This document package constitutes a Task Assignment (TA) issued under Contract HW687 by the State of Florida Department of Environmental Protection (FDEP) to Terracon Consultants, Inc. for supplemental site assessment activities at the Former Rose Printing Company facility located at 2503 Jackson Bluff Road, Tallahassee, Leon County, Florida. The work is funded through federal State & Tribal Response Program Bipartisan Infrastructure Law (BIL) cooperative agreement funds administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA). The TA was effective upon signature on March 22, 2023, with a completion date of August 31, 2023.

The contract encompasses four subtasks totaling $55,111.69: Subtask 1 (Project Management, $2,357.40) covering overhead and administrative costs; Subtask 2 (QAPP/Work Plan and HASP, $1,985.03) requiring development of quality assurance and health/safety documentation by April 14, 2023; Subtask 3 (Supplemental Site Assessment Activities, $46,107.13) involving installation of 12 monitoring wells, soil and groundwater sampling, and investigation-derived waste coordination, with deliverables due by June 9, 2023; and Subtask 4 (Supplemental Site Assessment Report, $4,662.13) requiring a sealed professional report by July 28, 2023. The Department Project Manager is Megan Johnson, and the contractor's Project Manager is Tom Lewis, P.G. Payment is structured on a fixed unit rate basis with invoicing contingent upon FDEP approval of deliverables at each subtask milestone. No option periods or renewals are specified in this task assignment.

View the file

Other files

File Type Posted
CN-370000-HW687-BF01A.pdf PDF
CN-370000-HW687-BF01B.pdf PDF
CN-370000-HW687-BF02A.pdf PDF
CN-370000-HW687-BF04A.pdf PDF
CN-370000-HW687-BF04ACO3.pdf PDF
CN-370000-HW687-BIL01B.pdf PDF
CN-370000-HW687-BIL02B.pdf PDF
CN-370000-HW687-BIL03B.pdf PDF
CN-370000-HW687-BIL1BCO2.pdf PDF
CN-370000-HW687-BIL2CCO2.pdf PDF
CN-370000-HW687-CSS02.pdf PDF
CN-370000-HW687-CSS03.pdf PDF
CN-370000-HW687-DC002A.pdf PDF
CN-370000-HW687-DC002G.pdf PDF
CN-370000-HW687-DC006C.pdf PDF
CN-370000-HW687-DC008B.pdf PDF
CN-370000-HW687-DC008D.pdf PDF
CN-370000-HW687-DC009B.pdf PDF
CN-370000-HW687-DC010C.pdf PDF
CN-370000-HW687-DC012A.pdf PDF
CN-370000-HW687-DC014B.pdf PDF
CN-370000-HW687-DC014D.pdf PDF
CN-370000-HW687-DC014H.pdf PDF
CN-370000-HW687-DC015D.pdf PDF
CN-370000-HW687-DC016C.pdf PDF
CN-370000-HW687-DC01ACO9.pdf PDF
CN-370000-HW687-DC021A.pdf PDF
CN-370000-HW687-DC021C.pdf PDF
CN-370000-HW687-DC022A.pdf PDF
CN-370000-HW687-DC023B.pdf PDF
CN-370000-HW687-DC023D.pdf PDF
CN-370000-HW687-DC024B.pdf PDF
CN-370000-HW687-DC024E.pdf PDF
CN-370000-HW687-DC024F.pdf PDF
CN-370000-HW687-DC027A.pdf PDF
CN-370000-HW687-DC028A.pdf PDF
CN-370000-HW687-DC028D.pdf PDF
CN-370000-HW687-DC029C.pdf PDF
CN-370000-HW687-DC02ACO1.pdf PDF
CN-370000-HW687-DC02HCO2.pdf PDF
CN-370000-HW687-DC030A.pdf PDF
CN-370000-HW687-DC031A.pdf PDF
CN-370000-HW687-DC035A.pdf PDF
CN-370000-HW687-DC037A.pdf PDF
CN-370000-HW687-DC03CCO2.pdf PDF
CN-370000-HW687-DC044A.pdf PDF
CN-370000-HW687-DC045B.pdf PDF
CN-370000-HW687-DC049A.pdf PDF
CN-370000-HW687-DC054A.pdf PDF
CN-370000-HW687-DC056A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW687

BIL01A Completion August 31, 2023

The Department approves this Task Assignment (TA), based upon the Cost Proposal and Level of Effort (CP/LOE), for Supplemental Site Assessment activities at the below project site, submitted to the Department on March 15, 2023, revised March 21, 2023, by Terracon Consultants, Inc. The final deliverable will be the Supplemental Site Assessment Report received by the Department no later than July 28, 2023.

Megan Johnson 850.245.8994 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Terracon Consultants, Inc.

Terracon Consultants, Inc.

Tom Lewis, P.G. 850.692.7194

ERIC_18047

2503 Jackson Bluff Road, Tallahassee, Leon County

Former Rose Printing Company

✔ $ 55,111.69

$ 55,111.69

Scope of Work

Donna Cline, P.E.

Senior Remediation Engineer

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2023.03.22 12:50:33 -04'00'

N/A

Cline, Donna L Typewriter 3/22/23

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

QAPP/Work Plan and HASP.

04/14/2023

Field notes, photographic log, chain of custody, and sampling logs.

06/09/2023

Supplemental Site Assessment Report; Project Management.

