Appendix B - AF Form 66 Design-Build 11-17-08.xls

XLS spreadsheet 66 KB Posted

Attached to
construct Emergency Control Center at Bldg 272 Federal contract opportunity
Solicitation number
FA2816-09-R-0064
Issued by
Department of the Air Force Space Command Space and Missile Systems Center

About this file

Attachment 9 - Appendix B - AF Form 66

View the file

Other files for this federal contract opportunity

Other files attached to construct Emergency Control Center at Bldg 272, newest first.
File Type Posted
Wage Determination CA080033.pdf PDF
Section 01010 - Environmental Requirements.pdf PDF
Attachment 5 - Warranty Letter Example.pdf PDF
PerformanceQuestionnaire.pdf PDF
FA2816-09-R-0064.pdf PDF
Rm 158 Conceptual Drawing.ppt PPT presentation
Appendix A - Schedule of Contract Documents.xls XLS spreadsheet
Attachment 7 - SECTION 02085.pdf PDF
Attachment 6 - SECTION 02086.pdf PDF
Drawings.zip ZIP file
Attachment 1 - SOW.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBER:PROJECT TITLE:SOLICITATION / CONTRACT NO.:
ACJP -092092Construct Emergency Control Centerxxx
(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTSDRAWINGSCOST ESTIMATETECHNICAL DATATEST REPORTSFIELD REPORTSELECTRONIC VERSION (CD or DVD)REQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
1Project Manager and designated representatives contact information (SOW Sec 5.8.1)21At time of NTP
2Project Schedule (SOW Sec 5.2)21NTP plus 5 working days - Updated weekly
3Meeting Minutes (SOW Sec 5.5.1)215 working days after event
4A-E Design Professionals List (SOW Sec 6.1)21Prior to start of Design Phase
5Preliminary Design submittal (35 percent) (SOW Sec 6.3.2)222Per Project Schedule
6Issued for Construction Submittal (100 percent) (SOW Sec 6.3.5)332Per Project Schedule
7Site Safety Plan (SOW Sec 7.4.3215 working days prior to onsite work
8Work Phasing Plan (SOW Sec 7.2.1)215 working days after NTP
9Environmental Protection Plan (Spec Sec 01010 - Section 1.6)215 working days prior to onsite work
10AF form 3952, MSDS Chemical/Hazardous Material Request Authorization (Spec Sec 01010 - Section 1.9)215 working days prior to use
11Hazardous Material Spill/Release Report (Spec Sec 01010 - Section 1.10)21As required
12Green Procurement Determination Form and Estimate/Certification Form (Spec Sec 01010 - Section 1.11)215 working days prior to onsite work
13Construction & Demolition Debris Report (Spec Sec 01010 - Section 1.13)21As required
14Construction Material and Shop Drawing Submittals Schedule/Log (SOW Sec 7.2.2)21At start of Construction Phase - Updated weekly
15AF Form 3000, Material Submittals (SOW Sec 7.2.2)22222222222As required
16A-E Site Visit Report (SOW Sec 6.4.2)215 working days after meeting
17Operations and Maintenance Manuals (SOW Sec 8.3)2230 days after BOD
18Operations and Maintenance Training Video (SOW Sec 8.3)230 days after BOD
19Equipment/Workmanship Warranty Letter (SOW Sec 8.4)2230 days after BOD
20DD-1354 Transfer and Acceptance of Real Property (Draft / Interim) (SOW Sec 8.5)2120 days prior to BOD
21DD-1354 Transfer and Acceptance of Real Property (Final) (SOW Sec 8.5)2130 days after BOD
22Construction Record Drawings (SOW Sec 8.6 and 8.7)2130 days after BOD
23
24
25
26
27

&L&"Arial,Bold"&8Schedule of Material Submittals, Feb 05 (SAF/AQCP) AF Form 66 (11-6-08)&C&"Arial,Bold"&8&P of &N&R&"Arial,Bold"&8Appendix B Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)

Enter any comments pertaining to the submittal