AF Form 66 Repair East Water Tower Booster Pump.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- East Water Tower Pump Station Federal contract opportunity
- Solicitation number
- FA303020Q0027
About this file
This document contains a schedule of material submittals and federal contract opportunity solicitation. The schedule of material submittals outlines various submittal requirements for a base-wide gate valve repair project, including traffic control plans, safety policies, as-built drawings, and manufacturer manuals. The federal contract opportunity solicitation is seeking offers for an above-ground, factory-built pressure booster station at East Water Tower at Goofdellow Air Force Base. The requirement will be solicited as a request for written quotation and evaluated under FAR Simplified Acquisition Procedures. This is a 100% Service-Disabled Veteran Owned Small Business set-aside with a NAICS code of 333914 and size standard of 750 employees. The anticipated award date is September 28, 2020 and period of performance is 150 days after award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0002 - FA303020Q0027.zip | ZIP file | |
| Questions and Answers.pdf | ||
| Amendment 0001 - FA303020Q0027.zip | ZIP file | |
| East Tower Booster Pump SOW_11Sept20.pdf | ||
| Solicitation - FA303020Q0027.pdf | ||
| Pictures of Site.pdf | ||
| East Tower Booster Pump SOW 09Sep20.pdf | ||
| Base Access Letter template.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT: Base-Wide Gate Valve Repair | CP# 1035508 | SOLICITATION/CONTRACT NO. | |||||||||||||||||||||
| TO BE COMPLETED BY THE PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||||
| NO. OF COPIES REQUIRED | ||||||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL (Ref spec & para no.) | CERTIFICATION | OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S | RECOMMENDATIONS | MANUFACTURER'S | WARRANTY | OPERATING | INSTRUCTIONS | SEE PARA | OTHERS AS SPECIFIED | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CON-TRACTING | DATE TO CIVIL ENGINEER-ING | RETURN SUSPENSE DATE | FOLLOW UP | DATE CONTRACTOR NOTIFIED | CONTRACT-TOR RE- SUBMIT- TAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DISAPPROVED | |||||||||||||||||||||||
| 1 | Para. 1.5 - Working Conditions | 1 | 14 Days Prior (e) | FIO | ||||||||||||||||||||
| 2 | Para. 1.5.1 - Work Schedule | 1 | 14 Days Prior (e) | GA | ||||||||||||||||||||
| 3 | Para 1.10 Portable toilet locations | 1 | (e) | GA | ||||||||||||||||||||
| 4 | Para 1.7.1 - Traffic Control Plan | 1 | (e) | GA | ||||||||||||||||||||
| 5 | Para 1.7.2 Company Safety Policy and Accident Prevention Plan | 1 | x | (c) | GA | |||||||||||||||||||
| 6 | Para 1.13 List of Warranties and Certificates | 1 | Upon Final Acceptance by Gov | GA | ||||||||||||||||||||
| 7 | Para 1.14.1 Parking & Storage | 1 | (e) | GA | ||||||||||||||||||||
| 8 | Para 1.15.1.1 AF Form 103 Base Work Clearance Request | 1 | (e) | GA | ||||||||||||||||||||
| 9 | Para 1.15.2 Utility Outages | 1 | 14 Days Prior (e) | GA | ||||||||||||||||||||
| 10 | Para 1.16 Waste Disposal | 1 | (d) | GA | ||||||||||||||||||||
| 11 | Para 2.2 Hazardous Waste Records | 2 | x | (b) | GA | |||||||||||||||||||
| 12 | Para 2.3 Haz. Material List with worksheet for each SDS | 2 | x | (c) | GA | |||||||||||||||||||
| 13 | Para 2.6 Air Emissions Reports | 2 | x | (b) | FIO | |||||||||||||||||||
| 14 | Para 2.7 Construction Waste Management Form | 2 | (b) | GA | ||||||||||||||||||||
| 15 | Para 2.11 Contractor Responsibility | 2 | x | Upon Final Acceptance by Gov | GA | |||||||||||||||||||
| 16 | Para 3.3 CPM: Manufacturer's Specifications | 3 | 30 Days After NTP | GA | ||||||||||||||||||||
| 17 | Para 3.3 e.CPM:Electrical wiring and materials | 3 | 30 Days After NTP | GA | ||||||||||||||||||||
| 18 | Para 3.3 f. CPM: Panelboard | 3 | 30 Days After NTP | GA | ||||||||||||||||||||
| 19 | Para 3.3 h. CPM: Reinforced concrete pad plan | 3 | 30 Days After NTP | GA | ||||||||||||||||||||
| 20 | Para 3.3 i. CPM: Gate valves, risers and material | 3 | 30 Days After NTP | GA | ||||||||||||||||||||
| 21 | Para 4.3.2 h. - Electrical/Controls | 4 | 30 Days After NTP | GA | ||||||||||||||||||||
| 22 | Para 4.4 b. Lesson Plan | x | 4 | 30 Days before end of POP | GA | |||||||||||||||||||
| 23 | Para 4.5 a. As-Built Drawings | x | 4 | (b) | GA | |||||||||||||||||||
| 24 | Par 4.5 b. Manufacturer's Manuals and Materials | x | 4 | (b) | GA | |||||||||||||||||||
| AF Form 66, SEP 86 | ||||||||||||||||||||||||
| (a) As soon as possible but in no case later than 45 calendar days after NTP. | ||||||||||||||||||||||||
| (b) Prior to Final Inspection. | ||||||||||||||||||||||||
| (c) Prior to Use. | ||||||||||||||||||||||||
| (d) As Required. | ||||||||||||||||||||||||
| (e) Prior to start of work. | ||||||||||||||||||||||||
| (f) Weekly. |
PAGE &P OF &N
FORM66.xls
Sheet2
File details come from the government source that posted it. Updated .