Repair Tower 9352, Tyndall AFB

Closed Solicitation Posted

Solicitation number
FA481921R0020
Agency
Air Combat Command Air Force, Department of Defense
Responses due
Set-aside
HUBZone

Opportunity facts

NAICS code
236220 Commercial and Institutional Building Construction
PSC
Z2JZ Repair Or Alteration Of Miscellaneous Buildings
Place of performance
Tyndall AFB, Florida 32403, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks design-build services to demolish, repair, and restore interior and exterior elements of Tower 9352 at Tyndall Air Force Base damaged by Hurricane Michael. The Department of the Air Force Air Combat Command is procuring these services to rehabilitate the identified communications tower. The contractor will form a design-build team consisting of a construction firm and designer of record responsible for performing all design and construction services outlined in the statement of work within 300 calendar days. Responses are due by July 8, 2021. The evaluation criteria will consider technical qualifications, past performance, and price.

The set-aside designation for this procurement is HUBZone. The primary NAICS code is 237130 and PSC code R499 applies. The place of performance is Tyndall AFB in Florida. No incumbent or current contractor is identified. The scope of work involves demolishing and repairing interior and exterior building elements as identified within the statement of work appendix for one communications tower damaged in the hurricane.

Notice text

4 versions

Update #4 · Latest ·

This is a Design-Build project to demo, repair and restore interior and exterior elements damaged as resulting from Hurricane Michael. Associated areas of repair are identified within this scope of work. The project is comprised of one building on Tyndall AFB and the related disciplines of work as specific tasks in Scope of Work (Appendix A). The Design-Build Team will consist of a Construction and design team Designer of Record (DOR) that shall perform the services herein and as described in this Statement of Work (SOW). 

***15 June 2021 -  Site Visit Sign in Sheet Attached.

***21 June 2021 -  Amendment to SOW "Attachment 2 - Appendix A updated 15 June 2021" 

The changes include:
1. Changed from 4 legged tower to 3 legged tower, this was a typo (paragraph 1.1.1.1.8)
2. Added note to place tower as close to existing tower as possible for user FAA certification by end user (paragraph 1.1.1.2.3)
3. Added note indicating swing gate needs to face existing access road (paragraph 1.5.2)
4. Added clarification indicating that only equipment shelter requires shallow foundation, tower requires deep foundations (paragraph 1.1.1.1.9)

UPDATE: 28 June 2021

Update to include the following attachments

-Attachment 12 XLWU218112 Q&As

-Attachment 13 RFI 006 Tower Signs 

-Attachment 14 Combined DA-Repair Multiple Communication Towers Tyndall 

Attachment 13 and 14 are from a previous Tower project and the information is intended to be a guide for Tower 9352. Any reference or direction to repair additional towers is not applicable. 

Update #3 ·

This is a Design-Build project to demo, repair and restore interior and exterior elements damaged as resulting from Hurricane Michael. Associated areas of repair are identified within this scope of work. The project is comprised of one building on Tyndall AFB and the related disciplines of work as specific tasks in Scope of Work (Appendix A). The Design-Build Team will consist of a Construction and design team Designer of Record (DOR) that shall perform the services herein and as described in this Statement of Work (SOW). 

***15 June 2021 -  Site Visit Sign in Sheet Attached.

***21 June 2021 -  Amendment to SOW "Attachment 2 - Appendix A updated 15 June 2021" 

The changes include:
1. Changed from 4 legged tower to 3 legged tower, this was a typo (paragraph 1.1.1.1.8)
2. Added note to place tower as close to existing tower as possible for user FAA certification by end user (paragraph 1.1.1.2.3)
3. Added note indicating swing gate needs to face existing access road (paragraph 1.5.2)
4. Added clarification indicating that only equipment shelter requires shallow foundation, tower requires deep foundations (paragraph 1.1.1.1.9)

Update #2 ·

This is a Design-Build project to demo, repair and restore interior and exterior elements damaged as resulting from Hurricane Michael. Associated areas of repair are identified within this scope of work. The project is comprised of one building on Tyndall AFB and the related disciplines of work as specific tasks in Scope of Work (Appendix A). The Design-Build Team will consist of a Construction and design team Designer of Record (DOR) that shall perform the services herein and as described in this Statement of Work (SOW). 

15 June 2021 Site Visit Sign in Sheet Attached.

Update #1 ·

This is a Design-Build project to demo, repair and restore interior and exterior elements damaged as resulting from Hurricane Michael. Associated areas of repair are identified within this scope of work. The project is comprised of one building on Tyndall AFB and the related disciplines of work as specific tasks in Scope of Work (Appendix A). The Design-Build Team will consist of a Construction and design team Designer of Record (DOR) that shall perform the services herein and as described in this Statement of Work (SOW). 