07/28/2023

Department approval of QAPP/Work Plan and HASP (Subtask 2) $ 1,985.03

Department approval of field notes, photographic log, chain of custody, and sampling logs (Subtask 3) $ 46,107.13

Department approval of Project Management and Supplemental Site Assessment Report (Subtasks 1 and 4) $ 7,019.53

$ 55,111.69

HW687

BIL01A

www.FloridaDEP.gov

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Terracon Consultants, Inc., HW687 Contract File

FROM: Megan Johnson, Contract Manager

DATE: March 21, 2023

SUBJECT: Negotiation Summary – BIL22 Task Assignment (TA) BIL01A

Former Rose Printing Company – Site ID # ERIC_18047 Supplemental Site Assessment Activities

This TA is intended for conducting Supplemental Site Assessment activities at the Former Rose Printing Company site, located at 2503 Jackson Bluff Road, Tallahassee, Leon County. The services under this task are being conducted using federal funds from the State & Tribal Response Program Bipartisan Infrastructure Law (BIL) funding cooperative agreement that is administered by the Department on behalf of the U.S. Environmental Protection Agency (EPA).

Subtask 1: Project Management This subtask is a percentage of the overall project fees and has been negotiated as a contract rate. It includes project management, overhead, general and administrative, and fringe. The agreed upon cost of this subtask is $2,357.40.

Subtask 2: QAPP/Work Plan and HASP In accordance with an EPA directive, this subtask includes the completion of a Quality Assurance Project Plan (QAPP)/Work Plan and a Health and Safety Plan (HASP). The QAPP/Work Plan will provide a brief summary of the scope of work, tables and figures showing the proposed sampling locations, and laboratory and field quality assurance measures and procedures. The agreed upon cost of this subtask is $1,985.03.

Subtask 3: Supplemental Site Assessment Activities Under this subtask, Terracon will supervise the well installation of 10 shallow monitoring wells to approximately 30 feet below ground surface and two deeper wells to approximately 45 feet below ground surface. Soil samples will be continuously collected at each well location and field screened using an OVA/PID. A total of six soil samples and 12 groundwater samples will be collected for laboratory analysis for benzene, toluene, ethylbenzene and xylene (BTEX) by EPA Method 8260, polycyclic aromatic hydrocarbons (PAHs) by EPA Method 8270, and total recoverable petroleum hydrocarbons (TRPHs) by FL PRO. Terracon will also coordinate the collection and disposal of up to 45 drums of investigation derived waste. The agreed upon cost of this subtask is $46,107.13.

http://www.floridadep.gov/

Negotiation Summary – Task Assignment BIL01A Former Rose Printing Company – Site ID # ERIC_18047 March 21, 2023 www.FloridaDEP.gov

Subtask 4: Supplemental Site Assessment Report A Supplemental Site Assessment Report will be prepared detailing the field and laboratory results. This report will also include figures, maps, tables, and conclusions and recommendations for any future work. The agreed upon cost of this subtask is $4,662.13.

Summary The Department’s BIL Contract Manager and Terracon’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $55,111,69. Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) Form and CP/LOE narrative provided by Terracon on March 15, 2023, revised March 21, 2023, and the TA Form for BIL01A prepared by the Department. The final deliverable for this TA must be received by the Department no later than July 28, 2023.

http://www.floridadep.gov/

3559 Timberlane School Rd

Tallahassee, FL 32312

P (850) 692-7185

F (850) 692-7186

Terracon.com

March 15, 2023

Florida Department of Environmental Protection

Waste Cleanup Program-Waste Management Division

2600 Blair Stone Road

Tallahassee, Florida 32399-2400

Attn: Ms. Megan R. Johnson, Environmental Consultant

Brownfields and CERCLA Site Screening Section

E: Megan.R.Johnson@floridadep.gov

W: 850-245-8994

Re: Proposal for Supplemental Site Assessment

Former Rose Printing Company

2503 Jackson Bluff Road

Tallahassee, Leon County, Florida

Terracon Proposal No. PHF237020

Dear Ms. Johnson:

Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the

Florida Department of Environmental Program (FDEP) Waste Cleanup Section to conduct a

Supplemental Site Assessment for the Former Rose Printing Company facility located at 2503 Jackson

Bluff Road in Tallahassee, Florida. These activities will be performed as approved by both FDEP and the U.S. Environmental Protection Agency (U.S. EPA) for utilizing Targeted Brownfield Assessment/Site

Specific Activities (TBA/SSA) federal funding administered by FDEP.

Scope of Services

(see Section 2.0 of attached

Proposal Detail)

◼ Develop a Workplan / Quality Assurance Project Plan (QAPP) and updated Health and Safety Plan (HASP) and (6) days supplemental site assessment including 12 monitoring well installations, soil sampling and groundwater sampling.

◼ Review data and prepare a Supplemental Site Assessment Report with tables and concentration exhibits sealed by a Professional

Geologist.

See attached LOE for details

Schedule

(see Section 4.0 of attached

Proposal Detail)

Deliverable of Workplan and QAPP within 5 business days of authorization;

Deliverable of field notes, photolog, and chain of custody within 2 business days of completion of field work;

Deliverable Supplemental Site Assessment within 20 business days following receipt of laboratory results.

Compensation

(see Section 4.0 of attached

Proposal Detail)

$55,111.69 (See attached CEF for details).

mailto:Megan.R.Johnson@floridadep.gov

Proposal for Supplemental Site Assessment and Preparation of Report

Former Rose Printing Company ■ Tallahassee, FL

March 15, 2023 ■ Terracon Proposal No. PHF237020

PROJECT INFORMATION

Prior to being redeveloped as a printing shop in the late 1950s, the site was occupied by the Dale

Mabry Army Airfield during the 1940s and 1950s to train pilots and air crews during World War II.

During site operations as Dale Mabry Army Airfield, the area of the site served as location for bunkered underground storage tanks (USTs) that transported fuel in an underground pipeline to a fuel depot adjacent to a runway northwest of the site.

