This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) under Contract Number HW687 to Terracon Consultants, Inc. for groundwater monitoring and reporting services at the Markham's Maytag Laundry (former) facility (ERIC_3989) located in Alachua, Florida. The task assignment was executed on June 23, 2022, with a completion date of October 31, 2022. Dean Cox serves as the Department Project Manager, while Donna Cline represents Terracon as the contractor's project manager.

The task assignment authorizes costs for site reconnaissance, groundwater monitoring and reporting, equipment, sample shipping and analysis, and waste disposal activities. The total contract value is $11,683.60 on a fixed unit rate basis, comprising 62.08 hours of labor. The scope of work includes sampling from 11 monitoring wells for volatile organic compounds (VOCs) using EPA 8260 short-list analysis, with water level measurements from five additional wells. Associated costs include analytical testing at $693.00, sample shipping at $123.50, vehicle rental and per diem at $968.00, field equipment and expendables at $2,329.00, and waste disposal through Erwin Remediation at $100.00. The deliverable is an Annual Groundwater Monitoring Report due by August 31, 2022. The cost was negotiated downward by $923.59 from the original proposal, with labor hours reduced by 6.51 hours. The monitoring is designed to identify current drycleaning solvent concentrations, specifically PCE, which was previously detected above the Groundwater Cleanup Target Level (GCTL) in 2020.

View the file

Other files

File Type Posted
CN-370000-HW687-BF01ACO1.pdf PDF
CN-370000-HW687-BF03ACO1.pdf PDF
CN-370000-HW687-BIL01A.pdf PDF
CN-370000-HW687-BIL2ACO1.pdf PDF
CN-370000-HW687-BIL2BCO1.pdf PDF
CN-370000-HW687-BIL2CCO1.pdf PDF
CN-370000-HW687-BIL3ACO2.pdf PDF
CN-370000-HW687-BIO1ACO1.pdf PDF
CN-370000-HW687-DC001A.pdf PDF
CN-370000-HW687-DC003A.pdf PDF
CN-370000-HW687-DC003D.pdf PDF
CN-370000-HW687-DC005D.pdf PDF
CN-370000-HW687-DC006A.pdf PDF
CN-370000-HW687-DC006B.pdf PDF
CN-370000-HW687-DC008C.pdf PDF
CN-370000-HW687-DC010A.pdf PDF
CN-370000-HW687-DC010B.pdf PDF
CN-370000-HW687-DC011F.pdf PDF
CN-370000-HW687-DC011H.pdf PDF
CN-370000-HW687-DC012D.pdf PDF
CN-370000-HW687-DC013C.pdf PDF
CN-370000-HW687-DC015C.pdf PDF
CN-370000-HW687-DC019A.pdf PDF
CN-370000-HW687-DC01ACO2.pdf PDF
CN-370000-HW687-DC020A.pdf PDF
CN-370000-HW687-DC020B.pdf PDF
CN-370000-HW687-DC020C.pdf PDF
CN-370000-HW687-DC020D.pdf PDF
CN-370000-HW687-DC023C.pdf PDF
CN-370000-HW687-DC025B.pdf PDF
CN-370000-HW687-DC025C.pdf PDF
CN-370000-HW687-DC025F.pdf PDF
CN-370000-HW687-DC027B.pdf PDF
CN-370000-HW687-DC027C.pdf PDF
CN-370000-HW687-DC02BCO1.pdf PDF
CN-370000-HW687-DC02CCO2.pdf PDF
CN-370000-HW687-DC02DCO1.pdf PDF
CN-370000-HW687-DC02HCO1.pdf PDF
CN-370000-HW687-DC032A.pdf PDF
CN-370000-HW687-DC034A.pdf PDF
CN-370000-HW687-DC034C.pdf PDF
CN-370000-HW687-DC034D.pdf PDF
CN-370000-HW687-DC035F.pdf PDF
CN-370000-HW687-DC036A.pdf PDF
CN-370000-HW687-DC03CCO1.pdf PDF
CN-370000-HW687-DC041C.pdf PDF
CN-370000-HW687-DC041D.pdf PDF
CN-370000-HW687-DC048A.pdf PDF
CN-370000-HW687-DC048B.pdf PDF
CN-370000-HW687-DC04BCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW687

DC015A Completion October 31, 2022

This task assignment (TA) authorizes costs for site reconnaissance and groundwater monitoring & reporting, along with associated costs for equipment, sample shipping and analysis, and waste disposal. The total cost of this TA is $11,683.60 with 62.08 hours of labor. The entire cost of this TA is fixed unit rate.

