This is a Task Assignment (TA) DC002F issued under Florida Department of Environmental Protection (FDEP) Contract HW687 between the State of Florida Department of Environmental Protection and Terracon Consultants, Inc. The task assignment authorizes annual groundwater sampling and monitoring services at the Village Cleaners site (ERIC_5205) located at 2100 45th Street, West Palm Beach, Palm Beach County, Florida. The assignment is effective through July 25, 2025, with Gabriel Sostre serving as the FDEP Project Manager and Donna Cline as the Contractor's Project Manager.

The scope of work consists of three subtasks: Subtask 1 dedicated to project management calculated at 13 percent of direct labor costs for the remaining subtasks; Subtask 2 involving volatile organic halocarbon (VOH) groundwater sampling and laboratory analysis of seven monitoring wells (MW-2, MW-7D, MW-9, MW-10, MW-12, MW-13, and MW-16) with preparation of a Groundwater Monitoring Report; and Subtask 3 comprising expanded per- and polyfluorinated substance (PFAS) sampling and analysis of eight monitoring wells (MW-1, MW-3D, MW-5, MW-7D, MW-8, MW-9, MW-10, and MW-16). The total task assignment value is $12,662.03, calculated on a fixed unit rate basis with 80.10 labor hours allocated. Invoice payments are scheduled as follows: $7,974.30 due upon submission of the Groundwater Monitoring Report with updated tables by May 30, 2025, and $4,687.73 due upon submission of PFAS monitoring results including laboratory analysis by June 27, 2025. The contractor may invoice according to the included schedule.

View the file

Other files

File Type Posted
CN-370000-HW687-BF01ACO1.pdf PDF
CN-370000-HW687-BF03ACO1.pdf PDF
CN-370000-HW687-BIL01A.pdf PDF
CN-370000-HW687-BIL2ACO1.pdf PDF
CN-370000-HW687-BIL2BCO1.pdf PDF
CN-370000-HW687-BIL2CCO1.pdf PDF
CN-370000-HW687-BIL3ACO2.pdf PDF
CN-370000-HW687-BIO1ACO1.pdf PDF
CN-370000-HW687-DC001A.pdf PDF
CN-370000-HW687-DC003A.pdf PDF
CN-370000-HW687-DC003D.pdf PDF
CN-370000-HW687-DC005D.pdf PDF
CN-370000-HW687-DC006A.pdf PDF
CN-370000-HW687-DC006B.pdf PDF
CN-370000-HW687-DC008C.pdf PDF
CN-370000-HW687-DC010A.pdf PDF
CN-370000-HW687-DC010B.pdf PDF
CN-370000-HW687-DC011F.pdf PDF
CN-370000-HW687-DC011H.pdf PDF
CN-370000-HW687-DC012D.pdf PDF
CN-370000-HW687-DC013C.pdf PDF
CN-370000-HW687-DC015A.pdf PDF
CN-370000-HW687-DC015C.pdf PDF
CN-370000-HW687-DC019A.pdf PDF
CN-370000-HW687-DC01ACO2.pdf PDF
CN-370000-HW687-DC020A.pdf PDF
CN-370000-HW687-DC020B.pdf PDF
CN-370000-HW687-DC020C.pdf PDF
CN-370000-HW687-DC020D.pdf PDF
CN-370000-HW687-DC023C.pdf PDF
CN-370000-HW687-DC025B.pdf PDF
CN-370000-HW687-DC025C.pdf PDF
CN-370000-HW687-DC025F.pdf PDF
CN-370000-HW687-DC027B.pdf PDF
CN-370000-HW687-DC027C.pdf PDF
CN-370000-HW687-DC02BCO1.pdf PDF
CN-370000-HW687-DC02CCO2.pdf PDF
CN-370000-HW687-DC02DCO1.pdf PDF
CN-370000-HW687-DC02HCO1.pdf PDF
CN-370000-HW687-DC032A.pdf PDF
CN-370000-HW687-DC034A.pdf PDF
CN-370000-HW687-DC034C.pdf PDF
CN-370000-HW687-DC034D.pdf PDF
CN-370000-HW687-DC035F.pdf PDF
CN-370000-HW687-DC036A.pdf PDF
CN-370000-HW687-DC03CCO1.pdf PDF
CN-370000-HW687-DC041C.pdf PDF
CN-370000-HW687-DC041D.pdf PDF
CN-370000-HW687-DC048A.pdf PDF
CN-370000-HW687-DC048B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW687

DC002F Completion July 25, 2025

This TA authorizes annual Groundwater Sampling for VOHs and PFAS at the Village Cleaners site.

