This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Terracon Consultants, Inc. for environmental remediation services at Miller Machinery & Supply Co, located in Tampa, Hillsborough County, Florida. The work is authorized under Contract Number HW687, an indefinite delivery vehicle. The project is identified as ERIC_4733 and is managed by FDEP Project Manager Gabriel Sostre and Contractor Project Manager Donna Cline.
Terracon will conduct a supplemental site assessment consisting of 11 soil borings with samples collected at three depth intervals, six Modified Active Gas Survey (MAGS) well installations and testing, investigative derived waste management, and preparation of a letter report documenting findings. The work is valued at $37,354.74 on a fixed unit rate basis, with 210 total labor hours. Deliverables include soil sampling and MAGS investigation due April 11, 2025; IDW management due May 16, 2025; and project management and reporting due July 11, 2025. Payment is structured in two invoicing milestones: $30,470.04 upon submittal and FDEP approval of the short letter report documenting MAGS results, and $6,884.70 upon submittal and approval of the final letter report. The task assignment is effective through September 19, 2025, and was authorized on December 18, 2024.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW687
DC020C Completion September 19, 2025
This Task Assignment authorizes Terracon to conduct Supplemental Site Assessment at Miller Machinery Co #2 in accordance with the November 25, 2024 Scope of Work, Cost Estimate, and Bid Documentation.
Gabriel Sostre 850-245-8749 Contractor Terracon Consultants, Inc. Contractor
Contractor Donna Cline Contractor 904-479-7415
ERIC_4733
1920 Tampa East Boulevard, Tampa, Hillsborough County
Miller Machinery & Supply Co
Contractor Contractor
✔ $ 37,354.74
$ 37,354.74
Scope of Work
Terracon Consultants, Inc.
Contractor Donna Cline
Senior Associate / Remediation Engineer Digitally signed by Cline, Donna L DN: cn=Cline, Donna L, ou=General Users, email=Donna.Cline@terracon.com Date: 2024.12.18 09:25:13 -05'00'
Cline, Donna L
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.12.17 16:29:22 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
BWC TAFORM 01/18
HW687
DC020C
Subtask 3 - IDW Management
Subtasks 1 & 4 - Project Management; Reporting
Subtask 2 - Soil Sampling and MAGS Investigation 04/11/2025
05/16/2025
07/11/2025
Subtasks 2 & 3 - Submittal and FDEP approval of a short letter report documenting MAGS results and field logs
Subtasks 1 & 4 - Submittal and FDEP approval of the Letter Report documenting field activities, MAGS results, and laboratory data for soil and vapor samples
$ 30,470.04
$ 6,884.70
$ 37,354.74
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette NNuñez Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO:
FROM:
Negotiation File Miller Machinery and Supply Co Tampa, Hillsborough County
ERIC_4733
, Project Manager
SUBJECT: Negotiation Summary Task Assignment DC020C (HW687)
DATE: November , 2024
This Task Assignment authorizes Terracon Consultants, Inc. (Terracon) to conduct Supplemental Site
Assessment at the Miller Machinery and Supply Co site. In an effort to address potential data gaps in the vadose zone, the FDEP and Terracon agreed to conduct further soil assessment. This will consist of 11 soil borings with samples collected at three depth intervals (0.5ft bgs, 2ft bgs, and 4ft bgs). Six of the 11 boring locations are to be completed as MAGS wells which will be subsequently sampled. Discussions on the scope of work are included below.
The total cost for this project is $37, . with total labor hours. All work is to be completed in accordance with the , 2024, Scope of Work, Cost Estimate, and Bid Documentation.
Terracon may invoice according to the included schedule.
