CN-370000-HW685-DC018B.pdf

PDF 3 MB Posted

Attached to
Master Agreement FL|HW685|184b9800bda47b032a54413957b4b38d
Contract number
HW685
Issued by
Florida

About this file

This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to WSP USA Inc. for environmental services at the Kimco of North Miami Inc. facility located at 19911 N.W. 2nd Avenue, Miami, Dade County, Florida. The task assignment was executed on November 21, 2023, under the underlying Contract Number HW685, with Patrick McGrane serving as the FDEP Project Manager and Matt Crews as the contractor's project manager. The project is designated as TA Number DC018B with a completion date of June 7, 2024.

The scope of work authorizes WSP to conduct annual groundwater monitoring, monitoring well installation, and PFAS (Per- and Polyfluoroalkyl Substances) screening activities in accordance with the October 30, 2023 Scope of Work, Cost Estimate, and Bid Documentation. The contract is structured as a Fixed Unit Rate agreement with a Total TA Value of $18,910.09. The work is organized into four subtasks: (1) Project Management ($1,343.33), (2) Monitoring Well Installation and Groundwater Monitoring ($12,328.66), (3) PFAS Related Costs and IDW Transportation & Disposal ($1,980.14), and (4) Reporting ($3,257.96). Deliverables include e-mail summaries with field documentation and certified laboratory reports due January 26, February 23, and March 29, 2024, with a final Annual Groundwater Monitoring and PFAS Screening Report due by May 24, 2024. The work involves installing one shallow monitoring well (MW010), collecting groundwater samples from six existing wells across three aquifer zones, analyzing samples for chlorinated volatile organic compounds and PFAS, and disposing of investigation-derived waste through approved non-hazardous waste facilities.

View the file

Other files

File Type Posted
CN-370000-HW685-BF01A.pdf PDF
CN-370000-HW685-BF01CCO1.pdf PDF
CN-370000-HW685-BF02A.pdf PDF
CN-370000-HW685-BF05A.pdf PDF
CN-370000-HW685-BF05ACO1.pdf PDF
CN-370000-HW685-BF1BCO1.pdf PDF
CN-370000-HW685-BIL02C.pdf PDF
CN-370000-HW685-BIL1ACO4.pdf PDF
CN-370000-HW685-BIL2CCO1.pdf PDF
CN-370000-HW685-BIL3ACO1.pdf PDF
CN-370000-HW685-CSS01.pdf PDF
CN-370000-HW685-CSS2ACO2.pdf PDF
CN-370000-HW685-DC001C.pdf PDF
CN-370000-HW685-DC001E.pdf PDF
CN-370000-HW685-DC002B.pdf PDF
CN-370000-HW685-DC002C.pdf PDF
CN-370000-HW685-DC002E.pdf PDF
CN-370000-HW685-DC003C.pdf PDF
CN-370000-HW685-DC004A.pdf PDF
CN-370000-HW685-DC007A.pdf PDF
CN-370000-HW685-DC007B.pdf PDF
CN-370000-HW685-DC008B.pdf PDF
CN-370000-HW685-DC008D.pdf PDF
CN-370000-HW685-DC009A.pdf PDF
CN-370000-HW685-DC009D.pdf PDF
CN-370000-HW685-DC009E.pdf PDF
CN-370000-HW685-DC010C.pdf PDF
CN-370000-HW685-DC012A.pdf PDF
CN-370000-HW685-DC012D.pdf PDF
CN-370000-HW685-DC014B.pdf PDF
CN-370000-HW685-DC016D.pdf PDF
CN-370000-HW685-DC017A.pdf PDF
CN-370000-HW685-DC017B.pdf PDF
CN-370000-HW685-DC019A.pdf PDF
CN-370000-HW685-DC019C.pdf PDF
CN-370000-HW685-DC01ACO1.pdf PDF
CN-370000-HW685-DC01ECO1.pdf PDF
CN-370000-HW685-DC021A.pdf PDF
CN-370000-HW685-DC021B.pdf PDF
CN-370000-HW685-DC021C.pdf PDF
CN-370000-HW685-DC021E.pdf PDF
CN-370000-HW685-DC022C.pdf PDF
CN-370000-HW685-DC023A.pdf PDF
CN-370000-HW685-DC023D.pdf PDF
CN-370000-HW685-DC024C.pdf PDF
CN-370000-HW685-DC025A.pdf PDF
CN-370000-HW685-DC027D.pdf PDF
CN-370000-HW685-DC028A.pdf PDF
CN-370000-HW685-DC028D.pdf PDF
CN-370000-HW685-DC029A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW685

DC018B Completion June 7, 2024

This Task Assignment authorizes WSP to conduct annual groundwater monitoring, monitoring well installation, and PFAS screening activities in accordance with the October 30, 2023 Scope of Work, Cost Estimate, and Bid Documentation.