Dean Cox 850-245-8969 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Terracon Consultants, Inc.

Terracon Consultants, Inc.

Donna Cline 813-321-0340

ERIC_3989

15093 US 441, Alachua

Markham's Maytag Laundry (former)

✔ $ 11,683.60

$ 11,683.60

Scope of Work

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.06.23 11:29:06 -04'00'

N/A dlcline Typewriter Donna Cline dlcline Typewriter Senior Remediation Engineer dlcline Typewriter 06/23/22

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report 08/31/2022

Groundwater Monitoring Report (Subtask 1 Project Management and Subtask 2 Site Reconnaissance, Groundwater Monitoring & Reporting) $ 11,683.60

$ 11,683.60

HW687

DC015A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Interim Secretary

Memorandum

TO: HW687 Contract File FROM: Dean Cox, Contract Manager SUBJECT: DC015A GW Monitoring – Markham’s Maytag Laundry (former) ERIC_3989

DATE: 6/20/2022

This task assignment (TA) authorizes costs for site reconnaissance and groundwater monitoring & reporting, along with associated costs for equipment, sample shipping and analysis, and waste disposal. The total cost of this TA is $11,683.60 with 62.08 hours of labor. The entire cost of this TA is fixed unit rate.

The cost of this TA was negotiated. Labor costs were reduced by 6.51 hours from the original proposal. The total cost of this TA is $923.59 less than the original proposal.

This groundwater monitoring TA is designed to identify current drycleaning solvent compound concentrations. Only PCE was detected above the GCTL in the previous groundwater monitoring event, completed in 2020. Three wells had PCE above the GCTL in that 2020 event, with a high of 63 ug/L. Site access has been verified.

FDEP COST ESTIMATE

Contractor: Terracon

Date: 5/26/2022 Task #: SubTask 1 Project Management SubTask 6

Site: Markhams Maytag Laundry, ERIC_3989 SubTask 2 Site Recon, Groundwater Monitoring and Reporting SubTask 7 Activity/Phase: Site Recon, Groundwater Monitoring and Reporting SubTask 3 SubTask 8

Project Manager: Dean Cox SubTask 4 SubTask 9 SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$70.19 Project Manager Tom Lewis 4.08 4.08 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$20.50 CADD Specialist Oscar Encalada 3.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Environmental Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$29.81 Field Scientist Darryl Williams 31.00 31.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Geologist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$31.25 Project Scientist A. Rodriguez-Baz 4.50 4.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$55.29 Senior Geologist Luke Davis 19.50 19.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 62.08 4.08 58.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $2,490.97 $286.57 $2,204.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $2,889.52 $332.42 $2,557.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $1,401.42 $161.22 $1,240.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,781.91 $780.21 $6,001.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 1

FDEP COST ESTIMATEContractor: Terracon Date: 5/26/2022

Task #: SubTask 1 Project Management SubTask 6 Site: Markhams Maytag Laundry, ERIC_3989 SubTask 2 Site Recon, Groundwater Monitoring and Reporting SubTask 7

Activity/Phase: Site Recon, Groundwater Monitoring and Reporting SubTask 3 SubTask 8 Project Manager: Dean Cox SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $560.00 $560.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $408.00 $408.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $968.00 $968.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin Remediation $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $693.00 $693.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $123.50 $123.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $816.50 $816.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,575.00 $1,575.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $534.00 $534.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $2,329.00 $2,329.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $11,005.41 $780.21 $10,225.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $678.19 $78.02 $600.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $11,683.60 $858.23 $10,825.37 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Markhams Maytag Laundry, ERIC_3989 SUBTASK 2: Groundwater Monitoring and Reporting

