection and Terracon Consultants, Inc. The task assignment is designated DC027B with a completion date of October 11, 2024, and authorizes work at the Carriage Trade Dry Cleaners site located at 3944 West Hillsborough Avenue, Tampa, Hillsborough County, Florida (ERIC_4799). The assignment is managed by Sarah Aduwa for FDEP and Donna Cline for Terracon, with oversight coordination through project number ERIC_4799.
The scope of work authorizes Terracon to conduct groundwater monitoring for volatile organic halocarbons (VOHs) and perform expanded groundwater sampling for per- and polyfluorinated substances (PFAS) analysis and reporting at the site. Work includes field preparation, sampling of eight monitoring wells and piezometers, water level collection, lab analysis, and preparation of a comprehensive groundwater monitoring report with updated exhibits due within 20 business days of laboratory results. The total task assignment value is $10,883.57, composed of $9,044.87 for Subtask 2 (VOH groundwater sampling, waste characterization, and reporting, due 08/08/2024) and $1,838.70 for Subtasks 1 and 3 (project management and PFAS sampling, analysis, and reporting, due 09/06/2024). The work encompasses 73.96 total labor hours at various staff levels, including vehicle rental ($320.00), subcontractor costs for IDW disposal ($148.50), laboratory analysis ($787.00), and field equipment and expendables ($566.00), with a completion fee of $823.83.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW687
DC027B Completion October 11, 2024
This Task Assignment authorizes Terracon to conduct groundwater monitoring for VOHs; and to perform expanded groundwater sampling for per- and polyfluorinated substances (PFAS) analysis and reporting Carriage Trade Dry Cleaners site in accordance with Terracon’s scope of work and cost estimate received on the June 5, 2024.
Sarah Aduwa 850-245-8973 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Terracon Consultants, Inc.
Terracon Consultants, Inc.
Donna Cline 813-321-0340
ERIC_4799
3944 West Hillsborough Ave., Tampa (Hillsborough County)
Carriage Trade Dry Cleaners
✔ $ 10,883.57
$ 10,883.57
Scope of Work
Donna Cline
Senior Associate / Remediation Engineer Digitally signed by Cline, Donna L DN: cn=Cline, Donna L, ou=General Users, email=Donna.Cline@terracon.com Date: 2024.06.24 12:19:44 -04'00'
Cline, Donna L
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2024.06.24 09:05:14 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2 - collect ground water samples, IDW waste characterization and manifest, Groundwater monitoring report 08/08/2024
Subtask 1, 3, - Project management, PFAS sampling, analysis and report 09/06/2024
Subtask 2 - collect ground water samples, IDW waste characterization and manifest, Groundwater monitoring report $ 9,044.87
Subtask 1, 3, - Project management, PFAS sampling, analysis and report $ 1,838.70
$ 10,883.57
HW687
DC027B
Printed on recycled paper.
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
To: HW687 Contract Negotiation File Carriage Trade Dry Cleaners
Tampa, Hillsborough County, Florida
ERIC_4799
From: Sarah Aduwa, Project Manager Date: June 5, 2024 Subject: Negotiation Summary
HW687_DC027B
This Task Assignment authorizes Terracon to conduct groundwater monitoring for VOHs and to perform expanded groundwater sampling for per- and polyfluorinated substances (PFAS) analysis and reporting Carriage Trade Dry Cleaners site in accordance with Terracon’s scope of work and cost estimate received on the June 5, 2024.
CEF task elements are accurately enumerated in each LOE subtask, with associated descriptions in the deliverables and invoicing schedule. The FDEP Project Manager agrees to the scope of work and final cost associated with this Task assigner. The final cost is $10,883.57 with 74 labor hours.