FDEP COST ESTIMATEContractor: Terracon Date: 11/25/2024
Task #: SubTask 1 Project Management Site: Miller Machinery (ERIC_4733) SubTask 2 Soil Sampling, MAGS Survey
Activity/Phase: Supplemental Soil and MAGS Investigation SubTask 3 IDW Management Project Manager: Patrick McGrane SubTask 4 Report Preparation
SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$70.14 Project Manager Donna Cline 14.52 14.52 $33.31 CADD Specialist Chelsea Fugate 4.00 0.00 0.00 4.00 0.00 $57.50 Senior Geologist Charles McCrackin 11.50 11.50 0.00 0.00 0.00 $23.50 Environmental Technicia Harvey Peach 29.00 26.50 2.50 0.00 0.00 $45.00 Senior Scientist/Enginee Mui Michael 44.00 32.00 0.00 12.00 0.00 $46.72 Senior Scientist Andrew Kucek 61.00 50.00 1.00 10.00 0.00 $70.14 Senior Engineer Donna Cline 2.00 0.00 0.00 2.00 0.00 $31.85 Staff Engineer Eddy Leon 43.50 43.50 0.00 0.00 0.00
Total Hours 209.52 14.52 163.50 3.50 28.00 0
Direct Labor $8,849.79 $1,018.12 $6,445.48 $105.47 $1,280.72 $0.00
Overhead 116.00% $10,265.77 $1,181.02 $7,476.76 $122.35 $1,485.64 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $4,978.89 $572.79 $3,626.23 $59.34 $720.53 $0.00 Total Labor $24,094.45 $2,771.93 $17,548.47 $287.16 $3,486.89 $0.00
Travel Vehicle Rental $1,440.00 1,320.00$ 120.00$ $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 -$ $0.00 $0.00 $0.00 Total Travel $1,440.00 $1,320.00 $120.00 $0.00 $0.00
Subcontractor (Equipment Procurement) MAGS well materials $1,161.22 1,161.22$ $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $1,161.22 $1,161.22 $0.00 $0.00 $0.00 Procurement Fee $116.12 $116.12 $0.00 $0.00 $0.00 Total Subcontractor Cost $1,277.34 $1,277.34 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Petrotech $535.00 $0.00 535.00$ $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $535.00 $0.00 $535.00 $0.00 $0.00 Handling Fee $53.50 $0.00 $53.50 $0.00 $0.00 Total Subcontractor Cost $588.50 $0.00 $588.50 $0.00 $0.00
Laboratory Analytical Costs $4,240.00 4,240.00$ $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $140.00 140.00$ $0.00 $0.00 $0.00 Total Laboratory $4,380.00 $4,380.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $173.00 173.00$ $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 -$ $0.00 $0.00 $0.00 Equipment (Analytical related) $1,361.00 1,361.00$ $0.00 $0.00 $0.00 Equipment (IDW related) $200.00 200.00$ $0.00 $0.00 $0.00 Equipment (Other) $1,431.00 1,431.00$ $0.00 $0.00 $0.00 Total Field Expenses $3,165.00 $3,165.00 $0.00 $0.00 $0.00
Subtotal $34,945.29 $2,771.93 $27,690.81 $995.66 $3,486.89 $0.00 Completion Fee $2,409.45 $277.19 $1,754.85 $28.72 $348.69 $0.00
Total Estimated Cost $37,354.74 $3,049.12 $29,445.66 $1,024.38 $3,835.58 $0.00
REV: 02/03 CEF TERRACON Page 1
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Miller Machinery and Supply Co #2 (ERIC_4733) SUBTASK 2: Soil Sampling, MAGS Survey
PROPOSAL NO. PH4237424
DATE: 11/25/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Task Planning Senior Scientist AK 4.00 Senior Scientist AK 3.00 Senior Scientist AK 1.00 Senior Scientist MM 2.00 Senior Scientist AK 3.00
Senior Scientist MM 1.50 Senior Scientist MM 1.50 Senior Scientist AK 6.00
Subsurface Geophysical Survey / Soil Sampling / MAGS Well Installation, Time Duration: 2 days ( thick concrete building slab/foundation up to 18") Scope: 11 soil borings to a depth of 4 ft bgs with soil investigation; 6 MAGS wells Senior Geologist CM 6.00 Senior Geologist CM 1.00 Senior Geologist CM 3.00 Environmental Technician HP Load/unload equipment (1 hour/day) 1.00 Senior Scientist AK 10.00
Staff Engineer EL Concrete coring (0.5 hours/boring) 5.50 Environmental Technician HP Concrete coring (0.5 hours/boring) 5.50 Staff Engineer EL Hand auger borings, decon between sampling, install 6 MAGS wells (8 hours/day) 16.00 Environmental Technician HP Collect samples at 0.5, 2, and 4 ft bgs for lab analysis (SPLP and VOCs) (8 hours/day) 16.00 Staff Engineer EL Tremie grout 5 borings (0.5 hours/boring) 2.50 Environmental Technician HP Containerize IDW (0.5 hours/day) 1.00 Senior Scientist AK Finalize field notes at end of day (1 hour/day) 2.00 MAGS Test , Time Duration: 2 days (8 MAGS tests @ 1.5 hours per test) Senior Scientist AK Deliver and set up MAGS System 3.00 Senior Scientist MM Perform and direct MAGS sampling test 12.00 Senior Scientist AK Collect vaccum/pressure and