Patrick McGrane 850-245-8899 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

WSP USA Inc.

WSP USA Inc.

Matt Crews 904-363-3430

ERIC_4487

19911 N.W. 2nd Avenue, Miami, Dade County

Kimco of North Miami Inc.

✔ $ 18,910.09

$ 18,910.09

Scope of Work

Matthew Crews

Environmental Engineer

11/21/2023

Crews, Matt (USMC700671) Digitally signed by Crews, Matt (USMC700671) Date: 2023.11.21 09:40:56 -05'00' Kelly Crain Digitally signed by Kelly Crain

Date: 2023.11.16 09:27:29 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 1 & 4: Project Management; Reporting 03/29/2024

Subtask 2: Monitoring Well Installation and Groundwater Monitoring 01/26/2024

Subtask 3: PFAS Related Costs and IDW Transportation & Disposal 02/23/2024

Subtasks 1 & 4: Submittal and FDEP approval of Annual Groundwater Monitoring and PFAS Screening Report; Project Management $ 4,601.29

Subtask 2: Submittal and FDEP approval of E-mail summary of groundwater reports with field documents; certified laboratory analytical report; MW construction logs $ 12,328.66

Subtask 3: Submittal and FDEP approval of E-mail summary of PFAS data figures;

field documentation; certified laboratory analytical report; signed IDW manifest $ 1,980.14

$ 18,910.09

HW685

DC018B

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: ERIC_4487

Kimco of North Miami INC., Dade County

FROM: Patrick McGrane, Project Manager

SUBJECT: Negotiation Summary

HW685 DC018B

DATE: Nov 13, 2023

This Task Assignment authorizes WSP to conduct annual groundwater monitoring activities, monitoring well installation, PFAS screening, and IDW transport and disposal in accordance with the October 30, 2023, Scope of Work, Cost Estimate, and Bid Documentation. The final cost of this Task Assignment is $18,910.09 with 98 labor hours.

Subtask 1: Project Management

An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Site Access, Utility Clearance, MW installation and Sampling, Chlorinated VOC and PFAS Analysis WSP will initiate a utility locate for underground utilities in the vicinity of the site and install one shallow monitoring well (MW010) adjacent to preexisting MW005. Following installation of MW010, WSP will collect groundwater samples for three shallow zone MWs (MW001, MW002, and MW010), two intermediate zone MWs (MW005 and MW007), and one deep zone MW (MW009). MW010 will not be sampled until 24 hours after installation. All wells will be purged prior to sampling. The depth-to-groundwater will be measured prior to this sampling from MW003 and MW008 (in addition to wells sampled) to determine groundwater elevation and flow direction. All samples taken will be completed in accordance with DEP’s SOP for Field Activities (DEP SOP-001/01 Jan. 2017) and in accordance with DEP’s SOP for Sampling with and Analysis of Perfluoroalkyl and Polyfluoroalkyl Substances (Aug. 2020).

Following sampling, groundwater samples selected for chlorinated VOCs testing will be delivered to Florida Department of Health and National Environmental Laboratory Accreditation Program. The groundwater samples selected for PFAS analysis will be shipped to the DEP Central Laboratory in Tallahassee, FL.

Subtask 3: PFAS Related Costs and IDW Transportation and Disposal Costs associated with PFAS screening and IDW disposal. PFAS related costs include completing bottle order requests with DEP Central Laboratory; waste characterization and waste profiling; packaging and shipping PFAS to DEP Central Laboratory; and IDW waste transportation and disposal (containerize IDW purge water, well development waste, and decontamination water). WSP estimates IDW transport and disposal will require two drums.

