ATTCH H- Submittal Register AF Form 66.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Replacement of Base Pool Controls Federal contract opportunity
Solicitation number
FA500421B0002
Issued by
Department of the Air Force Pacific Air Forces

About this file

This document contains an invitation for bids for a federal contract opportunity to replace a base pool controls system and perform related work. The U.S. Air Force is seeking bids to remove an existing pool control system at Eielson Air Force Base in Alaska and provide and install a new system, recertify the pool filtration system, replace drain lines, and conduct other incidental work. The scope of work includes commissioning and testing the new system as well as operator training. Bids are due by 14:00 AKST on 19 April 2021, and the contract is contemplated as a firm fixed price contract between $250,000 and $500,000. Questions are due by 2 April 2021 and may be submitted to the points of contact listed. The site visit requirement is waived.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

AF FORM 66 - SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION CONTRACT NUMBER
TO BE COMPLETED BY PROJECT ENGINEERFTQW 19-1028Base Pool Controls
Line NumberITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INTRUCTIONSMDSOTHERPLANSREQUIRED SUBMISSION DATE
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
DATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERDATE CONTRACTOR NOTIFIEDCOTNRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDIS-APPROVED
1Sampling and Analysis Plan (SAP)x60 Days Prior to Construction Start
2Progress Schedulex30 Days Prior to Construction Start
3AF Form 103x30 Days Prior to Construction Start
4Waste/Borrow Pit Coord.x30 Days Prior to Construction Start
5Construction Drawingsx30 Days Prior to Construction Start
6Construction Schedulex30 Days Prior to Construction Start
7Material Data Sheets (Non Hazardous)x30 Days Prior to Construction Start
8Environmental Permit DocumentationxPrior to Construction Start
9Lockout/Tagout Planx30 Days Prior to Construction Start
10Pool Control Panelxxx30 Days Prior to Construction Start
11HMI Screenxxx30 Days Prior to Construction Start
12VFDxxx30 Days Prior to Construction Start
13PLCxxxPrior to Construction Start
14Floor flood sensorxxx30 Days Prior to Construction Start
15Filter level sensorxxx30 Days Prior to Construction Start
16ORP sensorxxx30 Days Prior to Construction Start
17Residual chlorine sensorxxx30 Days Prior to Construction Start
18pH sensorxxx30 Days Prior to Construction Start
19Valve Actuator Motorxx30 Days Prior to Construction Start
20Pump pressure guagexx30 Days Prior to Construction Start
21Filter mediaxx30 Days Prior to Construction Start
22Floor Drains & Gratesxx30 Days Prior to Construction Start
23System commissioning reportx15 Days Prior to Project Close-Out
24System operating instructionsx15 Days Prior to Project Close-Out
25Manufacturer Warranty Infox15 Days Prior to Project Close-Out
26As-Build Drawings w/ CD Copyx15 Days Prior to Project Close-Out
27DD Form 1354x15 Days Prior to Project Close-Out
28Waste Disposal Receiptsx15 Days Prior to Project Close-Out