According to the Final Site Assessment Report - Site Assessment and Pipeline Abandonment Former

Dale Mabry Army Airfield Tallahassee, Leon County, Project No. I04FL0117-01, dated May 2016, prepared by Aerostar SES, LLC (Aerostar), this specific area of the fueling operations was identified as

“Site B”. Site B consisted of thirteen (13) 25,000-gallon USTs. It is believed that the north portion of this former tank area is north of the former Rose Printing Building and under the northwest corner of the former Rose Printing Building. Prior assessments performed at the site confirmed exceedances above the FDEP Cleanup Target Levels for soil and groundwater have been identified in this area. The reports reviewed suggest that the USTs and the pipeline were abandoned sometime prior to the site being occupied by Rose Printing. Only benzene, toluene, ethylbenzene, xylenes (BTEX) and lead were analyzed for in this prior groundwater assessment.

In a May 19, 2017 letter from FDEP to the U.S. Army Corp of Engineers (USACE), FDEP did not concur with the USACE recommendation for Site B and indicated the USACE “needs to conduct additional assessment activities at the site, and fully characterize and define the site’s groundwater plume, before the Department can determine if Site B qualifies for non-eligibility status”. This investigation was not performed.

In the fall of 2019, utilizing funds available from their US EPA Community Brownfield Assessment grant, the City of Tallahassee (City) contracted Terracon to perform Phase I and II Environmental Site

Assessment (ESA) activities prior to acquiring the site for redevelopment. Direct push sampling inside the building indicated significant groundwater impacts extended south of the former tank area under the building.

On March 3, 2022, FDEP approved the City’s application for further assessment and cleanup of this former airfield site. This following scope has been prepared to provide both an update to current onsite monitoring well data as well as perform additional horizontal and vertical extent profiling of the impacts to groundwater underneath the building and on the north portion of the site. The goal of this study is to provide an update to the original May 19, 2017 request by FDEP to the USACE and serve as an initial remedial planning tool for additional assessment and cleanup approaches to be implemented after the building’s demolition later in 2022.

SCOPE OF SERVICES

Based on prior discussions on phone and email, the proposed scope of services consists of four subtasks involving Project Management, developing a Workplan / QAPP and HASP, monitoring well installation and sampling, and producing a Supplemental Site Assessment Report:

Subtask Description

Subtask 1: Project Management This scope is provided for in the template worksheets

Subtask 2:

Workplan/QAPP/HASP

Develop a Workplan and Quality Assurance Project Plan and Health and

Safety Plan prior to field work for approval by FDEP

Subtask 3. Groundwater

Sampling and Analysis

▪ Mobilization/Demobilization to and from site.

▪ Supervise well installation of 10 shallow wells to 30 ft bgs constructed of 2-inch dia. PVC riser with 15 ft of 0.01-inch slotted screen. Additionally, install 2 deeper wells to 45 ft bgs constructed of 2-inch dia. PVC riser with 5 ft of 0.01-inch slotted screen.

▪ Collect soil cores continuously to total depth at each well location and field screen using an OVA/PID. Based on highest OVA/PID reading, A total of 6 soil samples will be collected for laboratory analysis for benzene, toluene, ethylbenzene and xylene (BTEX) by

EPA Method 8260, polycyclic aromatic hydrocarbons (PAHs) by EPA

Method 8270, and Total Recoverable Petroleum Hydrocarbons

(TRPH) by FL PRO. The analysis will be performed using a National

Environmental Laboratory Accreditation Conference (NELAC) approved laboratory.

▪ Collect 12 groundwater samples for laboratory analysis by BTEXM

(8260), PAHs (8270), and TRPHs (FL PRO). The analysis will be performed using a NELAC approved laboratory.

▪ Coordinate the collection and disposal of up to 45 drums investigation derived waste (IDW)

Subtask 4. Supplemental Site

Assessment Report

▪ Prepare a Supplemental Site Assessment Report with site history, methodology, conclusions, recommendations, tables, sample locations and concentration exhibits, sealed by a Professional

Geologist

SCHEDULE

It is estimated that the workplan, QAPP, and updated HSP can be submitted within five days of authorization and the supplemental site assessment can be implemented by mid-May 2023, or earlier should the current demolition activities be complete. A Supplemental Site Assessment Report can be issued within 20 business days of receipt of laboratory analytical results.

CLOSING REMARKS

Terracon services will be conducted in accordance with the terms and conditions, contained within DEP

Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.

We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact either of the undersigned at 850-692-7185.

Sincerely, Terracon Consultants, Inc.

for Donna Cline, P.E. Tom Lewis, P.G.

Senior Remediation Engineer Principal

Attachments: Exhibit 1

Cost Spreadsheet

Level of Effort

Drill Bids/

MW-8

JACKSON BLUFF RD

FORMER

ROSE PRINTING

M

ABR

Y ST

MW-7

MW-21

MW-1MW-6 TW-3

MW-13

TW-4

MW-2

MW-17

MW-3

MW-20

MW-5

MW-11

MW-12

GW-7

GW-6

GW-2

GW-1

SB-4

SB-11/TW-2

SB-12

SB-13

SB-14/TW-3

SB-15

SB-16

SB-17

SB-18

SB-5/TW-4

SB-1

SB-19

SB-2SB-3

SB-20

SB-21

SB-8

SB-7

SB-10

SB-6/TW-1

SB-9

MW-22MW-23

AREA OF

REFUSAL/

FORMER

USTs

MW-15MW-9

GW-4MW-4

GW-8/15

GW-3

MW-19

MW-18

GW-5

MW-14

MW-16

MW-10

GW-2

20-35

6/16/22

0.5 U

0.5 U

0.5 U

2 U 61.8

GW-3

20-35

6/16/22 1.1

0.5 U

0.5 U

2 U 30.6

GW-1

20-35

6/16/22 3.1

0.5 U

0.5 U

2 U

GW-4

20-35

6/16/22 4.1

1.8 I

41.1

GW-5

20-35

6/16/22 48.5

GW-6

20-35

6/16/22

0.5 U

0.5 U

0.96 I

2 U

15 U

GW-7

16-26

6/16/22

0.5 U

0.5 U

0.5 U

2 U

15 U

GW-8 GW-15

16-26 25-40

6/16/22 6/16/22

3.2 12

0.61 I 0.5 U

69 0.51 I

4.4 I 2 U

15 U 66.8

Approximate Scale0 (Feet)

Project Mngr:

Approved By:

Checked By:

Drawn By:

Project No.

