04 - AF Form 66 - MBMV212831 - LED Lighting South side.xls
Air Force Form XLS spreadsheet 40 KB Posted
- Solicitation number
- W50S84-21-B-0009
- Issued by
-
Department of the Army National Guard
About this file
This document contains a schedule of material submittals for a federal contract to upgrade LED lighting at Battle Creek Air National Guard Base. The contractor will replace current fluorescent fixtures and lighting with energy efficient LED fixtures and lighting in Buildings 6900, 6901, 6903, 6905, and 6913. Key submittals include a submittal schedule, construction schedule, quality control plan, shop drawings for LED lights, occupancy sensors and dimming switches/controls. The submittals are due 14 days after notice to proceed with returns to the contractor expected within 14 days. The solicitation was issued by the Department of the Army National Guard under number W50S84-21-B-0009 for an LED lighting upgrade to reduce energy consumption and costs at the base in accordance with DOD and federal policies.
View the file
Other versions and copies of AF Form 66
Show all 20
Who attaches AF Form 66
| State | Files |
|---|---|
| Iowa | 1 |
| Massachusetts | 1 |
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| SCHEDULE OF MATERIAL SUBMITTALS | |||||||||||||||
| (AF Form 66 Modified) | PROJECT NO. | PROJECT TITLE | SOLICITATION/CONTRACT NO. | ||||||||||||
| MBMV212831 | LED LIGHTING – SOUTH SIDE OF BASE | ||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | |||||||||||||||
| NO. OF COPIES REQUIRED | |||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE AND CLOSEOUT | SHOP DRAWINGS | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OTHER MATERIAL OR DATA | OPERATING INSTRUCTIONS | SUBMITTAL |
REQUIRED
BY 14 DAYS
AFTER
NTP DATE
RECEIVED
IN
CONTRACTING DATE
TO
CIVIL
ENGINEERING RETURN
SUSPENSION
| DATE | FOLLOW-UP | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL | ||||||
| APPROVAL | REMARKS | |||||||||
| APPROVED | DISAPPROVED | |||||||||
| 1 | Submittal Schedule - AF Form 66 | 1 | x | |||||||
| 2 | Transfer and Acceptance of DOD Real Property - DD Form 1354 | 1 | x | |||||||
| 3 | Contractor Hazardous Material Identification | 1 | x | |||||||
| 4 | Solid Waste Recycling and Disposal Reporting Form | 1 | x | |||||||
| 5 | Affirmative Procurement Reporting Form | 1 | x | |||||||
| 6 | Construction Schedule | 1 | x | |||||||
| 7 | Construction Photos | 1 | ||||||||
| 8 | Safety Documentation as stated | 1 | x | |||||||
| 9 | Permits, Licenses and Certificates | 1 | x | |||||||
| 10 | Quality Control Plan | 1 | x | |||||||
| 11 | LED Light | 1 | 1 | 1 | 1 | |||||
| 12 | Occupancy Senor | 1 | 1 | 1 | ||||||
| 13 | Dimming switch/controls | 1 |