FDEP COST ESTIMATE
Contractor: Terracon
Date: 6/5/2024 Task #: HW687 SubTask 1 Project Management SubTask 6
Site: Carriage Trade Dry Cleaners SubTask 2 VOH Groundwater Sampling SubTask 7 Activity/Phase: Annual GW Sampling/PFAS Screening SubTask 3 Expanded PFAS Sampling SubTask 8
Project Manager: Dean Cox SubTask 4 SubTask 9 SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$70.14 Project Manager Donna Cline 4.96 4.96 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0
$33.31 CADD Specialist Chelsea Fugate 6.00 4.00 2.00 0.00 0.00 0 0 0 0 0 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Environmental Technician 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0
$23.46 Field Geologist Jared Duncan 21.50 21.50 0.00 0.00 0.00 0 0 0 0 0 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Project Geologist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Project Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Project Scientist/Engineer 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0
$70.14 Senior Engineer Donna Cline 9.00 6.00 3.00 0.00 0.00 0 0 0 0 0 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0
$41.30 Senior Staff Engineer Ricker Lamphier 32.50 24.50 8.00 0.00 0.00 0 0 0 0 0 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 0
Total Hours 73.96 4.96 56.00 13.00 0.00 0.00 0 0 0 0 0
Direct Labor $3,025.87 $348.11 $2,070.32 $607.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 116.00% $3,510.01 $403.81 $2,401.57 $704.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $1,702.36 $195.85 $1,164.76 $341.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $8,238.24 $947.77 $5,636.65 $1,653.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 1
FDEP COST ESTIMATEContractor: Terracon Date: 6/5/2024
Task #: HW687 SubTask 1 Project Management SubTask 6 Site: Carriage Trade Dry Cleaners SubTask 2 VOH Groundwater Sampling SubTask 7
Activity/Phase: Annual GW Sampling/PFAS Screening SubTask 3 Expanded PFAS Sampling SubTask 8 Project Manager: Dean Cox SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $320.00 320.00$ -$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $320.00 320.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Initiation Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Capitol Environmental $135.00 135.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $135.00 $135.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $13.50 $13.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $148.50 $148.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $677.00 677.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 110.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $787.00 $787.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $119.00 99.50$ 19.50$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $347.00 347.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 100.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $566.00 $546.50 $19.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $10,059.74 $947.77 $7,438.65 $1,673.32 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $823.83 $94.78 $563.67 $165.38 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $10,883.57 $1,042.55 $8,002.32 $1,838.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF TERRACON Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Carriage Trade Dry Cleaners SUBTASK 2: VOH Groundwater Sampling Proposal No PH4247021
DATE: 1/26/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Task Planning Groundwater Sampling
Senior Staff Engineer RL 1.00 Senior Staff Engineer RL 3.00 Groundwater Sampling
Field Geologist JD Load/unload 1.00 Field Geologist JD Pickup drum for IDW from drum wholesale 1.50 Field Geologist JD Mobilization/Demobilization (from Tampa) 1.50 Field Geologist JD Collect water levels from 8 monitoring wells @ 10 minutes per well 1.50 Field Geologist JD Collect 8 VOH Groundwater Samples (MW001S, MW002I, MW003S, MW003I, PZ001, PZ002, PZ003, PZ004) 12.00 Field Geologist JD Containerize IDW in the Central Area 1.00 IDW Coordination
Senior Staff Engineer RL Prepare IDW Waste Characterization/Generator Profile 1.50 Field Geologist JD Coordinate IDW T&D Meet Transporter onsite 3.00 Report Deliverable