OVA screening measurements, collect samples for lab analysis 12.00 Staff Engineer EL Maintain system operation of the MAGS system, adjust vacuum/flows as directed by Engineer, 12.00 maintain hoses, decon as approriate between MAGS wells Senior Scientist MM Finalize field notes at end of day (1 hour/day) 2.00 Senior Scientist MM Interpret field data, perform calculations, and provide update to FDEP (10 hrs) 10.00 Mobilization / Demobilizations Senior Scientist AK 4 Days (1.5 hours/day from Tampa; 2 days soil and geo survey, 2 days MAGS) 6.00 Senior Geologist CM 1.50 Environmental Technician HP 3.00 Staff Engineer EL 7.50 Senior Scientist MM 2 Days (1.5 hours/day from Tampa; 2 days MAGS) 3.00
Personnel: AK MM CM HP EL Hours: 50.00 32.00 11.50 26.50 43.50 TOTAL LABOR 163.50
VEHICLE TYPE RATE UNIT USEAGE
Truck (AK) 480.00$ week 1 480.00$ Truck (HP, EL) 480.00$ week 1 480.00$ Truck (MM) 120.00$ day 2 240.00$ Truck (CM) 120.00$ day 1 120.00$
TOTAL VEHICLE 1,320.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
Action Environmental MAGS well materials (see quote attached) 1,161.22$ each 1 1,161.22$
TOTAL SUBCONTRACTOR 1,161.22$
LABORATORY COSTS
PARAMETER RATE # SAMPLES # IDW
Halocarbons (short list) EPA 8260 63.00$ 33 2,112.00$ VOCs (soil-prep) 5035 prep 7.00$ 33 1 264.00$ SPLP Bottle Extraction Method 1312, Zero Headspace 55.00$ To be submitted as a WCD -- VOCs (short list/SPLP) EPA 8260 63.00$ To be submitted as a WCD -- VOCs Soil Vapor- Full ScanTO-15 200.00$ 8 1,600.00$
Summa Canister 33.00$ 8 264.00$ Sample Shipping Large (2 day) 70.00$ 2 (vapor and soil) 140.00$
TOTAL LAB 4,380.00$
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables Expendables 40.00$ day 4 160.00$
Ice (Sample Preservation) 6.50$ each 2 13.00$ Analytical related Encore Sampler 16.00$ each 33 (SPLP samples - hold) 528.00$
Terra Core Sampler 11.00$ each 33 (VOH samples) 363.00$ Soil Sampling Kit (through concrete) 235.00$ day 2 470.00$
IDW related Drum, new 55-gallon 100.00$ each 2 200.00$ Other MAGS Investigation Kit 500.00$ day 2 1,000.00$
380.00$ day 1 380.00$ 51.00$ day 1 51.00$
TOTAL EQUIPMENT 3,165.00$
Pre Task Planning, develop MAGS well installation and MAGS test SOW
Update Health and Safety Plan Review technical approach to soil / MAGS Investigation Meet and conduct site walk with property owner and/or current tenants. Designate work zones, IDW staging area, decon pad location, and MAGS system staging area. Discuss site access and working around facility's production schedule.
Perform geophysical survey
Review preliminary soil VOC data to determine if SPLP tests need to be completed, contact the FDEP with suggested samples for SPLP analysis (3 hours), and prepare the Subtask 2 deliverable (field notes, sampling forms, and lab reports; 3 hours).
Purchase materials MAGS well installation
Ground Penetrating Radar Magnetic and Cable Locator
Prepare soil logging materials and order soil installation kit Request laboratory sample kit (soil and soil gas sampling)
2 Days (1.5 hours/day from Tampa; 2 days soil)
1 Day (1.5 hours/dayfrom Tampa; 1 day geo survey)
Finalize field notes at end of day (1 hour/day) Interpret field data, generate site maps for field use during soil investigation activities
4 Days (1.5 hours/day from Tampa: 2 days soil, 2 days MAGS)
Direct work & safety debriefs, record lithological descriptions, oversee GPR, MAGS well installations and grouting of boreholes (5 hours/day)
SUBTASK 3: IDW Disposal
PROPOSAL NO. PH4237424
DATE: 11/25/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Coordinate IDW T&D Senior Scientist/Geologist AK 1.00
Environmental Technician HP 2.50 Personnel: AK HP
Hours: 1.00 2.50 TOTAL LABOR 3.5
VEHICLE TYPE RATE UNIT USEAGE
Pickup (IDW site visit) 120 day 1 120.00$
TOTAL VEHICLE 120.00$
SUBCONTRACTOR COSTS
NAME PURPOSE COST UNIT USEAGE
Petrotech Southeast IDW Disposal (non haz- soil) 225.00$ each 2 450.00$ Petrotech Southeast Stop Fee 85.00$ each 1 85.00$
TOTAL 535.00$
Prepare waste characterization/Generator Profile Coordinate IDW T&D: Mobilize to site, meet transporter to unlock secure area for pickup and sign manifest
SUBTASK 4: Report Preparation
PROPOSAL NO. H4237424