PROPOSAL NO. PHF227057

DATE: 5/26/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Initial Site Visit to Evaluate Site Conditions Senior Geologist LD 1.00 Senior Geologist LD 3.50 Senior Geologist LD Site walk-around, locate and evaluate site and off-site monitoring wells, and general site conditi 1.50 Senior Geologist LD Meet with site owner to coordinate site access to interior wells 1.00

Field Task Planning and Groundwater Sampling Senior Scientist AK 0.50 Senior Scientist LD 1.50 Project Scientist DW Load/unload 1.00 Project Scientist DW Mobilization/Demobilization (from Jacksonville to Alachua) 1.00 Project Scientist DW Access wells and replace locks (16 wells) 3.50 Project Scientist DW Collect groundwater levels ( 16 wells,10 minutes per well) 2.50 Project Scientist DW Collect deep groundwater samples (11 wells, 2 hours each) 22.00 Project Scientist DW Containerize IDW 1.00

Report Deliverable Project Scientist AK Prepare report tables, trend graphs and draft maps 4.00 Senior Geologist LD Prepare report 6.00 Senior Geologist LD QA/QC field and laboratory data 1.00 Senior Geologist LD Summarize Water Quality Parameters and Trend Graphs 1.00 Senior Geologist LD Summarize Groundwater Analytical Results 2.00 Senior Geologist LD Conclusions/Recommendations 1.00

GIS Technician OE Prepare base figures and Exhibits (groundwater flow and concentrations maps) 3.00

TOTAL LABOR 58.0

VEHICLE TYPE RATE UNIT USEAGE

Automobile (Initial site visit) 80 day 1 $80.00

Truck (groundwater sampling) 120 day 3 $360.00 Truck (IDW pickup) 120 day 1 $120.00

TOTAL VEHICLE $560.00

PER DIEM STAFF RATE UNIT USEAGE

Lodging Field Scientist $150.00 night 2 $300.00 Meals Field Scientist $36.00 day 3 $108.00

TOTAL PER DIEM $408.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin Remediation IDW Disposal 100.00$ each 1 $100.00

Subcontractor Handling Fee 10% $10.00

TOTAL SUBCONTRATOR $110.00

Mobilization/Demobilization (from Jacksonville to Alachua) Prepare Health and Safety Plan

Request sample kit PreTask Planning, prepare field sampling SOW/coordinate site access

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Markhams Maytag Laundry, ERIC_3989 SUBTASK 2: Groundwater Monitoring and Reporting

PROPOSAL NO. PHF227057

DATE: 5/26/2022

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs EPA 8260 (short list) 63.00$ 11 $693.00 Sample Shipping Small Cooler (2 day) 52.00$ 2 $104.00 Sample Shipping Ice 6.50$ 3 $19.50

TOTAL LAB $816.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Site Reconnaisance kit 150.00$ day 1 $150.00 Deep groundwater sampling kit 415.00$ day 3 $1,245.00 Tubing, HDPE (1/2 x 5/8) 0.40$ ft 825 $330.00 Expendables 40.00$ day 3 $120.00 Lock, key operated 7.00$ ea 16 $112.00 Well Cap, 2" 17.00$ ea 16 $272.00 55-gallon drum, new 100.00$ drum 1 $100.00

TOTAL EQUIPMENT $2,329.00

Ranking by fee

Sub Solids non-haz 55-gal drum

Liquids non-haz

55-gal drum Additional pricing conditions

Minority Y/N

Regions* Contact Name Contact # email

1 Erwin Remediation 100.00$ 100.00$ all inclusive No All Johnathan Erwin 850-292-6511 erwinremediation@gmail.com

2 Clean Earth $63+$45=$108 $65+$45 =$110 15% EEI on total disposal, stop fee $100, 55% FSC of total transportation

No All Ryan Penfield 843-562-7481 rpenfield@harsco.com

3A Whatever Waste 150.00$ 150.00$ all included No North and

Central Florida

John 904-881-1957 John@whateverwaste.com

3B Whatever Waste 200.00$ 200.00$ all included No South Florida

John 904-881-1957 John@whateverwaste.com

* Regions that are specified with "All" of Florida, are not inclusive of the Keys