Field Geologist RL Prepare report tables, draft groundwater elevation and analytical isoconcentration figures 4.00 Field Geologist RL Prepare report 6.00 Field Geologist RL QA/QC field and laboratory data 2.00 Field Geologist RL Summarize groundwater analytical results 2.00 Senior Staff Engineer RL Summarize groundwater geochemistry field results 1.00 Senior Staff Engineer RL Evaluate and update CSM 4.00 Senior Engineer DC Conclusions and reccomendations 4.00 Senior Engineer DC Professional certification review and sign and seal 2.00 Cadd Specialist CF Prepare Figures and Exhibits 4.00
RL DC JD CF
Hours: 24.50 6.00 21.50 4.00 TOTAL LABOR 56.00
VEHICLE TYPE RATE UNIT USEAGE
Truck Drum pickup & Sampling 120.00$ day 2 240.00$ Car IDW Pick Up 80.00$ day 1 80.00$
TOTAL VEHICLE 320.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
Capitol Environmental IDW Disposal 135.00$ Drum 1 135.00$
Subcontractor Markup 10% 1 13.50$
TOTAL 148.50$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS
Halocarbons (short list) EPA 8260 63.00$ 8 0 1 567.00$ Sample Shipping Large Cooler 110.00$ 1 0 0 110.00$
TOTAL LAB 677.00$
* No charge for trip blanks
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables Expendables 40.00$ day 2 80.00$
Ice (Sample preservation) 6.50$ Bag 3 19.50$ Analytical Related Shallow Groundwater Sampling Kit 290.00$ day 1 290.00$
Tubing, HDPE 0.30$ ft 150 45.00$ Tubing, silicon (3/16 x 3/8) 3.00$ ft 4 12.00$
IDW 55-gallon drum, new 100.00$ drum 1 100.00$
TOTAL EQUIPMENT 546.50$
Request Sample Kit PreTask Planning, prepare field sampling and Field Work Request
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Carriage Trade Dry Cleaners - ERIC_4799 SUBTASK 3: Expanded PFAS Sampling Proposal No PH4247021
DATE: 1/26/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERRLN
STAFF-TITLE WORK DESCRIPTION HOURS
Field Task Planning Groundwater Sampling
Senior Staff Engineer RL 1.50 Senior Staff Engineer RL 2.00 Groundwater Sampling
Field Geologist JD Load/unload 0.00 Field Geologist JD Mobilization/Demobilization (fromTampa) 0.00 Field Geologist JD Collect 8 PFAS Groundwater Samples (MW001S, MW002I, MW003S, MW003I, 0.00
PZ001, PZ002, PZ003, PZ004) Same MW's sampled for VOHs Field Geologist JD Containerize IDW in the Central Area 0.00 IDW Coordination
Senior Staff Engineer RL Prepare IDW Waste Characterization/Generator Profile 0.50 Field Geologist JD Coordinate IDW T&D Meet Transporter onsite 0.00 Email Deliverable for PFAS Sampling
Senior Staff Engineer RL QA/QC field and laboratory data 2.00 Senior Staff Engineer RL Evaluate and summarize groundwater analytical results 2.00 Senior Engineer DC Conclusions and Recommendations for PFAS analysis 3.00 Cadd Specialist CF Prepare PFAS exhibit (showing PFOA, PFOS and PFOA+PFAS for each well) 2.00
RL DC JD CF
Hours: 8.00 3.00 0.00 2.00 TOTAL LABOR 13.00
VEHICLE TYPE RATE UNIT USEAGE
Truck (Sampling) $120.00 day 0 -$ Car IDW Pick Up 80 day 0 -$
TOTAL VEHICLE -$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
IDW Disposal -$ Drum 0 -$ Subcontractor Markup 10% 0 -$
TOTAL -$
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS
PFAS Analysis FDEP Laboratory -$ 8 1 1 -$
(MW001S, MW002I, MW003S, MW003I, PZ001, PZ002, PZ003, PZ004)
Sample Shipping Small Cooler -$ 8 -$
TOTAL LAB -$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables Expendables 40.00$ day 0 -$
Ice 6.50$ Bag 3 19.50$ Analytical Related Shallow Groundwater Sampling Kit 290.00$ day 0 -$
Tubing, HDPE 0.30$ ft 0 -$ Tubing, silicon (3/16 x 3/8) 3.00$ ft 0 -$
IDW 55-gallon drum, new 100.00$ drum 0 -$
TOTAL EQUIPMENT 19.50$
Request Sample Kit, Coordinate Lab Availability PreTask Planning, prepare field sampling and Field Work Request
5463 W. Waters. Ave. Suite 830
Tampa, FL 33634
P (813) 221-0050
F (813) 221-0051
Terracon.com
January 26, 2024
Florida Department of Environmental Protection
Waste Cleanup Program
Waste Management Division
2600 Blair Stone Road
Tallahassee, Florida 32399-2400
Attn: Mr. Dean Cox, Environmental Consultant
E: Dean.Cox@FloridaDep.gov
W: 850-245-8969
M: 727-686-6502
Re: Proposal for Combined VOH and PFAS Groundwater Sampling and Reporting
Carriage Trade Dry Cleaners
3920, 3924, and 3944 West Hillsborough Ave.