DATE: 11/25/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Report Deliverable Senior Scientist AK Prepare tables, trend graphs and draft maps 8.00 Senior Scientist/Engineer MM Prepare report, radius of influence presentations, calculate intrinsic permeability 12.00 Senior Scientist AK QA/QC field and laboratory data 2.00 Senior Engineer DC Conclusions/Recommendations 2.00 CADD Specialist CF Update base figures and prepare Exhibits 4.00
Personnel: AK MM CF DC Hours: 10.00 12.00 4.00 2.00 TOTAL LABOR 28.00
5463 West Waters Avenue Tampa, FL 33684
P (813) 221-0050 F (813) 221-0051
Terracon.com
November 2 , 2024
Florida Department of Environmental Protection Waste Cleanup Program Waste Management Division 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Attn: Mr. Patrick McGrane, Environmental Specialist III E: Patrick.McGrane@FloridaDEP.gov W: 850-245-8899
Re: Proposal for Supplemental Soil Sampling and MAGS Event Miller Machinery and Supply Company #2 1920 Tampa East Boulevard Tampa, Hillsborough County, Florida
ERIC_4733
Contract No. HW687 Terracon Proposal No. PH4247036
Dear Mr. McGrane:
Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the Florida Department of Environmental Program (FDEP) Waste Cleanup Program (WCP) to conduct supplemental soil sampling and a Modified Active Gas Survey (MAGS) Event for Miller Machinery and Supply Company #2 (ERIC_4733) located at 1920 Tampa East Boulevard, Tampa, Hillsborough County, Florida. The objective of the proposed scope is to address data gaps in support of remedial design; specifically, to (1) improve delineation of contaminant impacts in unsaturated soils and (2) evaluate the radius of influence for soil vapor extraction in the western part of the facility. The proposed scope and sampling locations were developed in collaboration with the FDEP; Robert Huckaby, P.E., indicated approval in the attached email dated January 26, 2024.
Scope of Services
Subtask 1. Project Management Subtask 2. Soil Sampling and Modified Active Gas Sampling
(MAGS): 11 soil borings, 6 MAGS well installations, 8 MAGS tests Subtask 3. Investigative Derived Waste Management Subtask 4. Preparation of Letter Report
See attached LOE for details
Schedule Submit a Letter Report of on-site activities within 30 business days following receipt of laboratory results.
Compensation See attached CEF for details.
Proposal for Soil Investigation and MAGS Testing Miller Machinery and Supply Company #2, ERIC_4733 Tampa, FL November 2 , 2024 Terracon Proposal No. PH4247036
SCOPE OF SERVICES
Subtask 1 – Project Management
Dan Nedvidek will serve as the Project Manager during the field investigation. Donna Cline, P.E., will be involved throughout the project, serving as Authorized Project Reviewer.
Subtask 2 – Soil Sampling and Modified Active Gas Survey
Pre-Task Planning will be performed to prepare for field investigations. Terracon will prepare a site-specific health and safety plan.
Utility Locate Prior to initiating any subsurface activities, Terracon personnel will mobilize to the site to conduct a subsurface geophysical survey for the identification of potential subsurface utilities or obstructions.
This scope of work is estimated to take one day to complete.
Soil Investigation Terracon personnel will mobilize to the site to collect soil samples via hand auger from 11 proposed soil boring locations, as illustrated on the attached site map (Exhibit 3). The soil samples will be collected from 0.5, 2, and 4 feet below ground surface (ft bgs), or to the top of the water table if encountered within 4 ft bgs. Terracon personnel will perform the core drilling and hand augering to advance the soil borings. Terracon personnel will field-screen the soils with an OVA-PID, document the lithology observed at each soil boring location, and record the Global Positioning Satellite (GPS) coordinates of completed borings. Based on the number of proposed boring locations and depth intervals, Terracon will collect up to 33 soil samples for laboratory analysis of Volatile Organic Halocarbons (VOH) via EPA Method 8260. Two of the proposed soil boring locations (6 of the 33 samples) will be held pending the results of the total VOH results. SPLP samples will be collected from all 33 samples, and all 33 SPLP samples will be held pending the results of the total VOH results. FDEP will be contacted to discuss whether to proceed with analyzing any of the hold samples. Soil borings without MAGS well completion will be abandoned by tremie grout with a neat cement/bentonite mixture.