Gabriel Sostre 850-245-8749 Contractor Terracon Consultants, Inc. Contractor

Contractor Donna Cline Contractor 904-479-7415

ERIC_5205

2100 45th St West Palm Beach, Palm Beach County

Village Cleaners

Contractor Contractor

✔ $ 12,662.03

$ 12,662.03

Scope of Work

Terracon Consultants, Inc.

Contractor Donna Cline

Senior Associate / Engineer Digitally signed by Cline, Donna L DN: cn=Cline, Donna L, ou=General Users, email=Donna.Cline@terracon.com Date: 2025.04.11 08:29:21 -04'00'

Cline, Donna L

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.04.10 14:39:12 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

BWC TAFORM 01/18

HW687

DC002F

Subtask 3: Expanded PFAS Sampling.

Subtask 1 & 2: VOH Groundwater Sampling; Project Management.

05/30/2025

06/27/2025

Subtasks 1 & 2: Groundwater Monitoring Report with updated tables, groundwater flow, and concentration tables for 7 monitoring wells.

Subtask 3: PFAS monitoring results including laboratory analysis for 8 monitoring wells.

$ 7,974.30

$ 4,687.73

$ 12,662.03

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Secretary

Memorandum

TO:

FROM:

Negotiation File

ERIC

, Project Manager

SUBJECT: Negotiation Summary

DATE:

Task Assignment (HW687)

FDEP COST ESTIMATE

Contractor: Terracon

Date: 4/9/2025 Task #: HW687 SubTask 1 Project Management SubTask 6

Site: Village Cleaners WPB ERIC_5205 SubTask 2 VOH Groundwater Sampling SubTask 7 Activity/Phase: Annual GW Sampling/PFAS Screening SubTask 3 Expanded PFAS Sampling SubTask 8

Project Manager: Gabriel Sostre SubTask 4 SubTask 9 SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 Labor Rate Category

$51.92 Project Manager Shawn Ouellette 7.60 7.60 $0.00 Administrative 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Brownfield Consultant 0.00 0.00 0.00 0.00 0.00 0 0 0 0

$33.31 CADD Specialist Chelsea Fugate 6.00 4.00 2.00 0.00 0.00 0 0 0 0 $0.00 Data Analyst & Visualization Specialist 0.00 0.00 0.00 0.00 0.00 0 0 0 0

$34.10 Environmental Technician Billy Philips 18.00 14.50 3.50 0.00 0.00 0 0 0 0 $0.00 Field Geologist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Field Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 GIS Technician 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Principal Consultant 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Project Geologist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Project Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Project Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Project Scientist/Engineer 0.00 0.00 0.00 0.00 0.00 0 0 0 0

$51.92 Senior Geologist Shawn Ouellette 17.00 9.00 8.00 0.00 0.00 0 0 0 0 $0.00 Senior GIS Analyst 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Senior Industrial Hygienist 0.00 0.00 0.00 0.00 0.00 0 0 0 0

$42.55 Senior Staff Scientist Jessica Endicott 31.50 18.00 13.50 0.00 0.00 0 0 0 0 $0.00 Staff Engineer 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 Staff Scientist 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0 $0.00 0.00 0.00 0.00 0.00 0.00 0 0 0 0

Total Hours 80.10 7.60 45.50 27.00 0.00 0.00 0 0 0 0

Direct Labor $3,431.39 $394.76 $1,860.87 $1,175.76 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 116.00% $3,980.41 $457.92 $2,158.61 $1,363.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 56.26% $1,930.50 $222.09 $1,046.93 $661.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $9,342.30 $1,074.77 $5,066.41 $3,201.12 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 1

