Attachment 3 - AF Form 66 Design-Build Fire Alarm Panel Upgrade.xls
Air Force Form XLS spreadsheet 71 KB Posted
- Solicitation number
- FA2816-09-R-0030
About this file
Attachment 13 - AF Form 66
View the file
Other versions and copies of AF Form 66
Show all 20
Who attaches AF Form 66
| State | Files |
|---|---|
| Iowa | 1 |
| Massachusetts | 1 |
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers.docx | DOCX document | |
| fire_alarm_what_model.jpg | JPG image | |
| Fire Alarm Drawing 2.PDF | ||
| Fire Alarm Drawing 1.PDF | ||
| amendment 2.pdf | ||
| ammendment 1.pdf | ||
| Recovery Repair Fire Alarm SOLICITATION.pdf | ||
| Design-Build SOW Replace Fire Alarm_Blg 286.doc | DOC document | |
| Appendix A - Detailed Scope of Work Fire Alarm Panel.doc | DOC document | |
| wagedetermination.doc | DOC document | |
| Drawing _286.pdf | ||
| Attachment 4 - SECTION 01010 JAN09.pdf | ||
| Fire panel photo.ppt | PPT presentation | |
| PerformanceQuestionnaire.doc | DOC document | |
| Attachment 6 -SECTION 02086 LAAFB Lead Specs Updated5Dec08.pdf | ||
| Attachment 5 - SECTION 02085 Updated5Dec08.pdf | ||
| Attachment 7 - Warranty Letter Example.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER: | PROJECT TITLE: | SOLICITATION / CONTRACT NO.: | ||||||||||||||||||||||
| ACJP081096 | REPLACE FIRE ALARM PANEL SYSTEM, FITNESS CENTER, BLG 286 | xxx | |||||||||||||||||||||||
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS | DRAWINGS | COST ESTIMATE | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | ELECTRONIC VERSION (CD or DVD) | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS |
| 1 | Project Manager and designated representatives contact information (SOW Sec 5.8.1) | 2 | 1 | At time of NTP | |||||||||||||||||||||
| 2 | Project Schedule (SOW Sec 5.2) | 2 | 1 | NTP plus 5 working days - Updated weekly | |||||||||||||||||||||
| 3 | Meeting Minutes (SOW Sec 5.5.1) | 2 | 1 | 5 working days after event | |||||||||||||||||||||
| 4 | A-E Design Professionals List (SOW Sec 6.1) | 2 | 1 | Prior to start of Design Phase | |||||||||||||||||||||
| 5 | Preliminary Design submittal (50 percent) (SOW Sec 6.3.2) | 2 | 2 | 2 | Per Project Schedule | ||||||||||||||||||||
| 6 | Issued for Construction Submittal (100 percent) (SOW Sec 6.3.5) | 3 | 3 | 2 | Per Project Schedule | ||||||||||||||||||||
| 7 | Site Safety Plan (SOW Sec 7.4.3 | 2 | 1 | 5 working days prior to onsite work | |||||||||||||||||||||
| 8 | Work Phasing Plan (SOW Sec 7.2.1) | 2 | 1 | 5 working days after NTP | |||||||||||||||||||||
| 9 | Environmental Protection Plan (Spec Sec 01010 - Section 1.6) | 2 | 1 | 5 working days prior to onsite work | |||||||||||||||||||||
| 10 | List of Equipment Requiring Air Permit (Spec Sec 01010 - Section 1.7) | 2 | 1 | 5 working days prior to onsite work | |||||||||||||||||||||
| 11 | Hazardous Waste Certification & Hazardous Waste Transporter Documentation (Spec Sec 01010 - Section 1.8) | 2 | 1 | As required | |||||||||||||||||||||
| 12 | AF form 3952, MSDS Chemical/Hazardous Material Request Authorization (Spec Sec 01010 - Section 1.9) | 2 | 1 | 5 working days prior to use | |||||||||||||||||||||
| 13 | Hazardous Material Spill/Release Report (Spec Sec 01010 - Section 1.10) | 2 | 1 | As required | |||||||||||||||||||||
| 14 | Green Procurement Determination Form and Estimate/Certification Form (Spec Sec 01010 - Section 1.11) | 2 | 1 | 5 working days prior to onsite work | |||||||||||||||||||||
| 15 | Construction & Demolition Debris Report (Spec Sec 01010 - Section 1.13) | 2 | 1 | As required | |||||||||||||||||||||
| 16 | NPDES General Permit Notice of Intent, SWPPP and Draft Notice of Termination (Spec Sec 01010 - Section 1.14) | 2 | 1 | 5 working days prior to onsite work | |||||||||||||||||||||
| 17 | Lead-Based Paint Abatement Submittals (Spec Sec 01010 - Section 1.15) | 2 | 1 | 5 working days prior to onsite work | |||||||||||||||||||||
| 18 | Asbestos Abatement Submittals (Spec Sec 01010 - Section 1.16) | 2 | 1 | 5 working days prior to onsite work | |||||||||||||||||||||
| 19 | AST Technical Information and Site Specific Spill Plan (Spec Sec 01010 - Section 1.19) | 2 | 1 | As required | |||||||||||||||||||||
| 20 | Construction Material and Shop Drawing Submittals Schedule/Log (SOW Sec 7.2.2) | 2 | 1 | At start of Construction Phase - Updated weekly | |||||||||||||||||||||
| 21 | AF Form 3000, Material Submittals (SOW Sec 7.2.2) | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | As required | ||||||||||||
| 22 | A-E Site Visit Report (SOW Sec 6.4.2) | 2 | 1 | 5 working days after meeting | |||||||||||||||||||||
| 23 | Operations and Maintenance Manuals (SOW Sec 8.3) | 2 | 2 | 30 days after BOD | |||||||||||||||||||||
| 24 | Operations and Maintenance Training Video (SOW Sec 8.3) | 2 | 30 days after BOD | ||||||||||||||||||||||
| 25 | Equipment/Workmanship Warranty Letter (SOW Sec 8.4) | 2 | 2 | 30 days after BOD | |||||||||||||||||||||
| 26 | DD-1354 Transfer and Acceptance of Real Property (Draft / Interim) (SOW Sec 8.5) | 2 | 1 | 20 days prior to BOD | |||||||||||||||||||||
| 27 | DD-1354 Transfer and Acceptance of Real Property (Final) (SOW Sec 8.5) | 2 | 1 | 30 days after BOD | |||||||||||||||||||||
| 28 | Construction Record Drawings (SOW Sec 8.6 and 8.7) | 2 | 1 | 30 days after BOD | |||||||||||||||||||||
| 29 | |||||||||||||||||||||||||
| 30 | |||||||||||||||||||||||||
| 31 | |||||||||||||||||||||||||
| 32 | |||||||||||||||||||||||||
| 33 |
&L&"Arial,Bold"&8Schedule of Material Submittals, Feb 05 (SAF/AQCP) AF Form 66 (11-6-08)&C&"Arial,Bold"&8&P of &N&R&"Arial,Bold"&8Design-Build Attachment 3 (11/17/08) Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE
(MM/DD/YY)
Enter the Submittal Number Enter Resubmittal Number Enter the submittal final approval date
(MM/DD/YY)
Enter any comments pertaining to the submittal
File details come from the government source that posted it. Updated .