Pool Controls _Bidder_QA.pdf

PDF 265 KB Posted

Attached to
Replacement of Base Pool Controls Federal contract opportunity
Solicitation number
FA500421B0002
Issued by
Department of the Air Force Pacific Air Forces

About this file

This document contains a federal contract opportunity solicitation for replacement of pool controls at Eielson Air Force Base in Alaska. The solicitation seeks qualified contractors to replace an existing pool pump control system, recertify the pool filtration system, replace drain lines, and conduct other related work. Contractors must remove the current pool control system and components, provide and install a new pool pump control system, recertify the pool filtration system to manufacturer specifications, and replace existing drain lines with larger diameter piping. Additional requirements include fully testing and commissioning the new system and providing operation personnel training. The estimated contract value is between $250,000 and $500,000 to be awarded on a firm fixed price basis. The response due date is August 20, 2021 and the bid opening date is April 19, 2021. All contractors must register in the System for Award Management. No site visits will be conducted due to COVID-19 and questions must be submitted electronically by April 2, 2021. The solicitation is available through the SAM website.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Name: Replacement of Pool Controls

EIELSON AFB, ALASKA

Solicitation Number: FA5004-21-B-0002

Project Number: FTQW 19-1028

Questions and Answers

Q1) Are site visits allowed?

A1) Site visits will not be conducted due to COVID.

Q2) Are there photos of the areas where the work is to be installed?

A2) Additional photos have been added under Section J/Attachments.

Q3) Please define “Recertifying the pool filtration system”?

A3) Verification that work done to the pool filtration system is operating in accordance with manufacturer/design specs and UFC 4-750-07 Recreational Aquatic Facilities.

Q4) Do you have photos of the existing filters or filters and their manufacturer data, in order to determine if the filter housing are in useable condition to be retained?

A4) Additional photos have been added, however filter internals are not able to be photographed.

All the manufacturer data that was retained for the pool control systems in additional to the filter system have been added under Section J/Attachments.

File details come from the government source that posted it. Updated .