FDEP COST ESTIMATEContractor: Terracon Date: 4/9/2025

Task #: HW687 SubTask 1 Project Management SubTask 6 Site: Village Cleaners WPB ERIC_5205 SubTask 2 VOH Groundwater Sampling SubTask 7

Activity/Phase: Annual GW Sampling/PFAS Screening SubTask 3 Expanded PFAS Sampling SubTask 8 Project Manager: Gabriel Sostre SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 Travel

Vehicle Rental $320.00 120.00$ 200.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $320.00 $120.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Initiation Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Erwin Remediation $545.00 -$ $545.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $545.00 $0.00 $545.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $54.50 $0.00 $54.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $599.50 $0.00 $599.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $441.00 441.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 110.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $551.00 551.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $80.00 40.00$ 40.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $709.00 395.00$ 314.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 100.00$ -$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $26.00 13.00$ 13.00$ $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $915.00 $548.00 $367.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $11,727.80 $1,074.77 $6,285.41 $4,367.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $934.23 $107.48 $506.64 $320.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $12,662.03 $1,182.25 $6,792.05 $4,687.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF TERRACON Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Village Cleaners WPB, ERIC_5205 SUBTASK 2: VOH Groundwater Sampling Proposal No PHD257001

DATE: 4/9/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning Groundwater Sampling Senior Geologist SO 1.00 Senior Geologist SO 3.00 Groundwater Sampling Environmental Technician BP Load/unload 1.00 Environmental Technician BP Mobilization/Demobilization 2.00 Environmental Technician BP Collect 7 VOH Groundwater Samples (MW-2, MW-7D, MW-9, MW-10, MW-12, MW-13, and MW-16) 10.50

7 wells @1.5 hours per well Environmental Technician BP Containerize IDW in the Central SVE Compound 1.00 IDW Coordination Senior Geologist SO Prepare IDW Waste Characterization/Generator Profile 0.00 Environmental Technician BP Coordinate IDW T&D Meet Transporter onsite unlock gate for access 0.00 Report Deliverable Senior Staff Scientist JE Prepare report tables, draft groundwater elevation and analytical isoconcentration figures 6.00 Senior Staff Scientist JE Prepare report 8.00 Senior Staff Scientist JE QA/QC field and laboratory data 2.00 Senior Staff Scientist JE Summarize groundwater analytical results 2.00 Senior Geologist SO Summarize groundwater geochemistry field results 1.00 Senior Geologist SO Conclusions/Recommendations QA/QC 4.00 Cadd Specialist CF GIS Technician AS Prepare and update TetraTech base Figures and Exhibits 4.00

SO BP JE CF

Hours: 9.00 14.50 18.00 4.00 TOTAL LABOR 45.50

VEHICLE TYPE RATE UNIT USEAGE

Truck (Sampling) $120.00 day 1 120.00$ Car IDW Pick Up 80 day 0 -$

TOTAL VEHICLE 120.00$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

Erwin IDW Disposal 545.00$ Drum 0 -$

TOTAL -$

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS

Halocarbons (short list) EPA 8260 63.00$ 7 0 441.00$

(EQ Blank 0 Sample Shipping Large Cooler 110.00$ 1 0 0 110.00$

TOTAL LAB 551.00$

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables Expendables 40.00$ day 1 40.00$

Ice 6.50$ Bag 2 13.00$ Analytical related Shallow Groundwater Sampling Kit 290.00$ day 1 290.00$

Tubing, HDPE 0.30$ ft 250 75.00$ Tubing, silicon (3/16 x 3/8) 3.00$ ft 10 30.00$

IDW related 55-gallon drum, new 100.00$ drum 1 100.00$

TOTAL 548.00$

Request Sample Kit PreTask Planning, prepare field sampling, contact site owner, coordinate contractors and Field Work Request

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Village Cleaners , ERIC_5205 SUBTASK 3: Expanded PFAS Sampling Proposal No PHD257001

