This is an AF Form 66 Schedule of Material Submittals for the FAMCAMP Expansion project at Shaw AFB (solicitation VLSB 24-0019). The form outlines required contractor submittals including a construction schedule due within one week of Notice to Proceed, light pole and Wi-Fi pole specifications with manufacturer's recommendations required before ordering, light specifications, 95% drawings, as-built drawings, asphalt mix design documentation required at time of paving, and soil compaction test results required prior to paving.

The form corresponds to a small business set-aside pre-solicitation for adding 14 recreational vehicle parking spaces at Shaw Air Force Base Family Camp Site, which will include asphalt drives, electrical systems, concrete RV pads, water, and sewer infrastructure. A site visit is scheduled for February 7 at 10:00 AM EST, with bids due April 7, 2025 at 2:00 PM under an upcoming Invitation for Bids (IFB). This is a Non-Appropriated Fund Instrumentality (NAFI) requirement under the Department of the Air Force Air Combat Command.

View the file

Other versions and copies of AF Form 66

File Revision Posted Attached to
Attachment 2 AF Form 66.pdf Revision not stated REPAIR AC PAVING
AF form 66 Blank.pdf Revision not stated Demo Mini mute sites
Attach 9_AF Form 66 Submittal Register.pdf Revision not stated PKAA Dorm Water Damage Repair (Construction)
AF Form 66-EEPZ260842 Renovate Convert Comm to SAPR B730.xlsx Revision not stated B730 Renovate Convert Comm to SAPR
AF Form 66_EEPZ254664-B972 UOQ.xlsx Revision not stated B972 Renovate UOQ Community Commons
AF Form 66 B268.xlsx Revision not stated B268 Replace STUS Backup Generator
AF Form 66 B730.xlsx Revision not stated B730 - Renovate RM106 for Emergency Operations Center
AF Form 66.xlsx Revision not stated B836 Replace Electrical in Airfield Lighting Vault
AF Form 66 OSI Flooring.xlsx Revision not stated OSI B926 Flooring
EEPZ254660 Repair Control Tower HVAC B1806 - AF Form 66.xlsx Revision not stated B1806 Repair Control Tower HVAC
AF Form 66 Template.xlsx Revision not stated Replace AAS BAK-15 Controls, B2001, B2003
AF Form 66 EEPZ216808 Replace Security Forces Elevator B926.xlsx Revision not stated B926 Replace Security Forces Elevator
WT 17518487 AF Form 66.xlsx Revision not stated Repair Structural Fire Trainer B17903, 17904
AF Form 66.xlsx Revision not stated RENOVATE/CONVERT 50th 49th SQ OPS, B230
AF Form 66.xlsx Revision not stated T-6 Flightline Shacks
AF Form 66 Template.xlsx Revision not stated Replace Fire Alarms, Multi Facility
EEPZ248229 -- AF Form 66.xlsx Revision not stated Repair Kiddie Pool
Atch 2 AF Form 66.pdf Revision not stated Removal of Underground Storage Tank at Launch Facility E-10 (Laramie County, WY)
Attachment 4 - AF Form 66 Submittal Register.pdf Revision not stated Bldg 65 - Renovation of Telephone Office Area, FE Warren AFB, WY AMENDMENT 03
Attachment 7 - AF Form 66.xlsx Revision not stated Replace Chapel Windows B912
Show all 20

Who attaches AF Form 66

State Files
Iowa 1
Massachusetts 1

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NCOC-A

PROJECT NUMBER :PROJECT TITLE:SOLICITATION/CONTRACT NO.:
SCHEDULE OF MATERIAL SUBMITTALSVLSB 24-0019FAMCAMP Expansion
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSOTHERREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDIS- APPROVED
1Construction SchedulexWithin 1 week of NTP
2Light Pole SpecsxxBefore ordering
3Light SpecsxBefore ordering
4Wi-Fi Pole SpecsxxBefore ordering
595% Drawings
6As-Built Drawings
7Asphalt Mix DesignxAt time of paving
8Soil Compaction Test ResultsxPrior to paving
9
10
11
12
13
14
15
16
17
18
19

Solicitation No. F38604-99-1480 Attachment 6

AF FORM 66

(Computer Generated) PAGE &P of &N