Erwin Remediation is the selected IDW Contractor

IDW Contractors, All of Florida (Except the Keys)

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Sid O’Neal

Terracon

3559 Timberlane School Road

Tallahassee, FL 32312

March 4, 2022

Re: Non-Hazardous Drum Disposal – State of Florida

Mr. O’Neal:

The price for the transportation and disposal (T&D) of drums of non-hazardous soil, mud and water located in the State of Florida is listed below.

Non-Hazardous Chlorinated VOHs, Petroleum and Metals:

Description Rate Unit

T&D - Non-Haz Soil $ 100.00 Per Drum

T&D - Non-Haz Mud/Water $ 100.00 Per Drum

The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida

Keys. Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

Cline, Donna L

From: O'Neal, Sid L Sent: Wednesday, March 9, 2022 12:12 PM To: Cline, Donna L; Wing, Lydia; Lewis, Tom E Subject: FW: :EXTERNAL: RFQ - Non-Haz T&D

Here’s an email quote from Clean Earth. Should be the final one needed

Thanks, Sid O’Neal Senior Scientist I Environmental

3559 Timberlane School Road I Tallahassee, Florida 32312 D (850) 692-7189 I F (850) 692-7186 I M (229) 400-5108 sid.oneal@terracon.com I Terracon.com

From: Penfield, Ryan L <rpenfield@harsco.com> Sent: Wednesday, March 9, 2022 12:09 PM To: O'Neal, Sid L <Sid.O'neal@terracon.com> Subject: RE: :EXTERNAL: RFQ - Non-Haz T&D

Hello Sid, Non haz liquids (NH-L-20) $65 per drum Non haz solids (NH-S-10) $63 per drum 15% EEI on total disposal

Transportation (excluding the KEYS) Stop fee $100 Per Drum Trans $45 FSC based upon DOE currently 55% of total trans

This will be good for all of Florida except the keys.

Ryan Penfield

Environmental Specialist

M 843.562.7841 O 1.800.739.9156 rpenfield@harsco.com www.cleanearthinc.com

402 Webster Chapel Road, Glencoe , AL 35905

From: O'Neal, Sid L <Sid.O'neal@terracon.com> Sent: Wednesday, March 9, 2022 11:59 AM To: Penfield, Ryan L <rpenfield@harsco.com> Subject: :EXTERNAL: RFQ - Non-Haz T&D

Hi Larry, Was just following up from yesterday’s phone call in case you have my email wrong.

Need quote for Non-Haz Drum T&D – soil and gw waste for all Florida regions covering north, central, and south regions

Thanks, Sid O’Neal Senior Scientist I Environmental

3559 Timberlane School Road I Tallahassee, Florida 32312 D (850) 692-7189 I F (850) 692-7186 I M (229) 400-5108 sid.oneal@terracon.com I Terracon.com

Terracon provides environmental, facilities, geotechnical, and materials consulting engineering services delivered with responsiveness, resourcefulness, and reliability.

Private and confidential as detailed here (www.terracon.com/disclaimer). If you cannot access the hyperlink, please e-mail sender.

CAUTION : This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.

You don't often get email from sid.o'neal@terracon.com. Learn why this is important

Whatever Waste, LLC 904.881.1957

3834 Mandarin Woods Dr. No.

Jacksonville, Florida

32223 United States

Overview RE: Non-hazardous Waste Drum Transport & Disposal LOC: North Florida (Jacksonville >< Pensacola) Central Florida (Greater Orlando >< Greater Tampa)

Good day Sid and Tom:

Whatever Waste appreciates the opportunity to price non-hazardous waste drums at facilities or sites throughout the North and Central Florida regions.