DATE: 4/9/2025

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Task Planning Groundwater Sampling Senior Geologist SO 1.00 Senior Geologist SO 2.00 Groundwater Sampling Senior Staff Scientist JE Load/unload 1.00 Senior Staff Scientist JE Mobilization/Demobilization (from PSL) 2.00 Senior Staff Scientist JE Collect 8 PFAS Groundwater Samples (MW-1, MW-3D, MW-5, MW-7D, MW-8, MW-9, MW-10, and MW-16) 6.00

4 additonal wells @1.5 hours per well, bolded are not included with VOHs 8 total PFAS Senior Staff Scientist JE Containerize IDW in the Central SVE Compound 0.50 IDW Coordination Senior Geologist SO Prepare IDW Waste Characterization/Generator Profile 1.00 Senior Environmental Technic BP Coordinate IDW T&D Meet Transporter onsite for access 3.50 Email Deliverable for PFAS Sampling Senior Staff Scientist JE QA/QC field and laboratory data 2.00 Senior Staff Scientist JE Evaluate and summarize groundwater analytical results 2.00 Senior Geologist SO Conclusions and Recommendations for PFAS analysis 4.00 Cadd Specialist CF Prepare PFAS exhibit with text boxes (showing PFOA, PFOS and PFOA+PFAS for each well) 2.00

SO BP JE CF

Hours: 8.00 3.50 13.50 2.00 TOTAL LABOR 27.00

VEHICLE TYPE RATE UNIT USEAGE

Truck (Sampling) 120.00$ day 1 120.00$ Car IDW Pick Up 80.00$ day 1 80.00$

TOTAL VEHICLE 200.00$

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNIT USEAGE

IDW Disposal (Erwin) 545.00$ Drum 1 545.00$ Subcontractor Markup 10% 0 54.50$

TOTAL 599.50$

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC* #IDW TOTALS

PFAS Analysis FDEP Laboratory -$ 8 1 1 -$

(MW-1, MW-3D, MW-5, MW-7D, MW-8, MW-9, MW-10, and MW-16) Sample Shipping Small Cooler -$ 1 -$

TOTAL LAB -$

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables Expendables 40.00$ day 1 40.00$

Ice 6.50$ Bag 2 13.00$ Analytical related Shallow Groundwater Sampling 290.00$ day 1 290.00$

Tubing, HDPE 0.30$ ft 60 18.00$ Tubing, silicon (3/16 x 3/8) 3.00$ ft 2 6.00$

IDW related 55-gallon drum, new 100.00$ drum 0 -$

TOTAL EQUIPMENT 367.00$

Request Sample Kit PreTask Planning, prepare field sampling Coordinate Contractors and Field Work Request

1225 Omar Road West Palm Beach, Florida 33405

P (561) 689-4299 F (813) 221-0051

Terracon.com

March 28, 2025

Florida Department of Environmental Protection Waste Cleanup Program Waste Management Division 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Attn: Mr. Gabriel Sostre, Environmental Specialist II E: gabriel.sostre@FloridaDep.gov W: (850) 245-8749

Re: Proposal for VOHs and PFAS Groundwater Monitoring- 2025 Village Cleaners (Former) 2100 45th Street West Palm Beach, Florida 34405

ERIC_5205

FDEP Contract HW687 Terracon Proposal No PHD257001

Dear Mr. Sostre:

Terracon Consultants, Inc. (Terracon) appreciates the opportunity to submit this proposal to the Florida Department of Environmental Program (FDEP) Waste Cleanup Program (WCP) to conduct Groundwater Monitoring for Volatile Organic Halocarbons (VOHs) and conduct expanded groundwater sampling for per-and polyfluorinated substances (PFAS) analysis for the above-referenced facility.

Scope of Services

Subtask 1 - The costs associated with this subtask are calculated automatically at 13% of the direct labor costs of the remaining subtasks.

Subtask 2 –VOH Groundwater Sampling Field preparation, mobilize to site, and perform groundwater sampling and laboratory analysis of 7 existing monitoring wells (MW-2, MW-7D, MW-9, MW-10, MW-12, MW-13, and MW-16) for VOHs.

