This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to APTIM Environmental & Infrastructure, LLC under Contract Number HW689. The task assignment, numbered DC001E, was executed on February 26, 2025, with an effective completion date of May 30, 2025. FDEP's Department Project Manager is Nicole Knutson, while APTIM's Project Manager is Eric Kramer. The task encompasses multiple project locations and sites within Florida under the Critical Response initiative.

APTIM will prepare and present materials for a DEP Site Review Meeting to be conducted in Tallahassee, with deliverables including meeting notes and action items due on April 11, 2025. The scope of work encompasses project review material preparation, travel to and from Tallahassee, hotel accommodations, and per diem expenses. The total task value is $11,779.79, calculated on a fixed unit rate basis. Cost components include direct labor totaling $4,213.08 (60 hours across project management and engineering/scientist categories), overhead and fringe benefits of $5,768.55, travel expenses of $800.00 (including $240.00 vehicle rental and $560.00 for hotel and per diem), and a completion fee of $998.16. No subcontractor, laboratory, or field equipment costs are included. Invoicing is contingent upon submission of meeting notes, action items, and project management documentation by the due date.

View the file

Other files

File Type Posted
CN-370000-HW689-BF01B.pdf PDF
CN-370000-HW689-BF01E.pdf PDF
CN-370000-HW689-BF1ECO1.pdf PDF
CN-370000-HW689-BIL01B.pdf PDF
CN-370000-HW689-BIL01C.pdf PDF
CN-370000-HW689-BIL01F.pdf PDF
CN-370000-HW689-BIL1ECO1.pdf PDF
CN-370000-HW689-CSS1ACO1.pdf PDF
CN-370000-HW689-DC002B.pdf PDF
CN-370000-HW689-DC003C.pdf PDF
CN-370000-HW689-DC009B.pdf PDF
CN-370000-HW689-DC011A.pdf PDF
CN-370000-HW689-DC011C.pdf PDF
CN-370000-HW689-DC015A.pdf PDF
CN-370000-HW689-DC015C.pdf PDF
CN-370000-HW689-DC017A.pdf PDF
CN-370000-HW689-DC018A.pdf PDF
CN-370000-HW689-DC026B.pdf PDF
CN-370000-HW689-DC03A.pdf PDF
CN-370000-HW689-DC03BCO1.pdf PDF
CN-370000-HW689-DC04BCO1.pdf PDF
CN-370000-HW689-DC05CCO2.pdf PDF
CN-370000-HW689-DC08BCO1.pdf PDF
CN-370000-HW689-DC08CCO4.pdf PDF
CN-370000-HW689-DC09CCO1.pdf PDF
CN-370000-HW689-DC11BCO1.pdf PDF
CN-370000-HW689-DC11BCO2.pdf PDF
CN-370000-HW689-DC11CCO1.pdf PDF
CN-370000-HW689-DC12BCO3.pdf PDF
CN-370000-HW689-DC13BCO6.pdf PDF
CN-370000-HW689-DC14ACO1.pdf PDF
CN-370000-HW689-DC15ACO1.pdf PDF
CN-370000-HW689-DC15DCO3.pdf PDF
CN-370000-HW689-DC15DCO4.pdf PDF
CN-370000-HW689-DC15ECO1.pdf PDF
CN-370000-HW689-DC16CCO4.pdf PDF
CN-370000-HW689-DC17BCO2.pdf PDF
CN-370000-HW689-DC17BCO3.pdf PDF
CN-370000-HW689-DC19BCO1.pdf PDF
CN-370000-HW689-DC24BCO1.pdf PDF
CN-370000-HW689-DC28ACO1.pdf PDF
CN-370000-HW689-DC29ACO3.pdf PDF
CN-370000-HW689-DC29ACO4.pdf PDF
CN-370000-HW689-DC32ACO3.pdf PDF
CN-370000-HW689-FIL10.pdf PDF
CN-370000-HW689-FIL11.pdf PDF
CN-370000-HW689-FIL14.pdf PDF
CN-370000-HW689-FIL17.pdf PDF
CN-370000-HW689-FIL18.pdf PDF
CN-370000-HW689-FIL6.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW689

DC001E Completion May 30, 2025

APTIM staff will prepare and present materials for the DEP Site Review Meeting.

Nicole Knutson 850-245-8763 Contractor APTIM Environmental & Infrastructure Contractor

Contractor Eric Kramer Contractor 407 287 3216 Multiple

Multiple

Multiple

Contractor Contractor

✔ $ 11,779.79

$ 11,779.79

Scope of Work

APTIM Environmental & Infrastructure Contractor

Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2025.02.27 13:46:02 -05'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.02.26 10:28:58 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtasks 2 & 1: Site Review Meeting notes and action items & PM 04/11/2025

Subtasks 2 & 1: Site Review Meeting notes and action items & PM $ 11,779.79

$ 11,779.79

HW689

DC001E

FFLORIDAA DEPARTMENTT OF

EEnvironmentall Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ronn DeSantis Governor

Jeanette Nuñez Lt. Governor

Alexiss A.. Lambert Secretary

Memorandum

TO: Multiple Sites

FROM: Nicole Knutson, Project Manager

SUBJECT: Negotiation Summary

HW689 DC001E

DATE: February 26, 2025

This task assignment includes travel expenses, including vehicle rentals and lodging, and labor hours for meeting preparation and meeting attendance.