Modified Active Gas Survey (MAGS) Terracon personnel will complete six of the proposed soil borings as MAGS wells, as indicated on the attached site map (Exhibit 3), after completing soil sampling activities at those locations. The MAGS wells will be constructed of 2" PVC, screened from 1 to 3 ft bgs, and completed with flush-mounted, threaded cleanout plugs, consistent with the previously installed MAGS wells in the lower (western) part of the facility.
MAGS testing will be conducted at two existing MAGS wells (MAGS015 and MAGS018), and at each of the six proposed new MAGS wells. The MAGS testing is anticipated to require a minimum of 2 days.
One soil gas (air) sample will be collected into a Summa canister at each MAGS location and analyzed for VOH by EPA Method TO-15. The MAGS results will be summarized in a brief letter report.
Subtask 3 –Investigation Derived Waste
Decontamination activities will take place at a designated staging and laydown area. The soil cuttings will be containerized in 55-gallon drums as investigative derived waste (IDW) and staged on-site at a
November 2 , 2024 Terracon Proposal No. PH4247036 designated location. It is estimated that up to 2 drums of IDW will be generated in Subtask 2. The transportation and disposal costs for the drums are included under Subtask 3.
Terracon recommends subcontracting for IDW transportation and disposal.
Terracon will provide oversight of the IDW pickup, and sign waste manifests as an agent of FDEP.
Subtask 4 –Letter Report
Terracon will prepare a Letter Report that will document the field activities, MAGS results, and laboratory analytical data for the soil and air samples. The report will include data tables, exhibits of soil and soil gas concentrations, and a summary of results and recommendations.
SCHEDULE
It is estimated that the proposed soil investigation and MAGS activities can be completed within 20 business days of receipt of the Task Assignment, subject to scheduling constraints with the active facility. Terracon anticipates the letter report deliverable of MAGS investigation activities within 30 business days of receipt of analytical results.
CLOSING REMARKS
Terracon services will be conducted in accordance with the terms and conditions, contained within DEP Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.
We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments regarding this proposal, please contact either of the undersigned at 813-221-0050.
Sincerely, Terracon Consultants, Inc.
Fabio Fortes, P.E. Dan Nedvidek, P.G.
Senior Engineer Department Manager – Environmental
Attachment A: Cost Estimate Form/Level of Effort Attachment B: Site Map with proposed boring locations Attachment C: Email approval of the proposed scope Attachment D: 3-Bid summary for IDW management Attachment E: MAGS well material quote
CONFIDENTIAL
CE (Quote) Addendum_v17_01.13.2023_unlocked
The terms and prices contained herein shall be treated as confidential property and may not be disclosed to others before, during, or subsequent to the terms of this Agreement, except as required by law or as necessary to perform Services (and then only on a confidential basis satisfactory to both parties.
QUOTE - ADDENDUM
September 6, 2024
Mr. Eric Clementelli Terracon Consultants Inc 10840 S Ridgeview Rd Olathe, KS 65898
Thank you for allowing Clean Earth Environmental Solutions, Inc. by and through any of its subsidiaries or affiliates ("Clean Earth") to service your waste management needs. This addendum is to add additional services or pricing to your existing agreement with Clean Earth either at your request, or due to items or services performed that are not in your existing pricing schedule with us. Please see the below pricing schedule that will be added to your existing agreement as referenced below.
Quote provides example transportation rates from the Orlando Service Center. Actual charges will vary based on the distance from nearest Clean Earth service location to site. Non-Hazardous solids and liquids pricing assumes no contamination high halogen contamination from dry cleaning solvents are present.
ansportation ratesnsportatio from the Orlando Service Centerfrom the Orlando Service Center. Actual c. Actual c st Clean Earth service location to site Nonst Clean Earth service location to site Non Hazardous solidsHazardous solids
The terms and prices contained herein shall be treated as confidential property and may not be disclosed to others before, during, or subsequent to the terms of this Agreement, except as required by law or as necessary to perform Services (and then only on a confidential basis satisfactory to both parties.
Pricing Details:
Assumptions and Conditions:
1. The disposal pricing as listed above is based on the information provided and will be confirmed following receipt of a completed waste profile. All pricing is pending profile approval and/or waste sample analysis. Clean Earth reserves the right to adjust the fees or rates herein to account for operational changes implemented to comply with changes in law, rules, regulations, permits, licenses or approvals, or to cover increases in the cost of fuel, insurance, disposal, record keeping or to otherwise address cost escalation. If Customer rejects the adjusted fees or rates, Clean Earth shall have the right to terminate the Agreement or refuse to provide any services to Customer for which Customer rejected the adjusted Rates.
2. Unless otherwise stated in the Agreement, all invoices are subject to applicable Federal, State, and local taxes & fees as well as an Energy & Insurance recovery charge tied to the National monthly average price for diesel fuel as published by the Department of Energy https://www.cleanearthinc.com/energy-and-insurance-fees/.