Review VOH results and prepare and Groundwater Monitoring Report including updated tables and groundwater flow and concentration exhibits and provide conclusions and recommendations.

Subtask 3 – Expanded PFAS Sampling Field task planning, mobilize to site, and perform groundwater sampling and laboratory analysis for PFAS of 8 monitoring wells.

Monitoring wells proposed for PFAS sampling: (MW-1, MW- 3D, MW-5, MW-7D, MW-8, MW-9, MW-10, and MW-16) PFAS analysis only bolded

Proposal fo Annual Groundwater Monitoring Report Village Cleaners (Former), ERIC_5205 West Plam Beach, FL March 28, 2025 Terracon Proposal No. PHD257001

PFAS samples are sent by overnight courier to FDEP’s laboratory for sample analysis.

Review PFAS results and prepare a report section to discuss results and provide conclusions and recommendations.

See attached LOE for details

Deliverable Deliverable Groundwater Monitoring Report in July 2025, tentatively, based on TA authorization and following receipt of laboratory results.

Compensation See attached CEF for details.

BACKGROUND GROUNDWATER

According to Tetra Tech’s 2021 Groundwater Monitoring Report, samples were collected from 10 monitoring wells. Three of the 10 monitoring wells sampled in the September 2021 sampling event exceeded the Chapter 62-777, Table I, Florida Administrative Code (F.A.C.) Groundwater Cleanup Target Level (GCTL) for vinyl chloride (8.50 μg/L from MW-9, 2.48 μg/L from MW-10 and 2.46 μg/L MW-13).

PCE and TCE were not found to be exceeding Chapter 62-777, GCTLs in any of the groundwater samples analyzed from the September 2021 sampling event. In addition, Cis-1,2 dichloroethene was detected in five of the 10 monitoring wells above the laboratory method detection limits (MDLs) but below the respective GCTL. Trans 1,2 dichloroethene was also detected in one of the 10 monitoring wells above the laboratory MDLs but below its respective GCTL. The remaining monitoring wells had no reported exceedances of drycleaning contaminants of interest (COIs) in groundwater during this monitoring period. All reported detections were reported below their respective target level prescribed in Chapter 62-777 for the September 2021 monitoring event.

Overall, where levels were detected above their respective GCTL (i.e., VC), the groundwater exhibited slight increases in concentrations from historical. These increases in VC concentrations coincide with decreases of PCE and TCE concentrations to below detection limits.

PFAS sampling was conducted at the site on August 22, 2023, for monitoring wells MW-1, MW-8, MW- 9, and MW-10. Analytical results reported Perfluorooctanic acid (PFOA) + perfluorooctanesulfonic acid (PFOS) above the FDEP Provisional Cleanup Target Level (PGCTL) in MW-1, MW-8, MW-9, and MW-10.

Expanded sampling of the PFOA+PFOS PGCTL exceedances was recommended to the FDEP during the email deliverable to define the horizontal extent and confirm if deeper investigation is warranted.

On October 17, 2024, Terracon prepared an Annual Groundwater Monitoring Report, during which in August 2024, 13 groundwater samples (MW1, MW-2, MW-3D, MW-6, MW-7D, MW-8, MW-9, MW-10, MW-12, MW-13, MW-14, MW-15 and MW-16) were collected and analyzed for drycleaning COIs. In addition, seven of the 13 wells that were sampled for drycleaning COIs (MW-1, MW-3D, MW-9, MW-12, MW-13, MW-14 and MW-16), with an additional three wells (MW-6, MW-8, and MW-15), were sampled for expanded PFAS screening. During the August 2024 sampling event, reported vinyl chloride was above the GCTL of 1 μg/L, in monitoring wells MW-7D, MW-9, MW-10, and MW-16. Overall, the groundwater concentrations reported for the drycleaning COIs in August 2024, appeared to be on a downward trend with slight increases in vinyl chloride and daughter products in source and downgradient wells. Combined PFOA and PFOS exceedances of the 70 ng/L PGCTL were detected in three of the 13 monitoring wells (MW-3D, MW-9 and MW-16), during the August 2024 sampling event.