Scale:

Date:

File No.

EXHIBITGROUNDWATER EXCEEDANCES SUMMARY MAP

5463 W. Waters Ave. Ste 830 Tampa, Florida

PH. (813) 221-0050 FAX. (813) 221-0051

N

ROSE PRINTING ASSESSMENT

2503 JACKSON BLUFF ROAD

TALLAHASSEE, LEON COUNTY, FLORIDA

HF227047

SO

CF

SO

SO

HF227047

AS-SHOWN

7/26/22

MONITORING WELL

LEGEND

APPROXIMATE SUBJECT PROPERTY BOUNDARY

AREA OF REFUSAL/FORMER USTs

ABANDONED/DESTROYED MONITORING WELL

HISTORICAL SOIL BORINGS INSTALLED BY

TERRACON

ANALYTE DETECTED BETWEEN THE LAB METHODI =

DETECTION LIMIT & THE PRACTICAL QUANTITATION

LIMIT

ANALYTE NOT DETECTED ABOVE LAB METHODU =

DETECTION LIMIT

RESULTS REPORTED IN MICROGRAMS PER LITERµg/L =

SAMPLE ID

SCREEN INTERVAL (FT)

SAMPLE DATE

BENZENE (μg/L)

TOLUENE (μg/L)

ETHYLBENZENE (μg/L)

TOTAL XYLENES (μg/L)

LEAD (μg/L)

1 100 40 400 30 300 20 200 15 150

GCTL NADC

EXCEEDS GCTL

EXCEEDS NADC

sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval sloneal Oval

FDEP COST ESTIMATE

Contractor: Terracon

Date: 3/21/2023 Task #: BIL01A SubTask 1 Project Management SubTask 6

Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7 Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8

Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9 SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$72.12 Project Manager Tom Lewis 11 10.9 $20.50 Administrative Ashley Miller 1 1 0 0 0 0 0 0 0 0 $72.50 Brownfield Consultant Belinda Richard 0 0 0 0 0 0 0 0 0 0 $31.25 CADD Specialist Chelsea Fugate 8 0 0 8 0 0 0 0 0 0 $0.00 Data Analyst & Visualization Specialist 0 0 0 0 0 0 0 0 0 0 $0.00 Environmental Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Field Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Field Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 GIS Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Principal Consultant 0 0 0 0 0 0 0 0 0 0 $0.00 Project Geologist 0 0 0 0 0 0 0 0 0 0 $0.00 Project Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$26.92 Project Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Engineer 0 0 0 0 0 0 0 0 0 0

$72.12 Senior Geologist Tom Lewis 5 1 0 4 0 0 0 0 0 0 $0.00 Senior GIS Analyst 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Industrial Hygienist 0 0 0 0 0 0 0 0 0 0

$45.19 Senior Scientist Sid O'Neal 73 1 55 17 0 0 0 0 0 0 $0.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0

$25.00 Env Technician Rodney Twiss 85 21 54 10 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 183 11 24 109 39 0 0 0 0 0 0

Direct Labor $6,842.12 $787.15 $662.81 $3,835.45 $1,556.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $7,936.85 $913.09 $768.86 $4,449.12 $1,805.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $3,849.38 $442.85 $372.90 $2,157.82 $875.81 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $18,628.35 $2,143.09 $1,804.57 $10,442.39 $4,238.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $600.00 $0.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $600.00 $0.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) PDS $19,785.00 $0.00 $19,785.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $4,950.00 $0.00 $4,950.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $24,735.00 $0.00 $24,735.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $2,473.50 $0.00 $2,473.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $27,208.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00REV: 02/03 $0.00 Page 1$27,208.50

FDEP COST ESTIMATEContractor: Terracon Date: 3/21/2023

Task #: BIL01A SubTask 1 Project Management SubTask 6 Site: Former Rose Printing Company TBA SubTask 2 QAPP and HASP SubTask 7

Activity/Phase: TBA and Reporting SubTask 3 Monitoring Well Installations/Soil and Groundwater Assessment SubTask 8 Project Manager: Megan Johnson SubTask 4 Site Assessment Report SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Laboratory

Analytical Costs $5,204.00 $0.00 $5,204.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $5,204.00 $0.00 $5,204.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $157.50 $0.00 $157.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $180.00 $0.00 $180.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $1,270.50 $0.00 $1,270.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,608.00 $0.00 $1,608.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $53,248.85 $2,143.09 $1,804.57 $45,062.89 $4,238.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,862.84 $214.31 $180.46 $1,044.24 $423.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $55,111.69 $2,357.40 $1,985.03 $46,107.13 $4,662.13 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Former Rose Printing SUBTASK 2: QAPP and Updated HASP

PROPOSAL NO. PHF237020

DATE: 3/10/2023

LABOR CATEGORY

STAFF-TITLE HOURS

HASP

Senior Scientist SO 1.00 Staff Scientist RT 3.00

QAPP

Staff Scientist RT 18.00 Senior Geologist TL 1.00

Admin Admin AM 1

Staff Total hours

TL 1

SO 1

RT 21

AM 1 TOTAL LABOR 24

VEHICLE TYPE RATE UNIT USEAGE

0 $0.00

$0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

*PROVIDE TIME REQUIRED FOR EACH PERSON

WORK DESCRIPTION

Prepare/Submit Final Plan Prepare Health and Safety Plan

Prepare QAPP Prepare/Submit Final QAPP

Project files set-up

SUBTASK 2: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 3/10/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning and Monitoring Well Installations with Soil Sampling Senior Scientist SO 1.00 Staff Scientist RT 3 days loading/unload mobilization 3.00 Senior Scientist SO 3 days loading/unload mobilization 3.00 Staff Scientist RT 3 days of well installation oversight with soil sampling at 12 locations 30.00 Senior Scientist SO 3 days of well installation oversight with soil sampling at 12 locations 30.00