Tampa, Hillsborough County, Florida 33614
ERIC_4799
Waste Cleanup Contract No. HW687
Terracon Proposal No. PH4247021
Dear Mr. Cox:
Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the
Florida Department of Environmental Program (FDEP) Waste Cleanup Program to conduct groundwater monitoring for VOHs, and to perform expanded groundwater sampling for per-and polyfluorinated substances (PFAS) analysis, and Reporting for Carriage Trade Dry Cleaners (ERIC_4799) facility located at 3920, 3924, and 3944 West Hillsborough Avenue Tampa, Hillsborough County, Florida.
Scope of Services
◼ Field preparation, update health and safety plan for combined
PFAS and VOH groundwater sampling;
◼ Mobilize to site, perform groundwater sampling of four (4) monitoring wells and four (4) piezometers, MW001S, MW002I, MW003S, MW003I, PZ001, PZ002, PZ003, and PZ004 for VOH analysis;
◼ Include PFAS analysis in the collected groundwater samples
◼ Collect water levels from four (4) monitoring wells and four (4) piezometers, MW001S, MW002I, MW003S, MW003I, PZ001, PZ002, PZ003, and PZ004;
◼ Submit PFAS samples in cooler preserved on ice by overnight courier to FDEP’s laboratory for sample analysis;
◼ Review data and prepare a Groundwater Monitoring Report including updated tables, groundwater flow, and concentration exhibits;
◼ PFAS sampling data will be included as a section in the groundwater monitoring report to include an exhibit, certified lab report, field notes and forms, and a summary of the QA/QC and mailto:Dean.Cox@FloridaDep.gov
Proposal for Combined VOH and PFAS Groundwater Sampling and Reporting
Carriage Trade Dry Cleaners, ERIC_4799 ■ Tampa, FL
January 26, 2024 ■ Terracon Proposal No. PH4247021 groundwater analytical results. The exhibit will include text boxes
(showing PFOA, PFOS, and PFOA+PFOS concentration for each well)
See attached LOE for details
Schedule Deliverable Annual Groundwater Monitoring Report submitted within 20 business days following receipt of laboratory results.
Compensation
See attached CEF for details.
SITE RECOMMENDATIONS
Terracon performed Site Assessment Activities in January and February 2023. Based on the results of the 2023 Assessment, concentrations of 1,1-dichloroethene (DCE) were reported above its respective groundwater cleanup target level (GCTL) outlined in Chapter 62-777, Florida Administrative Code
(F.A.C.).
Concentrations of 1,1-DCE were reported above the GCTL of 7 micrograms per liter (µg/L) in MW002I
(14 µg/L). No other detections of 1,1-DCE were reported from the monitoring wells (and piezometers) at the Site. 1,1-dichloroethane (DCA) was detected in MW002I (4.1 µg/L) below its respective GCTL of
70 µg/L.
Other volatile organic halocarbons (VOHs), including cis-1,2-DCE and trans-1,2-DCE, were also detected at PZ004 (58 µg/L and 1.1 µg/L, respectively) below their respective GCTLs (70 µg/L and
100 µg/L, respectively).
Based on this data, Terracon recommends VOHs sampling of the existing monitoring wells to confirm the previously reported VOHs concentrations and evaluate any potential trends of VOH concentrations.
Terracon also performed per-and poly-fluoroalkyl substances (PFAS) sampling activities during the
February 2023 sampling event. PFOA, PFOS, and their combined sum were reported in MW001S, MW003S, PZ001, PZ002, and PZ004, above the provisional groundwater cleanup target level(s) of 70 ng/L. Based on this data, Terracon recommends PFAS sampling of the existing monitoring wells to confirm and evaluate any potential trends of PFAS at the Site.