The terms and prices contained herein shall be treated as confidential property and may not be disclosed to others before, during, or subsequent to the terms of this Agreement, except as required by law or as necessary to perform Services (and then only on a confidential basis satisfactory to both parties.
3. For a complete list of process code specifications, visit:
https://www.cleanearthinc.com/sites/default/files/Process-Specifications.pdf
4. This proposal must be signed within 30 days of receipt; otherwise a new quote will be reissued.
The terms and conditions from the Master Service 02/22/2023 between Stericycle Environmental Solutions, Inc, (now known as Clean Earth Environmental Solutions, Inc.), and Terracon Consultants Inc apply to this quote addendum.
Between: Clean Earth Environmental Solutions, Inc. And: Terracon Consultants Inc
Signature Signature
Name Name
Title Title
Date: Date:
NameName
Certificate Of Completion Envelope Id: 5BC726C792324A3CB437B9CC8F156371 Status: Sent Subject: Documents for your DocuSign Signature Source Envelope:
Document Pages: 3 Signatures: 0 Envelope Originator:
Certificate Pages: 2 Initials: 0 Francis Colosi AutoNav: Enabled EnvelopeId Stamping: Enabled Time Zone: (UTC-05:00) Eastern Time (US & Canada)
350 Poplar Church Road Camp Hill, PA 17011 fcolosi@cleanearthinc.com IP Address: 52.44.156.44
Record Tracking Status: Original
9/6/2024 10:25:22 AM
Holder: Francis Colosi fcolosi@cleanearthinc.com
Location: DocuSign
Signer Events Signature Timestamp Eric Clementelli eric.clementelli@terracon.com Security Level: Email, Account Authentication (None)
Sent: 9/6/2024 10:27:00 AM Viewed: 9/6/2024 11:00:16 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Francis Colosi fcolosi@cleanearthinc.com Security Level: Email, Account Authentication (None) Electronic Record and Signature Disclosure:
Not Offered via DocuSign
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp ce-dealdesk@harsco.com dd ce-dealdesk@harsco.com Security Level: Email, Account Authentication (None) Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Martria Chapple mchapple@cleanearthinc.com Security Level: Email, Account Authentication (None) Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps Envelope Sent Hashed/Encrypted 9/6/2024 10:27:00 AM
Payment Events Status Timestamps
Preliminary Proposal
18500 N. Allied Way Phoenix, AZ 85054 | RepublicServices.com | Environmental Services, Recycling & Waste
Rev. 6.20.24
PROPOSAL #: MS-083024-TAM
COMPANY: Terracon ADDRESS: 5463 West Waters Ave
Tampa, FL 33634 CONTACT: Eric Clementelli
PHONE: (813) 321-0340
EMAIL: eric.clementelli@terracon.com
08/30/24
Dear Eric Clementelli:
Republic Services appreciates this opportunity to provide you with environmental solutions. Following up on our earlier discussion, we are pleased to present this preliminary proposal.
Republic Services now offers comprehensive environmental solutions, including waste treatment, field and industrial services and 24/7 emergency response services. With a network of 40,000 employees and more than 175 dedicated Environmental Solutions locations, our customers benefit from working with an industry leader that can provide innovative solutions for hazardous and regulated waste, in addition to our recycling and waste services you have relied on for years.
Tampa Facility offers a single source option for your waste management needs, providing premier service to companies in a wide variety of industries. This RCRA Part B facility manages most waste codes and specializes in lab packing, pharmaceutical wastes, small quantity services (LTL and household hazardous waste), waste generated by the travel/tourism industry, remediation, emergency response, and industrial cleaning.
We understand you need a professional, integrated solution, and we have designed this proposal to meet those needs. Our best-in-class customer service leverages our industry-leading capabilities and will allow us to deliver the strongest solution available in the market today. We look forward to supporting you on this project!
Scope of Work:
and equipment necessary to properly package, transport, and dispose of designated waste materials from your location in Florida. Republic Services proposes to perform the following work:
Properly segregate and label all designated waste materials in accordance with all applicable regulations (as necessary) Provide all necessary shipping documents and transport the materials in licensed vehicles.
Customer/Generator prepared material must be in DOT-shippable containers.