Survey Monitoring Well Top of Casing Senior Scientist SO 2.00 Field Scientist RT 2.00

Coordinate IDW T&D Senior Scientist SO 1.00 Field Scientist RT 2.00

Monitoring Well Groundwater Sampling Senior Scientist SO 1.00 Staff Scientist RT 2 days loading/unload mobilization 2.00 Senior Scientist SO 2 days loading/unload mobilization 2.00 Staff Scientist RT 1.5 days of monitoring welll sampling at 12 locations 15.00 Senior Scientist SO 1.5 days of monitoring well sampling at 12 locations 15.00

Staff Total hours

TL

SO 55

RT 54

TOTAL LABOR 109

VEHICLE TYPE RATE UNIT USEAGE

Truck (Well Installation/ sampling) 120 day 4.5 $540.00 Truck (IDW pickup) 120 day 0.5 $60.00

TOTAL VEHICLE $600.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin Remediation IDW Disposal 110.00$ each 45 $4,950.00 PDS Hollow-Stem Auger 19,785.00$ LS 1 $19,785.00

TOTAL $24,735.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Aromatic VOCs EPA 8260D (soil) 60.00$ 6 0 0 $360.00 PAHS EPA 8270 (soil) 110.00$ 6 $660.00 TRPH FL PRO (soil) 88.00$ 6 $528.00 Sample Shipping Large Cooler (2 day) 70.00$ 6 $420.00

Aromatic VOCs EPA 8260D (groundwater) 60.00$ 12 0 0 $720.00 PAHS EPA 8270 (groundwater) 110.00$ 12 $1,320.00 TRPH FL PRO (groundwater) 88.00$ 12 $1,056.00

Survey new monitoring wells (12) Survey new monitoring wells (12)

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

PreTask Planning, prepare field sampling SOW/coordinate site access, kit

Prepare waste characterization/Generator Profile Coordinate IDW T&D: Meet transporter to unlock secure area for pickup

SUBTASK 2: Monitoring Well Installations/Soil and Groundwater Assessment

PROPOSAL NO. PHF237020

DATE: 3/10/2023

Sample Shipping Large Cooler (2 day) 70.00$ 2 $140.00

TOTAL LAB $5,204.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables 40.00$ day 4.5 $180.00 Personal Protection 35.00$ day 4.5 $157.50 Photoionization Meter 352.00$ week 1 $352.00 Shallow groundwater sampling kit 290.00$ day 1.5 $435.00 Tubing, HDPE 0.30$ ft 450 $135.00 Tubing, silicon (3/16 x 3/8) 3.00$ ft 6 $18.00 Multimeter (YSI ProPlus) 105.00$ day 1.5 $157.50 Turbidimeter (Hach) 27.00$ day 1.5 $40.50 water level indicator 25.00$ day 1.5 $37.50 Pump, peristaltic 30.00$ day 1.5 $45.00 Total Survey Station 50.00$ day 1 $50.00 55-gallon drum, new 100.00$ drum 0 $0.00

$0.00

TOTAL EQUIPMENT $1,608.00

SUBTASK 3: SSA Report

PROPOSAL NO. PHF237020

DATE: 3/10/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning Senior Scientist SO 1.00 Senior Geologist TL 1.00

Deliverable Field Scientist RT 10.00 Senior Scientist/Geologist SO Summarize Water Quality Parameters 2.00 Senior Scientist/Geologist SO Summarize Groundwater Analytical Results 4.00 Senior Scientist SO 10.00

QA/QC and Review Senior Scientist/Geologist TL Review, Finalize, and Seal Report 3.00

CADD

Project Scientist CF Create updated exhibits 8.00 Staff Total hours

TL 4

SO 17

RT 10

CF 8 TOTAL LABOR 39.00

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE -$

PER DIEM STAFF RATE UNIT USEAGE

$0.00 -$

TOTAL PER DIEM -$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

TOTAL -$

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS

* No charge for trip blanks, only one duplicate

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT -$

Review data and make recommendations and conclusions Review data and make recommendations and conclusions

Data reduction/evaluation/Tables

Prep of Report

Preferred Drilling Solutions, Inc.

8820 66th St. North, Pinellas Park, FL 33782

Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com

DIRECT PUSH TECHNOLOGY QUOTE FORM

Date: 3/7/23 FAC ID#: ERIC_18047

Unit Unit Rate Number of Units Extended Price whole day $1,875.00 3 5,625.00$ half day $1,475.00 -$ per foot $20.00 390 7,800.00$ each $110.00 -$ each $45.00 -$ each $25.00 -$ per well $125.00 12 1,500.00$ roundtrip $750.00 1 750.00$ per crew / per night $450.00 2 900.00$ each $70.00 45 3,150.00$ per day $100.00 -$ each $30.00 2 60.00$

TOTAL QUOTE PRICE $19,785.00

Notes: 1. Includes saw cuts, development, standby time, and decon.