DELIVERABLES
The Groundwater Monitoring Report will detail and summarize the groundwater sampling activities, field observations, and results of monitoring well analysis and will include updates to the site’s historical data tables and updated exhibits of groundwater flow and well concentrations. Conclusions and recommendations will include a summary of results and recommendations for future sampling, closure, or remedial activities. As mentioned earlier the PFAS evaluation will be provided in an additional section within this report.
Proposal for Combined VOH and PFAS Groundwater Sampling and Reporting
Carriage Trade Dry Cleaners, ERIC_4799 ■ Tampa, FL
January 26, 2024 ■ Terracon Proposal No. PH4247021
SCHEDULE
It is estimated that the wells could be sampled within two weeks from TA authorization and report issued within 20 business days of receipt of analytical data.
CLOSING REMARKS
Terracon services will be conducted in accordance with the terms and conditions, contained within DEP
Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.
We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact either of the undersigned at 813-221-0050.
Sincerely, Terracon Consultants, Inc.
Ricker Lamphier, E.I. Donna Cline, P.E.
Senior Staff Engineer Senior Remediation Engineer
Attachments: Cost Spreadsheet
Level of Effort
ITE
M
DESCRIPTIO
N
UNIT OF
MEASURE
ESTIMATED
QUANTITY
UNIT
PRICE
EXTENDE
D PRICE
ITEM
NO.
DESCRIPTIO
N
UNIT OF
MEASURE
ESTIMATE
D
UNIT
PRICE
EXTENDED
PRICE
ITEM
NO.
DESCRIPTIO
N
UNIT OF
MEASURE
ESTIMATED
QUANTITY
UNIT
PRICE
EXTENDE
D PRICE
IDW Pickup, Manifest
EA 1 $95.00 $95.00 1
IDW Pickup, Manifest
EA 1 $135.00 $135.00 1
IDW Pickup, Manifest
EA 1 $140.00 $140.00
2 Stop Fee EA 1 $252.00 $120.00 2 Stop Fee 1 1 $150.00 $150.00
TOTAL $215.00 TOTAL $135.00 TOTAL $290.00
Low Bid: Capitol Service
IDW
THREE BID SUMMARY EVALUATION
Petrotech SE Capitol Services Whatever 2 Waste
Please see specific Vendor bids for details and equipment
23800 County Road 561, Astatula, FL 34705 407-656-8114 352-343-2635 (fax) www.petrotechse.com
March 24, 2023
Rachael Greller Terracon 1675 Lee Rd Winter Park Fl 32789 321-347-3196 Email: Rachael.greller@terracon.com
RE: Drum Disposal – Wildwood, FL
Dear Ms. Greller:
Thank you for the opportunity to quote this project. Per your request, please find our proposal for the services you require.
Description of work: Petrotech Southeast Inc. will provide the equipment and personnel to transport and dispose of drums of non-hazardous groundwater non-hazardous soil/mud in Central Florida. This pricing does not include disposal of PFAS-contamianted waste. The pricing below is based on normal working hours, M-F, 7:00 AM – 5:00 PM.
Service Unit Type Unit Price T&D of Non-Haz Impacted Water Drum 90.00$ T&D of Non-Haz Impacted Soil/Mud/Sludge Drum 120.00$ Stop Fee (for pick-ups of <6 drums) Per Stop 125.00$
A generator waste profile must be approved prior to scheduling the transportation. Disposal analysis shall include TCLP 8 RCRA Metals and TCLP Volatiles, at a minimum. Other potential or known COCs should be identified and analyzed as well. Drums shall be staged on an impervious surface and accessible to commercial trucks. Any delays on site will be billed at $115/hour.
Thank you for the opportunity to work with you on this project. If you have any questions or concerns with this proposal please do not hesitate to call me.
Thank You, Jason W. Yates Vice President
23800 County Road 561, Astatula, FL 34705 407-656-8114 352-343-2635 (fax) www.petrotechse.com
Petrotech Southeast, Inc.