Pricing applicable on all containers (percentage of 55-gallon drum price): 5-15 Gallons 35%; 16- 30 Gallons 75%; 31-55 Gallons 100%; 56-85 Gallons 150%; CYB 300%
18500 N. Allied Way Phoenix, AZ 85054 | RepublicServices.com | Environmental Services, Recycling & Waste
Rev. 6.20.24
Facility: Republic Services Tampa Facility
Treatment Type: Various
Rates:
Description Treat Group Size Unit Rate Quantity Minimums Ext Cost
IDW Liquids - NH 1218 55 Gal $110.00 IDW Solids - NH 1446 55 Gal $90.00 IDW PFAS Liquids 55 Gal $255.00 IDW PFAS Solids 55 Gal $237.00
Profile Fee $125.00
RCRA Haz Waste Fee - Haz Waste only 3% E-Manifest Fee $20.00
Estimated Disposal Subtotal
Transportation - Tampa, FL Size Unit Rate Quantity Minimums Ext Cost Transportation Minimum Container Rate <50 Miles 1-10 Drums 55 Gal $40.00 $218.00 Container Rate <50 Miles 11-15 Drums 55 Gal $34.00 $218.00 Container Rate <50 Miles 16-20 Drums 55 Gal $30.00 $218.00 Container Rate <50 Miles >20 Drums 55 Gal $24.00 $218.00 Container Rate 51-100 Miles 1-10 Drums 55 Gal $43.00 $254.00 Container Rate 51-100 Miles 11-15 Drums 55 Gal $37.00 $254.00 Container Rate 51-100 Miles 16-20 Drums 55 Gal $32.00 $254.00 Container Rate 51-100 Miles >20 Drums 55 Gal $26.00 $254.00 Container Rate 101-200 Miles 1-10 Drums 55 Gal $48.00 $327.00 Container Rate 101-200 Miles 11-15 Drums 55 Gal $41.00 $327.00
Container Rate 101-200 Miles 16-20 Drums 55 Gal $36.00 $327.00
Container Rate 101-200 Miles >20 Drums 55 Gal $29.00 $327.00 Container Rate 201-300 Miles 1-10 Drums 55 Gal $55.00 $400.00 Container Rate 201-300 Miles 11-15 Drums 55 Gal $47.00 $400.00
Container Rate 201-300 Miles 16-20 Drums 55 Gal $41.00 $400.00
Container Rate 201-300 Miles >20 Drums 55 Gal $33.00 $400.00
18500 N. Allied Way Phoenix, AZ 85054 | RepublicServices.com | Environmental Services, Recycling & Waste
Rev. 6.20.24
Container Rate >300 Miles 1-10 Drums 55 Gal $71.00 $508.00 Container Rate >300 Miles 11-15 Drums 55 Gal $60.00 $508.00 Container Rate >300 Miles 16-20 Drums 55 Gal $53.00 $508.00 Container Rate >300 Miles >20 Drums 55 Gal $43.00 $508.00
Demurrage - After 1 Hour Free Hour $175.00
Estimated Transportation Total
Environmental, Energy & Compliance Fee 20%
Estimated Project Total
TERMS & CONDITIONS
DIVISION ENTITY
IDENTIFIED BELOW THAT IS OFFERING TO PERFORM THE SERVICES. ALL SERVICES PROVIDED UNDER THIS www.RepublicServices.com/ServiceTermsES. A HARD COPY OF THE SERVICE TERMS WILL BE PROVIDED
UPON REQUEST. BY EXECUTING THIS PROPOSAL OR RECEIVING THE SERVICES, CUSTOMER
ACKNOWLEDGES THAT IT HAS AUTHORIZED THE SERVICES AND HAS READ AND AGREES TO BE BOUND BY THE SERVICE TERMS. IF CUSTOMER HAS A VALID CONTRACT WITH CONTRACTOR THAT INCLUDES THE SCOPE OF SERVICES HEREIN, THE TERMS OF SUCH CONTRACT SHALL PREVAIL IN THE EVENT OF ANY CONFLICTS WITH THE SERVICE TERMS. NO TERMS OR CONDITIONS ON ANY CUSTOMER-PROVIDED
SET UP PROCESS SHALL APPLY. THIS PROPOSAL AND
THE SERVICE TERMS OR CONTRACT, AS APPLICABLE, CONTAIN THE ENTIRE AGREEMENT OF THE PARTIES
THAT HE/SHE HAS AUTHORITY TO BIND CUSTOMER TO THIS PROPOSAL.
This preliminary proposal is valid for 30 days. After expiration of this proposal, the offer to perform services, and the prices, are subject to change or withdrawal. When waste approval is granted, we will provide written confirmation of pricing and billing unit. Payment terms are Net 30 days. Final pricing is subject to credit approval and standard credit terms.
GENERAL PROPOSAL CONDITIONS:
Prices and services are contingent upon credit approval and waste acceptance approval from the receiving facility. Approval of waste materials will be based on a completed and signed waste profile, an MSDS or analytical report, and an evaluation of a representative sample (if required) for a treatability study.
