About this file

This document contains a material submittals schedule template for a federal construction project. The template includes columns for identifying items requiring submittals, the required number of copies, submission due dates from the contractor and dates received. Additional columns track routing within the agency, including dates submitted to civil engineering, return suspense dates, submittal numbers, approval notification dates, resubmittal numbers if needed, and final approval dates.

The related federal contract opportunity is a solicitation to perform design-build services for repair and restoration of an Air Force tower damaged during Hurricane Michael at Tyndall Air Force Base. The scope of work involves demolishing and repairing interior and exterior building elements as identified within the statement of work. The design-build team will include a construction firm and design firm of record to perform the described services.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
[ enter here ]Project Title:
[ enter here ]Solicitation / Contract Number:

[ enter here ]

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies RequiredRemarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationManufacturer's WarrantyCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission DateDate Received in ContractingDate to Civil EngineeringReturn Suspense DateSubmittal NumbersDate Contractor
NotifiedContractor ResubmittalFinal Approval
ApprovedDisapproved
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).

&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)