Project No.:

Subcontract Company Name: Preferred Drilling Solutions, Inc. (727) 561-7477

Subcontract Mailing Address: 8820 66th St, Pinellas Park, FL 33782

Signature and Title of Person Submitting Quote: ___________________________________Austin Bonacum, Estimator Date: 3/7/23

Days to Complete Scope of Work: 3

Direct Push Daily Rate 1 - on-site day

Equipment Type: Geoprobe 8040DT, Geoprobe 3230DT

*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner

Other (specify)

Other (specify)

Other (specify)

GeoProbe Consumables (includes tubing, points, liners, concrete patch, asphalt patch, and grouting)

DOT Approved 55-gal Drum

Per Diem Mobilization

DIRECT PUSH TECHNOLOGY

MISCELLANEOUS

Permits

Site Name and Location: Former Rose Printing

Consultant Name: Terracon

PROPOSED SCOPE OF WORK:

(10) 2" x 30' MW's with 15' .010 screen, continuous soil sampling, drum soil & water, pad and 8" manhole

(2) 2" x 45' MW's with 5' .010 screen, continuous soil sampling, drum soil & water, pad and 8" manhole

2503 Jackson Bluff Rd, Tallahassee, Leon County, FL

Well Completion (includes MH w/ cover, concrete pad, and locking well cap)

Well Riser (includes all materials) ID 1" 5' Length

Slotted PVC Well Screen (includes all materials) 5' Length Pack OD 3.5"

Pre-Packed Well Screen (includes all materials) ID 1" 5' Length Pack OD 3.5"

Auger Attachment, 2" Well Install

Direct Push Half-Day Rate 1 - on-site half day

Date: March 7, 2023

Quote # : SERS6313

FDEP Facility ID No.:

Project No.:

Purchase Order No.:

To: Sid O'Neal

Terracon Consultants, Inc.

3559 Timberlane School Rd.

Tallahassee, FL

(850) 692-7189

Sid.O'Neal@terracon.com

Job Payment Terms

Net 60 Days

Qty Unit Price Line Total

390.00 $30 11,700.00$

390.00 $18 7,020.00$

12.00 $77 924.00$

2.00 $40 80.00$

12.00 $200 2,400.00$

1.00 $1,300 1,300.00$

2.00 $450 900.00$

Subtotal 24,324.00$

Sales Tax

Total 24,324.00$

6741 Pine Forest Road Pensacola, Florida 32526 Office:850-944-7799 Fax:850-944-0704 Email: pensacola@singleycc.com

Thank you for your business!

due to the ever changing cost of materials and fuel

Note: Cost Estimate is valid for 30 days

Mobilization and demobilization- equipment and crew

55 gallon drums if needed

Well Permit

Estimated days to complete scope of work 3-4 days

Salesperson

Pattie Eckerle Rose Printing -

2503 Jackson Bluff Road, Tallahassee, FL

Well Completions; 2'x2' well pads w/ 8" manhole w/bolt down covers

Description

Continuous soil sampling

QUOTE

Singley Environmental & Remediation Services Singley Construction Company

6741 Pine Forest Road Pensacola, Florida 32526

Actual number of drums used will be invoiced at $77 ea.

2 nights per diem / 3 man crew

10) 30' x 2 monitoring wells with 15' screenfrom 15'-30', 2) 45' x 2 monitoring wells with 5' screen from 40'-45' Installed via H.S.A.

sloneal Line sloneal Line sloneal Callout sloneal Callout sloneal Callout $26,865 sloneal Line sloneal Line

547 North Monroe Street, Suite 201 Tallahassee, Florida 32301

Phone: 850-222-3975 Email: driller@jsna.com

Client Information Project Information

Company: Terracon Location: Date: 3/9/2023 Client Rep: Tom Lewis

Phone: Project Type: Crew: 2-man Email: Rig/Equip: Duration: 9 days

Proposed Scope of Work

Column1 Column2 Column3 Column4 Column5 Column6 Quantity Price Unit Cost Total Drilling Services 2" Monitor Well Drilling (includes Equipment, Crew, Decon, etc.) 390 $28.50 Feet $11,115.00 DPT Soil Sample Collection 390 $10.00 Feet $3,900.00 Well Completion (Manhole, Pad, Development-30 mins) 12 $295.00 Each $3,540.00

Subtotal $18,555.00 Moblization Job Prep and Mob/Demob - Drilling Services 1 $750.00 LS $750.00

Subtotal $750.00 Consumable Materials / Misc. Equipment / Other Related Items Permits (includes permit fee, permitting, completion reports, etc.) 1 $150.00 LS $150.00 2" PVC Well Installation 390 $13.75 Feet $5,362.50 55-gallon drum (does NOT include disposal) 45 $75.00 Each $3,375.00

Subtotal $8,887.50

Total Cost $28,192.50

Ben Rush Acceptance of Above Rates Date JSA Drilling Division Phone: 850-445-3459 Email: brush@jsna.com

This is a cost estimate subject to our stand terms and conditions, not a fixed price bid. Due to the variable nature of subsurface conditions, site acess constraints, and/or site specific information not made known to JSA prior to mobilization, work will be billed on the above unit costs unless otherwise agreed in writing. The client will be responsible for loss or damage to any and all equipment and any associated extra costs, as a result of adverse, risky or unknown site conditions, by requesting field staff to attempt work that is normally beyond the capabilities of the equipment. The client is responsible for any disposal of Investigation Derived Waste (IDW) generated during services unless otherwise stated. At JSA's discretion, a restock fee may be imposed on the invoice for well materials not utilized due to changes in scope by client. Payment terms are net 30 days upon receipt of invoice unless otherwise stated in writing prior to initiation of work.

Jim Stidham & Associates, Inc.

JSA Drilling Division

COST PROPOSAL

Rose Printing 2503 Jackson Bluff Rd, Tallahassee, FL DPT/Drilling AMS 9700 Combo

Install (10) 2-inch MWs to 30 feet bls with 15' screen and (2) 2-inch MWs to 45 feet bls with 5' screen. Prior to installing wells, a soil boring will be advanced with DPT at each location to provide continous soil cores for lithology description and screening. Each well will be completed with filter sand pack, fine sand pack, grout, 2'x2' concrete well pad, 8" manhole and developed.

All drilling IDW and development water will be containerized in 55-gallon drums. Client responsible for IDW disposal.

Includes NWFWMD construction permits and completion reports.