Proposal fo Annual Groundwater Monitoring Report Village Cleaners (Former), ERIC_5205 West Plam Beach, FL March 28, 2025 Terracon Proposal No. PHD257001

SCOPE OF SERVICES

Based on the results of the October 17, 2024, Groundwater Monitoring Report, Terracon recommends collecting groundwater samples from 7 monitoring wells (MW-2, MW-7D, MW-9, MW-10, MW-12, MW- 13, and MW-16)for analysis of VOHs, of which 7 (MW-1, MW-3D, MW-5, MW-7D, MW-8, MW-9, MW-10, and MW-16)) will be sampled for VOHS and PFAS, in addition monitoring wells MW-1, MW-3D, MW-5, and MW-8 will be analyzed for PFAS only, for a total of 8 wells to be collected for PFAS monitoring during the sampling event.

CLOSING REMARKS

Terracon services will be conducted in accordance with the terms and conditions, contained within DEP Waste Cleanup Program (WCP) Contract No. HW687, executed January 5, 2022. It is understood that a Task Assignment will be issued to authorize us to perform this work.

We appreciate the opportunity to provide this proposal and look forward to working with you on this project. If you should have any questions or comments, please contact either of the undersigned at .

Sincerely, Terracon Consultants, Inc.

Shawn Ouellette, P.G. Donna Cline, P.E.

Senior Geologist Senior Remediation Engineer

Attachments: Cost Spreadsheet Level of Effort IDW Bids

Erwin Remediation

Common Ground

Environmental Inc. Clean Earth

Disposal of 1 55g drum (PFAS Water) 195.00 1 .00 446.00 Profiling fee (one time) 350.00 0.00 Tranportation 300.00 59.00 Stop Charge 125.00 Fuel Surcharge (subject to change ) 15.50 Manifest Administration Fee 254.00 Total 545.00 5 50 759.00

IDW Transportation & Disposal: Erwin Remediation

3-Bid Summary IDW Transportation and Disposal

(ERIC

Page 1 of 1 Village Cleaners (ERIC_5205)

408 Ditmar Street Pensacola, FL 32503

To: Ms. Jessica Endicott Terracon 645 NW Enterprise Drive Suite 107 Port Saint Lucie, FL 34986

September 11, 2024

Re: Non-Hazardous Drum Disposal of PFOS/PFAS Impacted Materials - West Palm Beach, FL

Ms. Endicott:

The price for the transportation and disposal (T&D) of eight (8) 55-gallon drums of non-hazardous PFAS/PFOS impacted soil and water from your site in West Palm Beach, FL is $195.00 per drum. Additionally, there is a one time profiling fee of $350.00. The total cost for the T&D of the eight (8) drums is $1,910.00.

Please ensure that all drum lids are properly secured and that drums are on a level surface like the surrounding area (i.e., not on a pallet, etc.). A single False Mobilization fee will apply if our driver is not able to locate a drum on site or if we are unable to access the property due to a locked gate, etc. This quote is valid for 90 days.

Respectfully, Robert Donado Erwin Remediation, Inc.

Phone: 850-466-2358 Email: robert@erwinremediation.com

Erwin Remediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562 (850) 292-6511

Common Ground Environmental Inc.

(Common Sense Approach to Environmental Issues)

P.O. Box 1044, Lakeland, Florida 33802 Phone: (863) 647-3888

Jessica Endicott Terracon 645 NW Enterprise Drive Suite 107 Port Saint Lucie, FL 34986

RE: Cleaners with One (1) Drum of Non-Hazardous Waste for Disposal

Dear Jessica, Thank you for the opportunity to present Common Ground Environmental Inc. (CGE) to you.

CGE is committed to providing the best service in the waste management industry at competitive pricing. When you choose CGE, you choose to have a partner with the experience and the capabilities to handle all your environmental needs, from proper paperwork to site audits to remediation and analytical testing. CGE will be on site at time of pick up to correctly complete all paperwork and to tackle any unexpected problems. CGE makes it easy for you by handling all profiles, paperwork, and scheduling; all you do is sign the shipping documents!