18500 N. Allied Way Phoenix, AZ 85054 | RepublicServices.com | Environmental Services, Recycling & Waste
Rev. 6.20.24
Surcharges may apply if waste varies from its original profile or is re-characterized or reclassified on site at the TSDF.
Additional fees may apply at the time of delivery for assistance with off-loading or due to non-conforming waste.
Improperly classified and/or rejected waste will be returned to the customer, or managed in an
Quoted bulk disposal charges for solid materials will be billed by the cubic yard if the truckload density is less than 2,000 pounds per cubic yard. If the truckload density is greater than 2,000 pounds per cubic yard, then bulk charges will be billed by the ton, regardless of the approved container. personnel will monitor all shipments.
Due to the U.S. -manifest regulations, a fee will be assessed to all customers for shipments utilizing a hazardous waste manifest.
An EEC fee will be added to your services. EEC is an environmental, energy & compliance fee. The EEC fluctuates monthly and will be charged as a percentage of all invoiced charges, excluding taxes.
For more information about this fee, please visit www.republicservices.com/customer-support/fee-disclosures.
Fees will be charged for waste approvals. A Profile Submission Fee of $125 will be charged for each initial profile approval, and a Profile Renewal Fee of $40 will be charged for each profile renewal.
Standard non-hazardous disposal pricing does not include PFOS/PFAS contaminants.
Republic Services reserves the right to modify pricing if the scope changes in any manner.
TRANSPORTATION CONDITIONS:
In the event that the scope of work changes from that specified above, out-of-scope work shall be charged at cost plus 15% or at rates mutually agreed upon in writing before work continues. The work site must be accessible for the size and type of truck ordered.
Washout/cleanout charges for tankers and/or containers shall be billed at Standard Rates, unless previously quoted.
Expenses related to waiting time at the work site or work stoppage outside of control will be the responsibility of the customer and will be billed at quoted rates, or at cost plus 15% if not quoted.
All shipping containers must be non-leaking and D.O.T. approved.
Thank you for this opportunity we appreciate your interest in our services. I believe this preliminary proposal meets your specifications, but please contact me if you have any questions.
Division Entity: US Ecology Tampa, Inc.
Republic Services Sales Representative: Marco Sapone
Phone: (386) 530-9891 Email: msapone@republicservices.com
Customer hereby accepts this Preliminary Proposal.
Customer Representative: ________________________________________________________________
18500 N. Allied Way Phoenix, AZ 85054 | RepublicServices.com | Environmental Services, Recycling & Waste
Rev. 6.20.24
Name: ___________________________________________________________________
Title: ___________________________________________________________________
Date: ___________________________________________________________________
Phone: _________________________________________________________________
Email: _________________________________________________________________
November 2 , 2024 Terracon Proposal No. PH4247036
Attachment E MAGS well material quote
3007 N. 50th St. Tampa, Florida 813-909-0040/0042 fax
November 22, 2024
Fabio Fortes, P.E.
Senior Environmental Engineer
Terracon 5463 W. Waters Avenue, Suite 830 Tampa, Florida 33634 D. 813.221.0050 | M. 703.606.8538 fabio.fortes@terracon.com
Re: Miller Machinery Materials
Dear Mr. Fortes:
In accordance with your request, Action Environmental is pleased to provide you with a cost estimate for the MAGS Materials for Miller Machinery.
3007 N. 50th St. Tampa, Florida 813-909-0040/0042 fax
Respectfully Submitted, Action Environmental
ESTIMATED COSTS
MAGS Materials Cost Estimate
Quantity Units Rate Extended
Concrete- 60 lbs. Bags 2 EA $7.72 $15.44
Portland Cement 47 lbs. Bags
6 EA $12.34 $74.04
3.5 Inch Brass Fill Box
6 EA $45.00 $27 .00
2 Inch Diameter Schedule 40 PVC Female S x FPT Adapter
6 EA $3.50 $21.00
2 Inch Diameter Schedule 40 PVC Socket Pressure Cap
6 EA $2.50 $15.00
2 Inch Diameter Locking Cap
6 EA $6.54 $39.24
2 Inch Diameter Schedule 40 PVC Casing
6 EA $25.41 $152.46
2 Inch Diameter Schedule 40 PVC Screen .010 Slotted
6 EA $41.27 $247.62
Sub Total $ .80 State Sales Tax 7% $ .4 Contractor Markup 30% $ .9
TOTAL
EA= Each
Jonathan Abbott, Drilling Division Manager
X Jonathan Abbott
November 2 , 2024 Terracon Proposal No. PH4247036