Jim Stidham & Associates, Inc. (“JSA”)

TERMS AND CONDITIONS

ACCEPTANCE & CONSIDERATION& TERM: By authorizing Jim Stidham & Associates, Inc. (JSA) to commence work, Client agrees to these terms and conditions and JSA agrees to perform work and/or extend credit in exchange.

PAYMENT & INTEREST: Invoices will be submitted by JSA once a month with payment due from Client within 30 days of the invoice date. At JSA’s discretion, interest at the rate of 1½% per month (18% per annum) will be charged on the principal amount owing after the due date.

DISCLAIMER OF WARRANTY: JSA will exercise reasonable skill and judgment in performing its work. All express or implied guarantees, representations and warranties, including, without limitation, any implied warranty of merchantability, fitness for a particular purpose, whether written or oral, are hereby excluded and are expressly disclaimed by JSA. JSA does not warrant any specific results of any kind. To the extent an implied guarantee, representation, or warranty, cannot be excluded, JSA’S LIABILITY, IF ANY, IS LIMITED TO THE AMOUNT PAID BY CLIENT TO JSA, AND SHALL IN NO EVENT EXCEED THAT AMOUNT.

LIMITATION OF LIABILITY: JSA shall not be liable to Client or any other party for damages of any type, including, but not limited to, indirect, consequential, incidental, special, or punitive damages, whether arising out of contract, negligence, tort, warranty, strict liability or any other legal theory. JSA’S LIABILITY, IF ANY, IS LIMITED TO

THE AMOUNT PAID BY CLIENT TO JSA, AND SHALL IN NO EVENT EXCEED THAT AMOUNT.

NOTICE OF CLAIM: Any and all claims related to or arising from JSA’s work shall be made in writing to JSA within one (1) year after JSA’s completion of its work. Any subsequent claims are waived.

DELAYS/CONDITIONS BEYOND JSA’S CONTROL: JSA shall not be liable for delays in performance beyond JSA’s control, including, but not limited to, acts of third parties, inability to obtain permits, fire, earthquake, flood, windstorm or other natural disasters, labor stoppages, lockouts, strikes or other differences with employees, war, riot, embargoes, or stoppages created by any government agency or authority. JSA’s liability, if any, is limited as provided in the limitation of liability provision.

JOB SITE SAFETY: JSA is not responsible for providing safety monitoring for the site on behalf of Client or any other trade on site. If JSA observes that safety monitoring is not being performed in strict compliance with the site-specific health and safety plan, applicable federal, state or local laws, and/or as contractually required, JSA may cease operations and go on standby until safety monitoring is resumed. JSA shall be entitled to an equitable adjustment in its contract price, including standby time, and for time to perform its work.

INFORMATION: Client has superior knowledge of the job site, site history, access routes to the job site, known or suspected contaminants, surface and subsurface conditions, etc. The Client is obligated to advise JSA of all or any conditions that may affect JSA’s work. Client agrees to provide JSA with such specifications, plans, site history information, reports, studies or other information on surface and subsurface conditions as will be reasonably required by JSA for safe, proper and timely performance of its work. Client shall locate all underground utilities and structures. Client shall obtain all necessary permits and rights-of-way and indemnify, defend, and hold JSA harmless for its failure to do so and for claims of trespass or damage to property, including underground utilities or structures, which arise out of the performance of JSA’s work.

DISPOSAL: JSA is not, and has no authority to act as a generator, operator, treater, storer, transporter or disposer of hazardous waste, substances, pollutants or contaminants found or identified at the site. JSA shall have no responsibility for the transportation, storage, treatment or disposition of contaminated or potentially contaminated waste materials of any kind which are directly or indirectly generated from JSA’s performance of work, other than hazardous wastes, substances, pollutants or contaminants brought to the work site by JSA. Client or its agents shall be responsible for the disposal of any such waste materials.

CHANGED CONDITIONS: The discovery of any hazardous waste, substance, pollutant, contaminant, underground obstruction, condition or utilities on or under the job site which were not brought to the attention of JSA prior to JSA commencing work, and which create health and safety risks, or requires JSA to perform work outside the original scope or beyond its capabilities, will constitute a materially different site condition entitling JSA to immediately terminate its work (and to receive payment for all work performed up to and including the date of termination). If JSA elects to continue its work, it is entitled to receive an equitable adjustment in its contract price, including standby time, and for time to perform its work.

REMEDIATION TERMS: JSA is not responsible for the remediation design and bears no responsibility for the remediation results or impact to existing conditions.

Notwithstanding anything contained here within this agreement to the contrary, Client indemnifies, holds harmless and shall defend JSA and its affiliates, directors, officers, employees, agents and Subcontractors against any claims or actions, including third party claims or actions, arising from any remediation design, results or impact to existing conditions.

INDEMNIFICATION: Client agrees to indemnify, defend, and hold JSA and its agents harmless from and against any and all claims, demands, causes of action (including third party claims for contribution or indemnification), liability and costs (including attorneys’ fees and other costs of defense) which result from (i) any release or threatened release of any substance (whether hazard or not); (ii) any claim that JSA, or any of its subcontractors was a “generator” or “transporter” of hazardous waste or an “operator” of the job site (as such terms are used or defined under local, state or federal laws or regulations); or (iii) any negligent or wrongful act or omission of Client or others under Client’s control, except the duty to indemnify, defend, and hold harmless shall not apply to the extent any demand or cause of action results solely from JSA’s negligence or willful misconduct.

INCORPORATION CLAUSE: All work performed by JSA is subject to these terms and conditions. All terms and conditions contained in JSA’s bids, proposals, and invoices, as now exist and as may be modified, are expressly incorporated herein by this reference and made a part of the terms and conditions.