TERMS AND CONDITIONS
BILLING AND PAYMENT: Unless otherwise indicated in the proposal, Petrotech Southeast, Inc. billing will be based on accrued time, test costs and expenses. Client agrees to pay invoice upon receipt. Should payment not be received within 10 days, the amount due shall bear a service charge of 1½ per cent per month or 18 percent per year and the cost of collection, including reasonable attorneys’ fees, if collected by law through an attorney. If the Client has any objection to any invoice or part thereof submitted by Petrotech Southeast, Inc., he shall so advise us in writing giving his reasons within 14 days of receipt of such invoice. If the project is terminated in whole or in part then Petrotech Southeast, Inc. shall be paid for services performed prior to receiving notice of such termination, in addition to Petrotech Southeast, Inc. reimbursable expenses and any shut down costs incurred. Shut down costs may, at Petrotech Southeast, Inc.’s sole discretion, include completion of analyses and records necessary to document our files and protect our professional reputation. In the event that Petrotech Southeast, Inc. agrees to pay for a recyclable product, the price paid for that product shall be based on current market conditions and may be subject to change.
LIABILITY: Petrotech Southeast, Inc. maintains worker’s compensation and employer’s liability insurance for our employees as required by state laws. In addition we maintain comprehensive general liability, pollution liability, and vehicle liability insurance with limits of $1,000,000.00. A certificate of insurance can be supplied evidencing such coverage. We will not be liable or responsible for any loss, damage or liability beyond amounts limits, coverage or conditions of such insurance specified above.
GALLONAGE: The amount of material to be treated and disposed of by Petrotech Southeast, Inc. and paid for by the Client shall be determined by Petrotech Southeast, Inc. utilizing metered removal, gauging, or physical measurement.
HAZARDOUS SUBSTANCES AND CONSTITUENTS: Client agrees to advise Petrotech Southeast, Inc. upon execution of this agreement of any hazardous substances or any condition existing in, on or near the site presenting a potential danger to human health, the environment or equipment. Client agrees to provide continuing information, as it becomes available to the attention of the Client in the future.
EXCLUSIVITY: Upon execution of this agreement, Client agrees to exclusively use Petrotech Southeast, Inc. for all services and products described in this agreement
UNFORESEEN OCCURRENCES: If during the performance of services, any unforeseen hazardous substances or constituents or other unforeseen conditions or occurrences are encountered which, in Petrotech Southeast, Inc.’s judgment significantly affect or may affect the services, the risk involved in providing the services or the recommended scope of services, we will promptly notify the Client thereof. Subsequent to that notification, Petrotech Southeast, Inc. may: (a) If practicable, in Petrotech Southeast, Inc. sole judgment, complete the original scope of services in accordance with the procedures originally intended in this proposal: (b) Agree with the Client to modify the scope of services and the estimate of charges to include study of the previously unforeseen conditions or occurrences, such revision to be in writing and signed by the parties and incorporated herein: or (c) Terminate the services effective on the date specified by us in writing.
SUBCONTRACTED SERVICES: Petrotech Southeast, Inc. may furnish or obtain from others Subcontracted Services which are not considered normal or customary services of Petrotech Southeast, Inc
TAXES AND SURCHARGES: Any applicable taxes and surcharges shall be invoiced accordingly.
CLAIMS: in the event that Client makes claim against Petrotech Southeast, Inc. for any alleged error, omission, or act arising out of the performance of Petrotech Southeast, Inc. that cannot be mutually resolved without litigation, and Client fails to prove such claim, then Client shall pay all costs incurred by Petrotech Southeast, Inc. in defending itself against the claim, including, without limitation our personnel related costs, attorney’s fees, court costs and other claim related expenses, including without limitation, costs, fees, and expenses of experts.
SEVERABILITY: in the event that any provision herein shall be deemed invalid or unenforceable, the other provisions herein shall remain in full force and effect, and binding to the parties hereto.
SURVIVAL: All obligations arising prior to termination of the agreement and all provisions of this agreement allocation responsibility or liability between Client and Petrotech Southeast, Inc. shall survive the completion of the services and the termination of this agreement.
INTEGRATION: This agreement and the documents attached hereto and which are incorporated herein constitute the entire agreement between the parties and cannot be changed except by written instrument signed by both parties.
GOVERNING LAW: This agreement shall be governed in all respects by the laws of the State of Florida.