Total task amount is $1 . APTIM’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is April 11, 2025. Task completion date is May 30, 2025.

FDEP COST ESTIMATE

Contractor: Aptim Environmental & Infrastructure, LLC

Date: 2/20/2025

Task #: HW689 - DC001F SubTask 1 Project Management

Site: Critical Response SubTask 2 Site Review Meeting

Activity/Phase: Site Review Meetoing SubTask 3

Project Manager: Eric Kramer SubTask 4

SubTask 5

TTotals 1 2 3 4 5 Labor Rate Category

$73.18 PProject Manager E. Kramer 7 6.6 $73.18 Engineer/Scientist 5 E. Kramer 20 20 0 0 0 $68.63 Engineer/Scientist 5 G. Roberts 33 33 0 0 0

Engineering Technician 4 A. Escobar 0 0 0 0 0 Designer 2 S. Ferianc 0 0 0 0 0 Technical Publications Specialist 3 H. Vining 0 0 0 0 0

$0.00 0 0 0 0 0 Total Hours 60 7 53 0 0 0

Direct Labor $4,213.08 $484.69 $3,728.39 $0.00 $0.00 $0.00

Overhead 85.58% $3,605.56 $414.80 $3,190.76 $0.00 $0.00 $0.00 Gen & Admin 19.38% $816.49 $93.93 $722.56 $0.00 $0.00 $0.00 Fringe 31.96% $1,346.50 $154.91 $1,191.59 $0.00 $0.00 $0.00 Total Labor $9,981.63 $1,148.33 $8,833.30 $0.00 $0.00 $0.00

Travel Vehicle Rental $240.00 $240.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $560.00 $560.00 $0.00 $0.00 $0.00 Total Travel $800.00 $800.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF SHAW Page 1

FDEP COST ESTIMATE

Contractor: Aptim Environmental & Infrastructure, LLC

Date: 2/20/2025

Task #: HW689 - DC001F SubTask 1 Project Management

Site: Critical Response SubTask 2 Site Review Meeting

Activity/Phase: Site Review Meetoing SubTask 3

Project Manager: Eric Kramer SubTask 4

SubTask 5

TTotals 1 2 3 4 5 Total Subcontractor Cost $$0.00 $0.00 $0.00 $0.00 $0.00

LLaboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $$0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $10,781.63 $1,148.33 $9,633.30 $0.00 $0.00 $0.00 Completion Fee $998.16 $114.83 $883.33 $0.00 $0.00 $0.00

Total Estimated Cost $11,779.79 $1,263.16 $10,516.63 $0.00 $0.00 $0.00

REV: 02/03 CEF SHAW Page 2

SITE :

SUBTASK:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Engineer/Scientist 5 E. Kramer 20

Engineer/Scientist 5 G. Roberts 33

TOTAL LABOR 53

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Day 0 $0.00 Van or Truck $120.00 Day 2 $240.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

Hotel 0 $225.00 Day 2 $450.00 Day 1-leave before 6:00 AM 0 $36.00 Day 0 $0.00 Day 1-Leave between 6 - Noo 0 $30.00 Day 0 $0.00 Day 1-leave before 6:00 PM 0 $19.00 Day 2 $38.00 Day 0 $36.00 Day 2 $72.00

TOTAL PER DIEM $560.00

SUBCONTRACTOR COSTS

NAME PURPOSE USAGE COST

Drum $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00

Sample Shipping (Small cooler) $110.00 $0.00 Sample Shipping (large cooler) $150.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 0 $0.00 55-gallon Drum $100.00 Each 0 $0.00

TOTAL EQUIPMENT $0.00

Critical Response

2/20/2025

Preparation of project summary (3 hrs.), Round Trip Travel (10 hrs), Attend Program/Project Review Meeting (6 hrs), Review Meeting Notes (1 hr)

Research Project Questions and Preparation of Review Documents/Presentation for Meeting (15 hrs), Round Trip Travel to Meeting (10 hrs), Attend Program/Project Review Meeting (6 hrs), Preparation of Summary Notes for Deliverable (2 hrs)

Site Review Meeting

Proposed Scope of Work APTIM Environmental & Infrastructure Project Meeting Contract HW689, Task Assignment DC001E APTIM Environmental & Infrastructure, LLC 2/20/25

Task Assignment (TA) DC001E has been prepared for the requested project review meeting to be conducted in Tallahassee as schedules allow. The LOE includes preparation of project review materials in accordance with the previously provided FDEP Contractor Site Review Meeting Tasking Guidance document.

The TA will also include travel to and from Tallahassee, hotel and per diem expenses and meeting time. The deliverable will include a list of action items identified during the meeting for each site and will be submitted approximately two weeks following the meeting.

A task completion date of May 30, 2025, is recommended. If you have any questions please contact us for clarification.