INTEGRATION: The terms and conditions stated herein constitute the entire understanding of the parties relating to JSA’s work. All previous proposals, offers, and other communications relative to the work, oral or written, are hereby superseded. Any additional or conflicting provision(s) contained in any purchase order, acknowledgment, contract, or other form of the Client is hereby expressly objected to by JSA and shall not modify these terms and conditions.

ATTORNEYS’ FEES & COSTS: The prevailing party shall be entitled to recover all of its costs, fees and expenses incurred in any dispute regarding collecting the balance due, enforcing the terms and conditions, or pertaining to JSA’s work. Such fees and expenses shall include attorneys’ fees, recording fees, and title report fees whether or not legal proceedings are instituted, and if instituted, shall include all other costs, fees expenses and, including without limitation, court costs and expert witness fees incurred in the trial/arbitration, appellate proceedings, and post-judgment.

APPLICABLE LAW/JURISDICTION & VENUE: Any lawsuit to collect the balance due, enforce the terms and conditions, or that pertains to JSA’s work shall be governed by the laws of the State of Florida, USA. Client agrees that if a lawsuit or action is necessary that it shall be brought in Superior Court for Leon County, Florida. In the event that such lawsuit or action includes enforcement of a real property lien, such action shall be brought in the county and state in which the real property is located.

SEVERABILITY: If any of these terms and conditions are determined to be invalid or unenforceable, such determination shall not affect the validity and enforceability of the remaining terms and conditions.

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Sid O’Neal

Terracon

3559 Timberlane School Road

Tallahassee, FL 32312

August 4, 2022

Re: Non-Hazardous Drum Disposal – State of Florida

Mr. O’Neal:

The price for the transportation and disposal (T&D) of drums of non-hazardous soil, mud and water located in the State of Florida is listed below.

Non-Hazardous Drums:

Description Rate Unit

False Mobilization (No drum found) $ 70.00 Per Stop

T&D - Non-Haz Soil, Mud or Water $ 110.00 Per Drum

The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida

Keys. Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

A single False Mobilization fee will apply if our driver is not able to locate a drum on site.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

O'Neal, Sid L

From: Penfield, Ryan L <rpenfield@harsco.com> Sent: Wednesday, March 9, 2022 12:09 PM To: O'Neal, Sid L Subject: RE: :EXTERNAL: RFQ - Non-Haz T&D

Hello Sid, Non haz liquids (NH-L-20) $65 per drum Non haz solids (NH-S-10) $63 per drum 15% EEI on total disposal

Transportation (excluding the KEYS) Stop fee $100 Per Drum Trans $45 FSC based upon DOE currently 55% of total trans

This will be good for all of Florida except the keys.

Ryan Penfield

Environmental Specialist

M 843.562.7841 O 1.800.739.9156 rpenfield@harsco.com www.cleanearthinc.com 402 Webster Chapel Road, Glencoe, AL 35905

From: O'Neal, Sid L <Sid.O'neal@terracon.com> Sent: Wednesday, March 9, 2022 11:59 AM To: Penfield, Ryan L <rpenfield@harsco.com> Subject: :EXTERNAL: RFQ - Non-Haz T&D

Hi Larry, Was just following up from yesterday’s phone call in case you have my email wrong.

You don't often get email from sid.o'neal@terracon.com. Learn why this is important

Need quote for Non-Haz Drum T&D – soil and gw waste for all Florida regions covering north, central, and south regions

Thanks, Sid O’Neal Senior Scientist I Environmental

3559 Timberlane School Road I Tallahassee, Florida 32312 D (850) 692-7189 I F (850) 692-7186 I M (229) 400-5108 sid.oneal@terracon.com I Terracon.com

Terracon provides environmental, facilities, geotechnical, and materials consulting engineering services delivered with responsiveness, resourcefulness, and reliability.

Private and confidential as detailed here (www.terracon.com/disclaimer). If you cannot access the hyperlink, please e-mail sender.

CAUTION : This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.

Whatever Waste, LLC 904.881.1957

3834 Mandarin Woods Dr. No.

Jacksonville, Florida

32223 United States

Overview RE: Non-hazardous Waste Drum Transport & Disposal LOC: North Florida (Jacksonville >< Pensacola) Central Florida (Greater Orlando >< Greater Tampa)

Good day Sid and Tom:

Whatever Waste appreciates the opportunity to price non-hazardous waste drums at facilities or sites throughout the North and Central Florida regions.

Overview Manifest, transport and dispose of non-hazardous petroleum contaminated soil, solids or liquids (including but not limited to PCW, IDW, groundwater, well drilling, and tank cleaning) in 55-gallon DOT shippable drums

Pricing

Prepared For Sid O'Neal Sr. Scientist

Terracon 3559 Timberlane School Road

Tallahassee, FL 32312

Proposal Number 030822.1

Proposal Date 03/08/2022

Description Rate Qty Line Total

Solids or Liquids Drums (each)

$150.00 1 $150.00

$0.00 1 $0.00

Notes Pricing includes assisting with waste profiling and analytical testing advisement unless the waste stream falls under a blanket profile.

Pricing and non-hazardous disposal acceptance of the drums is based on the waste being on-specification and RCRA non-hazardous. Required analytical testing data TBD based on disposal facility requirements DOT shippable drums must be on a hard surface and accessible location.

Drum pickup time frame can range from one week to several weeks based on location Whatever Waste also quotes hazardous waste drum transport and disposal

Terms

Whatever Waste will invoice actual amounts or volumes unless minimum quantities apply Due to pricing volatility in national and international energy sectors the non-hazardous waste drum transport and disposal rate will increase by $15.00 per drum for every $0.50 per gallon over $5.00 per gallon No-load stop fee if called off in transit or on-site $125.00 Payment is due in 30 days from email receipt of invoice

Sid O'Neal Sr. Scientist, Terracon

Subtotal

Tax

150.00

0.00

Proposal Total (USD) $150.00

File details come from the government source that posted it. Updated .