Overview Manifest, transport and dispose of non-hazardous petroleum contaminated soil, solids or liquids (including but not limited to PCW, IDW, groundwater, well drilling, and tank cleaning) in 55-gallon DOT shippable drums

Pricing

Prepared For Sid O'Neal Sr. Scientist

Terracon 3559 Timberlane School Road

Tallahassee, FL 32312

Proposal Number 030822.1

Proposal Date 03/08/2022

Description Rate Qty Line Total

Solids or Liquids Drums (each)

$150.00 1 $150.00

$0.00 1 $0.00

Notes Pricing includes assisting with waste profiling and analytical testing advisement unless the waste stream falls under a blanket profile.

Pricing and non-hazardous disposal acceptance of the drums is based on the waste being on-specification and RCRA non-hazardous. Required analytical testing data TBD based on disposal facility requirements DOT shippable drums must be on a hard surface and accessible location.

Drum pickup time frame can range from one week to several weeks based on location Whatever Waste also quotes hazardous waste drum transport and disposal

Terms

Whatever Waste will invoice actual amounts or volumes unless minimum quantities apply Due to pricing volatility in national and international energy sectors the non-hazardous waste drum transport and disposal rate will increase by $15.00 per drum for every $0.50 per gallon over $5.00 per gallon No-load stop fee if called off in transit or on-site $125.00 Payment is due in 30 days from email receipt of invoice

Sid O'Neal Sr. Scientist, Terracon

Subtotal

Tax

150.00

0.00

Proposal Total (USD) $150.00

Whatever Waste, LLC 904.881.1957

3834 Mandarin Woods Dr. No.

Jacksonville, Florida

32223 United States

Overview RE: Non-hazardous Waste Drum Transport & Disposal LOC: South Florida (south of Lake Okeechobee north end) Florida Keys

Good day Sid and Tom:

Whatever Waste appreciates the opportunity to price non-hazardous waste drums at facilities or sites throughout South Florida and the Florida Keys.

Overview Manifest, transport and dispose of non-hazardous petroleum contaminated soil, solids or liquids (including but not limited to PCW, IDW, groundwater, well drilling, and tank cleaning) in 55-gallon DOT shippable drums

Pricing

Prepared For Sid O'Neal Sr. Scientist

Terracon 3559 Timberlane School Road

Tallahassee, FL 32312

Proposal Number 030822.2

Proposal Date 03/08/2022

Description Rate Qty Line Total

Solids or Liquids Drums (each) (South Florida)

$200.00 1 $200.00

Solids or Liquid Drums (each) (Florida Keys)

$275.00 1 $275.00

Notes Pricing includes assisting with waste profiling and analytical testing advisement unless the waste stream falls under a blanket profile.

Pricing and non-hazardous disposal acceptance of the drums is based on the waste being on-specification and RCRA non-hazardous. Required analytical testing data TBD based on disposal facility requirements DOT shippable drums must be on a hard surface and accessible location.

Drum pickup time frame can range from one week to several weeks based on location Whatever Waste also quotes hazardous waste drum transport and disposal

Terms

Whatever Waste will invoice actual amounts or volumes unless minimum quantities apply Due to pricing volatility in national and international energy sectors the non-hazardous waste drum transport and disposal rate will increase by $15.00 per drum for every $0.50 per gallon over $5.00 per gallon No-load stop fee if called off in transit or on-site $175.00 Payment is due in 30 days from email receipt of invoice

Sid O'Neal Sr. Scientist, Terracon

Subtotal

Tax

475.00

0.00

Proposal Total (USD) $475.00

DC015A.pdf
DC015A memo.pdf
CEF-LOE220620.pdf
Cost Estimate
LOE Subtask 2
DC015Aproposal220607_Page_5.pdf
DC015Aproposal220607_Page_6.pdf
DC015Aproposal220607_Page_7.pdf
IDWbids.pdf
ErwinRemediation Quote - Terracon - Drum - All Regions - 03.04.2022
Clean Earth
Whatever Waste - Drum Quote Proposal 030822.1
Whatever Waste Proposal 030822.2 - South Region