ACCEPTANCE: This proposal, when accepted by Client and final approval of proposal by a Petrotech Southeast, Inc. officer will constitute a bona fide contract between us, subject to terms and conditions. It is expressly agreed that there are no promises, agreements, oral or written, not specified in this proposal. This contract automatically renews on renewal date as prescribed on Page 1 of this agreement. Either party may cancel this agreement within 30 days of the renewal date.
By signing you acknowledge acceptance of Petrotech Southeast, Inc.’s terms and conditions.
Signature Printed Name Title Date If this proposal meets with your approval, please sign all pages and return Petrotech Southeast, Inc.
Capitol 200 Biddle Ave, Suite 205 Environmental Newark, DE 19702 Services, Inc. 302-380-3737 www.capitolenv.com
EXPERTISE SUSTAINABILITY SOLUTIONS
Rachael Greller Terracon 3-28-2023 1675 Lee RD Winter Park FL 32789
Scope of Work: Provide transportation and disposal of Non Hazardous drill cuttings, and Purged waters. Drums to be located on a hard surface for loading, or additional charges could apply. Quote good for sites in Central FL North areas. With approved profile and analytical.
DESCRIPTION
Estimated Quantity
UM Price $ Total $
Drill cuttings from drilling operation solids 30 drums Per Drum $140.00
Drums Purge waters ( 55 GL drum ) 30 drums Per Drum $135.00
Additional loading time after 1-hour site. Per Hour $155.00
Actual time
Rachael, I appreciate the opportunity to submit this proposal and hope that Capitol Environmental Services, Inc. can be of service to Terracon. Should you require additional information, or have any questions at all, please do not hesitate to contact me at 813-613-0452 Manderson@capitolenv.com
Sincerely Yours, Mike Anderson www.capitolenv.com mailto:Manderson@capitolenv.com file://CESIFP01/Users/TSRedirections/bfrenchman/AppData/Roaming/Microsoft/Word/www.capitolenv.com
Whatever Waste, LLC 3834 Mandarin Woods Dr. No.
Jacksonville, FL 32223 United States 904.881.1957
Rachael Greller Staff Scientist Terracon 1675 Lee Road Winter Park 32789 United States
Proposal Number 033023.1
Overview RE: Drycleaner Waste Drum Cleanup Program Non-haz IDW Drum Transport & Disposal LOC: Statewide including Florida Keys
Good day Ms. Greller, Whatever Waste is pleased to provide non-haz IDW soil and water drum transport & disposal services to you and Terracon in regions throughout Florida including the Keys
Pricing
Notes
Proposal Date 03/30/2023
Description Rate Qty Line Total
North Region: NH IDW Soil & Water 55-gallon drums - each (No Stop Fee)
$140.00 1 $140.00
Central Region:NH IDW Soil & Water 55-gallon drums - each (South of Ocala; North of Sarasota/Port St. Lucie) (Stop fee $150; 2 drums or less)
$140.00 1 $140.00
South Region: NH IDW Soil & Water 55-gal drums - each (South of Sarasota/Port St. Lucie) (Stop fee $200; 2 drums or less)
$225.00 1 $225.00
Florida Keys: NH IDW Soil & Water 55-gal drums - each (Stop Fee - $250)
$275.00 1 $275.00
Subtotal
Tax
780.00
0.00
Proposal Total (USD) $780.00
Whatever Waste will assist with IDW profiling and require VOCs, and RCRA 4 metals for IDW drycleaner site soils; and VOCs only for IDW drycleaner site water.
DOT shippable drums at each location must be accessible in one area and on a hard surface.
No-load run charges to locations if called off in transit or upon arrival would be the stop fee in Central, South Regions and the Keys. In the North Region the no-load charge would be $100.
Terms
Actual amounts will be invoiced unless minimum quantities and associated fees apply Rates under contract are valid for 6 months Payment terms are 30 days after receiving emailed invoice with associated documents
Indemnification: Each party agrees to indemnify, defend and hold harmless each other for and from any loss or liability arising out of the party's breach of this agreement except for gross negligence, willful misconduct or bad faith.