AF Form 66 _ Bldg. 170 Boilers and Pump Replacement.pdf

PDF 84 KB Posted

Attached to
Selfridge _ Bldg. 170 Boilers Federal contract opportunity
Solicitation number
W50S8520R0006
Issued by
Department of the Army Michigan Army National Guard

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NO.

VGLZ 192044

APPROVED DISAPPROVED

01.00.00 Submittal Schedule - AF Form 66 10

01.00.00

Transfer and Acceptance of DOD Real Property - DD Form 1354 60

01.00.00

Contractor Hazardous Material Identification - SANGB Form 23 10

01.00.00

Solid Waste Recycling and Disposal Reporting Form 72 60

01.00.10 Affirmative Procurement Reporting Form 60

01.00.00 DD Form 1354 60

01.32.00

Construction Schedule AF 3064 submittals 10

01.32.33 Construction Photos 45

01.35.23 Safety Documentation as stated 10

01.40.00 Schedule of Test and Inspections 21

01.40.00 Permits, Licenses and Certificates 10

01.40.00 Quality Control Plan 10

01.74.00 Warranties 10

01.75.00

Starting System -Testing, Adjusting & Balancing Reports 60

15 01.78.23 O & M Data 15

16 01.78.39 Project Record Documents Close out Documantation 60

17 01.79.00 Instructional Training Program as applicable 60

Product Data 18 23.05.13

Common Motor Requirements for HVAC Equipment

REMARKSFINAL

APPROVAL

CONTRACTOR

RESUBMITTAL

RETURN

SUSPENSION

DATE

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE OF

SUBMITTAL

FOLLOW-UP

SUBMITTAL

REQUIRED

BY XX DAYS

AFTER

NTP

DATE

RECEIVED

IN

CONTRACTING

DATE

TO

CIVIL

ENGINEERING

DATE CONTRACTOR NOTIFIED

O

PE

R

AT

IN

G

IN

ST

R U

C

TI

O N

S

C

AT

AL

O

G D

AT

A

LI

N

E N

U M

BE

R

M

AN

U

FA

C

TU

R

ER

'S W

AR

R

AN

TY

O

TH

ER

M

AT

ER

IA

L o r

D

AT

A

SH

O

P D

R

AW

IN

G

S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

C

TU

R

ER

'S

R

EC

O M

M

EN

D

AT

IO

N

S

Spec Section

C

ER

TI

FI

C

AT

IO

N

O F

C O

M

PL

IA

N

C E

AN

D

C

LO

SE

O

U T

SOLICITATION/CONTRACT NO.PROJECT TITLE

Building 170 - Replace Boilers and Pumps

SCHEDULE OF MATERIAL SUBMITTALS

(AF Form 66 Modified)

NO. OF COPIES REQUIRED

TO BE COMPLETED BY PROJECT ENGINEER

APPROVED DISAPPROVED

REMARKSFINAL

APPROVAL

CONTRACTOR

RESUBMITTAL

RETURN

SUSPENSION

DATE

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE OF

SUBMITTAL

FOLLOW-UP

SUBMITTAL

REQUIRED

BY XX DAYS

AFTER

NTP

DATE

RECEIVED

IN

CONTRACTING

DATE

TO

CIVIL

ENGINEERING

DATE CONTRACTOR NOTIFIED

O

PE

R

AT

IN

G

IN

ST

R U

C

TI

O N

S

C

AT

AL

O

G D

AT

A

LI

N

E N

U M

BE

R

M

AN

U

FA

C

TU

R

ER

'S W

AR

R

AN

TY

O

TH

ER

M

AT

ER

IA

L o r

D

AT

A

SH

O

P D

R

AW

IN

G

S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

C

TU

R

O M

M

EN

D

AT

IO

N

S

Spec Section

C

ER

TI

FI

C

AT

IO

N

O F

C O

M

PL

IA

N

C E

AN

D

C

LO

SE

O

U T

SOLICITATION/CONTRACT NO.PROJECT TITLE

Building 170 - Replace Boilers and Pumps

SCHEDULE OF MATERIAL SUBMITTALS

(AF Form 66 Modified)

NO. OF COPIES REQUIRED

TO BE COMPLETED BY PROJECT ENGINEER

Product Data 15

18 23.05.17 Sleeves and Sleeve Seal for HVAC Piping 19 Product Data for General Duty Valves 15 20 23.05.18 Escutcheons for HVAC Piping 21 Product Data as req'd 22 23.05.19 Meters and Gages for HVAC Piping

Product Data for Meters and Gages as req'd Shop Drawing as req'd O & M Data as req'd Warranty as req'd

23 23.05.23 General-Duty Valves for HVAC Piping as req'd Product Data for General Duty Valves as req'd

24 22.05.29 Hangers & Supports for HVAC Piping & Equipment Product Data as req'd Shop Drawing as req'd O & M Data as req'd Warranty as req'd

23.05.53

Identifcation for HVAC Piping and Equipment

Product Data as req'd Sample for ID as req'd Equipment Label Schedule / Scheme as req'd Valve Schedule as req'd

