Attachment 2 - AF Form 66 Building 225.pdf

PDF 168 KB Posted

Attached to
Building 225 Fire Alarm Project Federal contract opportunity
Solicitation number
FA4419-23-Q-0030
Issued by
Department of the Air Force Air Education and Training Command

About this file

This submittal register outlines required pre-construction and closeout submittals for a project to repair the fire alarm notification system in Building 225 at an Air Force installation. Key submittals include an accident prevention plan, solid waste management plan, operation and maintenance manuals, and training documentation. The related federal contract opportunity is a solicitation to demolish and replace or install new fire alarm/detection systems in Building 225. The project is currently unfunded, and quotes must remain valid until 30 September 2023. The solicitation is issued by the Department of the Air Force Air Education and Training Command and includes wage determinations. Interested parties should review all attachments and the COMBO document, and provide pricing, proposed period of performance, and an authorizing signature on Attachment 20.

View the file

Other files for this federal contract opportunity

Other files attached to Building 225 Fire Alarm Project, newest first.
File Type Posted
Altus AFB B225 RFI Answers.pdf PDF
Attachment 5 - COMBO B225 Building Project.pdf PDF
Attachment 4 - AF 813 Building 225.pdf PDF
Attachment 3 - Specs Building 225.pdf PDF
Attachment 1 - SOW Building 225.pdf PDF
Attachment 1A - Altus MAAP-X MNS Custom Message.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATE OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE OF

ACTION

(a) (c) (d) (e) (f) (k) (l) (p) (q) (r)

01 11 00 SD-01 Preconstruction Submittals Salvage Plan 1.8 G

01 14 00 SD-01 Preconstruction Submittals List of Contact Personnel 1.3.1.1 G

01 32 01.00 10 SD-01 Preconstruction Submittals Preliminary Project Schedule 3.4.1 G Initial Project Schedule 3.4.2 G Periodic Schedule Update 3.6.2 G

01 33 00 SD-01 Preconstruction Submittals Submittal Register 1.7 G

01 35 26 SD-01 Preconstruction Submittals Accident Prevention Plan (APP) 1.7 G SD-06 Test Reports Accident Reports 1.12.2 G

01 45 00.00 10 SD-01 Preconstruction Submittals Contractor Quality Control (CQC) Plan 3.2 G

01 57 19 SD-01 Preconstruction Submittals Solid Waste Management Permit 1.10 G Regulatory Notifications 1.6.2 G SD-06 Test Reports Monthly Solid Waste Disposal Report 1.10.1 G

SD-07 Certificates SD-11 Closeout Submittals Project Solid Waste Disposal Documentation Report

3.7.2.1 G

01 78 00 SD-10 Operation and Maintenance Operation and Maintenance Manuals 3.3 G

SD-11 Closeout Submittals As-Built Drawings 3.1 G Record Drawings 3.2 G As-Built Record of Equipment and Materials

1.5.1 G

01 78 23 SD-10 Operation and Maintenance O&M Database 1.3 G Training Plan 3.1.1 G SD-11 Closeout Submittals Training Video Recording 3.1.4 G Validation of Training Completion 3.1.6 G

02 82 00 SD-03 Product Data Amended Water 1.2.2 G

Safety Data Sheets (SDS) for All 1.3.9 G Local Exhaust Equipment 3.1.7 G

SUBMITTAL REGISTER AGGN221052

TITLE AND LOCATION

REPAIR FIRE ALARM NOTIFICATION SYSTEM B225

A C T I V I T

Y N O

S P E C S E C T

DESCRIPTION ITEM SUBMITTED

P A R A G # R A P H

G O V C T L A O S R S I A F / I E C A R T E I V O W N R

MAILED TO

CONTR/

DATE RCD

FRM APPR

AUTH

REMARKS

Pressure Differential Automatic Recording Instrument

3.1.7 G

Vacuums 3.1.8 G Glovebags 3.1.10 G SD-06 Test Reports Air Sampling Results 1.5.5 G

Pressure Differential Recording for Local Exhaust System

1.5.6 G

Encapsulation Test Patches 3.2.12.2 G Clearance Sampling 3.2.14.5 G Asbestos Disposal Quantity 3.3.3.2 G Employee Training 1.3.4 G Notifications 1.3.5 G Respiratory Protection Program 1.3.7 G Asbestos Hazard Abatement Plan 1.3.10 G Landfill Approval 1.3.12 G Delivery Tickets 1.3.12 G Worker's License 1.5.3 G Contractor's License 1.5.4 G Federal, State or Local Citations on Previous Projects

1.5.9 G

Encapsulants 2.1 G Equipment Used to Contain Airborne Asbestos Fibers

3.1 G

Permits[ and Licenses] 1.3.5 G Notifications 1.3.5 G Respirator Program Records 1.3.7.1 G

23 31 76 SD-01 Preconstruction Submittals Qualified Fire Protection Engineer (QFPE) Credentials

1.3.2 G

Fire Alarm System Designer Credentials 1.9.2.1 G

Supervisor 1.9.2.2 G Monaco MAAP-X Technician Credentials 1.9.2.3 G

Installer Credentials 1.9.2.4 G Test Technician Credentials 1.9.2.5 G

SOW Professional Service Labor-Rate Proposal SOW G Design Report SOW G 35% Design Analysis SOW G 35% Design Drawings SOW G 35% Specifications SOW G 65% Design Analysis SOW G 65% Design Drawings SOW G 65% Specifications SOW G 95% Design Analysis SOW G 95% Design Drawings SOW G 95% Specifications SOW G IFC Design Analysis SOW G IFC Design Drawings SOW G IFC Specifications SOW G Work Plan SOW G Schedule SOW G

Table 1

2023-05-09T15:13:31-0500
WOODS.JOSHUA.QUINN.1270857783

File details come from the government source that posted it. Updated .