Common Ground Environmental, Inc. is pleased to submit this quote for the following services.

Waste Stream Qty. Price per Unit Total Disposal Only of Non-Hazardous Non-Regulated Material in 55 Gallon Drums

1 $1 .00.00 per 55 Gallon Drum

$ 0

Transportation Only of Drums 1 0B$60.00 per Drum Minimum $300

$300.00

Stop Charge 1 $125.00 per Trip $125.00 Fuel Surcharge as of 9/10/24 1 $15.50 per Drum $15.50 Estimated Total $5 .50

NOTES:

The above pricing will be valid for 10 days from date of this quote. _____ Int.

The first hour of loading is included in the above price. For each additional hour, customer will be billed $225.00 per hour. _____ Int.

The above quote is only an estimated total. Final invoice can be higher or it can be lower due to number of drums for disposal, number of surcharges and/or waste conditions. _____ Int.

Quote is based on final profile approval from waste facility. _____ Int.

A monthly fee of 1 ½ % interest will be charged on the balance of every past due invoice that is over 30 days past due and will incur every 30 days until invoice and late fees are paid in full. _____ Int.

Our terms are 30 Days Net. _____ Int.

Terracon Page 2

The pricing above includes transportation and disposal to an EPA permitted facility. Pricing is based on approved waste profiles and non-conforming waste will be assessed surcharges that are billed separately. A $125.00 stop fee will be passed on to the customer. Please note, due to the high cost of Diesel, the fuel surcharge rate will now be managed separately on a month-to-month basis.

Thank you for considering Common Ground Environmental, Inc. as your waste management provider. Please review the above pricing and if it meets with your approval, please confirm your order by signing and returning this quote to my attention. Do not hesitate calling me at (863) 860- 0827 or (863) 647-3888 with questions or concerns.

Sincerely, Michael Propst Mike Propst Common Ground Environmental, Inc.

Acceptance of Proposal

The above prices, specifications and conditions are satisfactory to generator/client and are hereby accepted. Common Ground Environmental, Inc. is hereby granted to do the work as specified.

Payment terms are net 30 days unless specified otherwise. A 1.5% per month finance charge will be applied on all past due invoices. The generator/client will be responsible for all cost, expenses and reasonable counsel fees incurred by or on behalf of Common Ground Environmental, Inc. as a result of failure to remit payment as specified above.

Date of Acceptance _______________________________________________________

Signature: __________________________________________Title: ________________

Printed Name: ___________________________________________________________

CONFIDENTIAL Page 1 of 3 CE (Quote) – Addendum_v17_01.13.2023_unlocked

The terms and prices contained herein shall be treated as confidential property and may not be disclosed to others before, during, or subsequent to the terms of this Agreement, except as required by law or as necessary to perform Services (and then only on a confidential basis satisfactory to both parties.

QUOTE - ADDENDUM

September 6, 2024

Mr. Eric Clementelli Terracon Consultants Inc 10840 S Ridgeview Rd Olathe, KS 65898

Thank you for allowing Clean Earth Environmental Solutions, Inc. by and through any of its subsidiaries or affiliates ("Clean Earth") to service your waste management needs. This addendum is to add additional services or pricing to your existing agreement with Clean Earth either at your request, or due to items or services performed that are not in your existing pricing schedule with us. Please see the below pricing schedule that will be added to your existing agreement as referenced below.

Quote provides example transportation rates from the Orlando Service Center. Actual charges will vary based on the distance from nearest Clean Earth service location to site. Non-Hazardous solids and liquids pricing assumes no contamination high halogen contamination from dry cleaning solvents are present.

CONFIDENTIAL Page 2 of 3

The terms and prices contained herein shall be treated as confidential property and may not be disclosed to others before, during, or subsequent to the terms of this Agreement, except as required by law or as necessary to perform Services (and then only on a confidential basis satisfactory to both parties.

