Attachment_07_AF_Form_66.pdf

PDF 253 KB Posted

Attached to
Repair Backflow Preventers Federal contract opportunity
Solicitation number
FA481918B7005
Issued by
Department of the Air Force Air Combat Command

About this file

AF Form 66

View the file

Other files for this federal contract opportunity

Other files attached to Repair Backflow Preventers, newest first.
File Type Posted
FA481918B7005_Amendment_1.pdf PDF
Q&A.pdf PDF
Appendix_B_-_Survey_Field_Reports.pdf PDF
Attachment_01_SOW_Repair_Backflow_Preventers.pdf PDF
FA481918B7005.pdf PDF
Attachment_06_AF3065.pdf PDF
Attachment_02_APPENDIX_A_Repair_Backflow_Preventers.pdf PDF
Attachment_04,_AF_Form_3000.pdf PDF
Attachment_03_Wage_Determination.pdf PDF
Attachment_05_AF_3064.pdf PDF
Attachment_1_-_DRAFT_Statement_of_Work.pdf PDF
Pre-Solicitation_Notice_-_Repair_Backflow_Preventers.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

8 11

/REPLACE BACKFLOW

PREVENTERS, BASEWID

AF FORM 66 SCHEDULE OF

MATERIAL SUBMITTALS

Page Intentionally Left Blank

PROJECT NUMBER SOLICITATION/CONTRACT NO.

FA4819-18-C-XXXX

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION OF ITEM, CONTRACT

REFERENCE, TYPE OF SUBMITTAL

C

ER

TI

FI

C

AT

E O

F C

O M

PL

IA

N C

E

SH

O

P D

R

AW

IN

G

S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

C

TU

R

ER

'S R

EC

O

M M

EN

D

AT

IO

N S

M

AN

U

FA

C

TU

R

ER

'S W

AR

R

AN

TY

C

AT

AL

O

G D

AT

A

O

PE

R

AT

IN

G

IN

ST

R U

C

TI

O N

S

AS

-B U

IL

T

D R

AW

IN

G S

D

IS

K

D O

C U

M

EN

TA

TI

O N

A S

R

EQ

U

IR

ED

R

EQ

U

IR

ED

S

U

BM

IS

SI

O N

D

AT

E

D

AT

E R

EC

EI

VE

IN

C

N

TR

AC

TI

N G

D

AT

E

TO

C

IV

IL

EN

G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

SE

E

SU

BM

IT

TA

L N

U M

BE

R

S

DATE CONTRACTOR NOTIFIED

C O

N

TR

AC

TO

R

ES

U

BM

IT

TA

L

FI

N

AL

A

PP

R

O

VA

L

REMARKS

APPROVED DISAPPROVED

1 Kick-Off Meeting Award + 7 Days

2 Meeting Minutes (All Meetings) Meeting + 2 Days

3 Project Schedule - AF Form 3064 At Kick-Off Meeting

4 Work Clearance Request / Digging Permit - AF Form 103

10 Days Prior to Commencing

Work

3 Contractor Badging Applications Award + 14 Days

4 HAZMAT Inventory Form 81 & 82 14 Days Prior to

Commencing Work

5 Regulatory Agency Permit / Exemption Documentation

14 Days Prior to Commencing

Work

6 Contractor's Work Plan

5 Days After Each Field Condition

Assessment

7 Material Approval - AF Form 3000 1 1 1 1 7 Days Prior to Order

8 Progress Report - AF Form 3065 Weekly

R E F

Backflow Assembly Testing Reports 3 Days After Field Testing

R E F

Construction Material Testing Reports Upon Receipt

1 1

SCHEDULE OF MATERIAL SUBMITTALS

PROJECT TITLE

XLWU 18-1011 REPAIR/REPLACE BACKFLOW PREVENTERS, BASEWIDE

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

AF Form 66 1 of 2

PROJECT NUMBER SOLICITATION/CONTRACT NO.

FA4819-18-C-XXXX

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION OF ITEM, CONTRACT

REFERENCE, TYPE OF SUBMITTAL

C

ER

TI

FI

C

AT

E O

F C

O M

PL

IA

N C

E

SH

O

P D

R

AW

IN

G

S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

C

TU

R

ER

'S R

EC

O

M M

EN

D

AT

IO

N S

M

AN

U

FA

C

TU

R

ER

'S W

AR

R

AN

TY

C

AT

AL

O

G D

AT

A

O

PE

R

AT

IN

G

IN

ST

R U

C

TI

O N

S

AS

-B U

IL

T

D R

AW

IN

G S

D

IS

K

D O

C U

M

EN

TA

TI

O N

A S

R

EQ

U

IR

ED

R

EQ

U

IR

ED

S

U

BM

IS

SI

N

E

D

AT

E R

EC

EI

VE

IN

C

N

TR

AC

TI

N G

D

AT

E

TO

C

IV

IL

G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

SE

E

SU

BM

IT

TA

L N

U M

BE

R

S

DATE CONTRACTOR NOTIFIED

C O

N

TR

AC

TO

ES

U

BM

IT

TA

L

FI

N

AL

A

PP

R

O

VA

L

REMARKS

APPROVED DISAPPROVED

SCHEDULE OF MATERIAL SUBMITTALS

PROJECT TITLE

XLWU 18-1011 REPAIR/REPLACE BACKFLOW PREVENTERS, BASEWIDE

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

R E F

Production of Delivery Problem Report Same Day of Problem

R E F

Welding/Burn Permit - As Required 3 Days Prior to Commencing

Hot Work R E F

Draft DD 1354 - Transfer & Acceptance of Military Real Property NTP +30 Days

R E F

Pre-Final Inspection Report Pre-Final + 3 Days

R E F

Contractor Environmental Reporting Entry - TAFB Form 83

Prior to Final Inspection

R E F

Equipment Manuals and Parts Lists Prior to Final Inspection

R E F

Final DD 1354 - Transfer & Acceptance of Military Real Property

At Final Inspection

R E F

Comprehensive Device Installation List At Final Inspection

R E F

Project Close Out Documents Final

Inspection + 7 Days