26 23.05.93 Testing, Adjusting, & Balancing for HVAC Qualification Data Contract Document Examination Report 60 Certified TAB Reports 60

27 23.07.19 HVAC Piping Insulation

Product Data on Insulation as req'd Samples of Insulation as req'd

28 23.09.00 Instrumentation & Control for HVAC Product Data on DDC System & Controls 15 Shop Drawing 15 Data Comm. Protocol Certificates 15

APPROVED DISAPPROVED

REMARKSFINAL

APPROVAL

CONTRACTOR

RESUBMITTAL

RETURN

SUSPENSION

DATE

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE OF

SUBMITTAL

FOLLOW-UP

SUBMITTAL

REQUIRED

BY XX DAYS

AFTER

NTP

DATE

RECEIVED

IN

CONTRACTING

DATE

TO

CIVIL

ENGINEERING

DATE CONTRACTOR NOTIFIED

O

PE

R

AT

IN

G

IN

ST

R U

C

TI

O N

S

C

AT

AL

O

G D

AT

A

LI

N

E N

U M

BE

R

M

AN

U

FA

C

TU

R

ER

'S W

AR

R

AN

TY

O

TH

ER

M

AT

ER

IA

L o r

D

AT

A

SH

O

P D

R

AW

IN

G

S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

C

TU

R

O M

M

EN

D

AT

IO

N

S

Spec Section

C

ER

TI

FI

C

AT

IO

N

O F

C O

M

PL

IA

N

C E

AN

D

C

LO

SE

O

U T

SOLICITATION/CONTRACT NO.PROJECT TITLE

Building 170 - Replace Boilers and Pumps

SCHEDULE OF MATERIAL SUBMITTALS

(AF Form 66 Modified)

NO. OF COPIES REQUIRED

TO BE COMPLETED BY PROJECT ENGINEER

29 23.09.23.11 Control Valves Product Data 15 Shop Drawing 15 O & M Data 15 Warranty 15

30 23.09.23.12 Control Dampers Product Data as req'd Shop Drawing as req'd O & M Data as req'd Warranty as req'd

31 23.09.93.11 Sequence of Operation for HVAC DDC Control Sequences 15

33 23.21.13 Hydronic Piping Product Data on the following Material: 15 Air Control Devices 15 Hydronic Specialties 15 O & M Data 15

34 23.21.16 Hydronic Piping Specialities Product Data 15 Shop Drawing 15 Warranty 15 O & M Data 15

35 23.21.23 Hydronic Pumps Product Data 15 Shop Drawing 15 Warranty 15 O & M Data 15

36 23.25.13 Water Treatment for Closed-Loop Hydronic Systems Product Data 15 Shop Drawing 15 Warranty 15 O & M Data 15

37 23.52.16 Condensing Boilers Product Data 15 Shop Drawing 15 Warranty 15 O & M Data 15

APPROVED DISAPPROVED

REMARKSFINAL

APPROVAL

CONTRACTOR

RESUBMITTAL

RETURN

SUSPENSION

DATE

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE OF

SUBMITTAL

FOLLOW-UP

SUBMITTAL

REQUIRED

BY XX DAYS

AFTER

NTP

DATE

RECEIVED

IN

CONTRACTING

DATE

TO

CIVIL

ENGINEERING

DATE CONTRACTOR NOTIFIED

O

PE

R

AT

IN

G

IN

ST

R U

C

TI

O N

S

C

AT

AL

O

G D

AT

A

LI

N

E N

U M

BE

R

M

AN

U

FA

C

TU

R

ER

'S W

AR

R

AN

TY

O

TH

ER

M

AT

ER

IA

L o r

D

AT

A

SH

O

P D

R

AW

IN

G

S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

C

TU

R

O M

M

EN

D

AT

IO

N

S

Spec Section

C

ER

TI

FI

C

AT

IO

N

O F

C O

M

PL

IA

N

C E

AN

D

C

LO

SE

O

U T

SOLICITATION/CONTRACT NO.PROJECT TITLE

Building 170 - Replace Boilers and Pumps

SCHEDULE OF MATERIAL SUBMITTALS

(AF Form 66 Modified)

NO. OF COPIES REQUIRED

TO BE COMPLETED BY PROJECT ENGINEER

38 26.05.19 Low-Voltage Electrical Power Conductors & Cables Product Data for Each Type of Cable as req'd

39 26.05.26 Grounding & Bonding for Electrical Systems O & M Data as req'd

40 26.05.33 Raceway & Boxes for Electrical Systems Product Data on the following Material: as req'd Metal Conduit & Tubing as req'd Metal Wireways as req'd Surface Raceways as req'd Boxes, Enclosures, Cabinets as req'd

41 26.24.16 Panelboards Product Data as req'd Shop Drawings as req'd O & M Data as req'd Warranty as req'd

42 26.28.16 Enclosed Switches Product Data as req'd Shop Drawings as req'd O & M Data as req'd

43 26.29.13 Enclosed Controllers Product Data as req'd Shop Drawings as req'd O & M Data as req'd