PPricingg Details::

Assumptionss andd Conditions:

1. The disposal pricing as listed above is based on the information provided and will be confirmed following receipt of a completed waste profile. All pricing is pending profile approval and/or waste sample analysis. Clean Earth reserves the right to adjust the fees or rates herein to account for operational changes implemented to comply with changes in law, rules, regulations, permits, licenses or approvals, or to cover increases in the cost of fuel, insurance, disposal, record keeping or to otherwise address cost escalation. If Customer rejects the adjusted fees or rates, Clean Earth shall have the right to terminate the Agreement or refuse to provide any services to Customer for which Customer rejected the adjusted Rates.

2. Unless otherwise stated in the Agreement, all invoices are subject to applicable Federal, State, and local taxes & fees as well as an Energy & Insurance recovery charge tied to the National monthly average price for diesel fuel as published by the Department of Energy https://www.cleanearthinc.com/energy-and-insurance-fees/.

Faci l i ty IItem Descr iption UUOM Price QQTY Nett Pr ice MMinimums

Orlando STAB01 Non regulated sludges with free liquids , bulkable , for solidification to subtitle D landfill, DR55 $137.00 1 $137.00

Orlando STAB02 Solids/Sludges/Liquids (neutral pH) with RCRA metals, for stabilization to subtitle C/D landfill

DR55 $207.00 1 $207.00

Orlando LF72L PFAS Impacted Water Wastes DR55 $446.00 1 $446.00 #N/A

Orlando INC71 PFAS Impacted Solid Material DR55 $1,121.00 1 $1,121.00 #N/A

$1,911.00

Faci l i ty IItem Descr iption UUOM Price QQTY Nett Pr ice MMinimums

Orlando TRSTOP1-3 30-55 GL drums, LTL Trans., Zone 1 (0-50 mi, RT) Each $34.00 1 $34.00 $210 Minimum / $499 Maximum per Pickup

Orlando TRSTOP2-3 30-55 GL drums, LTL Trans., Zone 2 (51-100mi, RT) Each $40.00 1 $40.00 $250 Minimum / $599 Maximum per Pickup

Orlando TRSTOP3-3 30-55 GL drums, LTL Trans., Zone 3 (101-150 mi, RT) Each $48.00 1 $48.00 $300 Minimum / $749 Maximum per Pickup

Orlando TRSTOP4-3 30-55 GL drums, LTL Trans., Zone 4 (151-200 mi, RT) Each $54.00 1 $54.00 $350 Minimum / $949 Maximum per Pickup

Orlando TRSTOP5-3 30-55 GL drums, LTL Trans., Zone 5 (>200 mi, RT) Each $59.00 1 $59.00 $400 Minimum / CBC Maximum per Pickup

$235.00

Faci l i ty IItem Descr iption UUOM Price QQTY Nett Pr ice MMinimums

Orlando ADMEMANFST Manifest Administration Fee Each $254.00 1 $254.00

$254.00

$432.00

$2,832.00Estimatedd Total :

E&II Estimate :

Equipmentt Subtotal :

Disposall Charges :

Transportationn Charges :

Equipment/Adminn Charges :

Transportationn Subtotal :

Disposall Subtotal :

CONFIDENTIAL Page 3 of 3

The terms and prices contained herein shall be treated as confidential property and may not be disclosed to others before, during, or subsequent to the terms of this Agreement, except as required by law or as necessary to perform Services (and then only on a confidential basis satisfactory to both parties.

3. For a complete list of process code specifications, visit:

https://www.cleanearthinc.com/sites/default/files/Process-Specifications.pdf

4. This proposal must be signed within 30 days of receipt; otherwise a new quote will be reissued.

The terms and conditions from the Master Service (“Agreement”) with an effective date of 02/22/2023 between Stericycle Environmental Solutions, Inc, (now known as Clean Earth Environmental Solutions, Inc.), and Terracon Consultants Inc apply to this quote addendum.

Between: Clean Earth Environmental Solutions, Inc. And: Terracon Consultants Inc

Signature Signature

Name Name

Title Title

Date: Date:

File details come from the government source that posted it. Updated .