Subtask 4: Reporting An Annual Groundwater Monitoring Report will be provided that includes a description of the sampling procedure, evaluation of the analytical results; tabulated summary and comparison of current to historical data; a site map showing the groundwater analytical results; water level elevation information; laboratory analytical date; and conclusions and recommendations. The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment.

FDEP COST ESTI MATEContractor: WSP USA Inc.

Date: 10/30/2023

Task #: DC018B SubTask 1 Project Management SubTask 6

Site: Kimco of North Miami SubTask 2 MW Installation and GW Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 PFAS Related Costs and IDW T&D SubTask 8

Project Manager: Kelly Crain SubTask 4 Reporting SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$39.62 Project Manager (SS) 11 11.3 $0.00 Program Leader - X-14 0 0 0 0 0 0 0 0 0 0

$64.39 Senior Consultant - X-12 (MCC) 3 0 0 3 0 0 0 0 0 0 $0.00 Practice Leader - X-13 0 0 0 0 0 0 0 0 0 0

$53.28 Senior Sci/Eng - X-11 (RFM) 0 0 0 0 0 0 0 0 0 0 $48.00 Senior Project Sci/Eng - P-10 (BL) 4 0 0 4 0 0 0 0 0 0 $39.62 Project Sci/Eng - P-10 (SS) 25 3 6 16 0 0 0 0 0 0 $36.66 Staff Sci/Eng - P-9 (JS) 27 25 2 0 0 0 0 0 0 0 $39.00 Staff Sci/Eng - P-8 (LS) 26 24 2 0 0 0 0 0 0 0 $33.90 Staff Sci/Eng - P-8 (AS) 2 0 0 2 0 0 0 0 0 0

$0.00 Sci/Eng/Admin - P-7 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 98 11.3 52.0 10.0 25.0 0 0 0 0 0 0

Direct Labor $3,895.44 $448.15 $1,971.36 $389.04 $1,086.89 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 172.50% $6,719.64 $773.06 $3,400.60 $671.09 $1,874.89 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $10,615.08 $1,221.21 $5,371.96 $1,060.13 $2,961.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 1

FDEP COST ESTI MATEContractor: WSP USA Inc.

Date: 10/30/2023

Task #: DC018B SubTask 1 Project Management SubTask 6

Site: Kimco of North Miami SubTask 2 MW Installation and GW Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 PFAS Related Costs and IDW T&D SubTask 8

Project Manager: Kelly Crain SubTask 4 Reporting SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $816.00 $816.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,176.00 $1,176.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $2,920.00 $2,920.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $740.00 $0.00 $740.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $505.00 $505.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $4,165.00 $3,425.00 $740.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $416.50 $342.50 $74.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $4,581.50 $3,767.50 $814.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $329.00 $329.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $150.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $479.00 $479.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $80.00 $80.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $325.00 $325.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $392.00 $392.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $997.00 $997.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $17,848.58 $1,221.21 $11,791.46 $1,874.13 $2,961.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,061.51 $122.12 $537.20 $106.01 $296.18 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $18,910.09 $1,343.33 $12,328.66 $1,980.14 $3,257.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GOLDER Page 2

SITE : Kimco of North Miami SUBTASK 2: MW Installation and GW Monitoring

DATE: 10/30/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Sci/Eng (S. Sider) 3

Project Sci/Eng (J. Spengler) 25

Staff Sci/Eng (L. Swindle) 24

TOTAL LABOR 52

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 Per Day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Per Diem Project Sci/Eng (J. Spengler) $36.00 Per Day 3 $108.00 Per Diem Project Sci/Eng (L. Swindle) $36.00 Per Day 3 $108.00

Hotel Project Sci/Eng (J. Spengler) $150.00 Per Day 2 $300.00 Hotel Project Sci/Eng (L. Swindle) $150.00 Per Day 2 $300.00

TOTAL PER DIEM $816.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

GWP Monitoring Well Installation $2,920.00 LS 1 $2,920.00 Bloodhound Utility Locate $505.00 LS 1 $505.00

TOTAL $3,425.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Chlorinated VOCs - EPA Method 8260B

Total VOHs EPA Method 8260B $73.00 3 $219.00 Total VOCs EPA Method 8021 - IDW $110.00 1 $110.00

Sample Shipping Large $150.00 1 $150.00

TOTAL LAB $479.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Miscellaneous Expendables $40.00 Per Day 2 $80.00 Monitor Well Installation Kit $325.00 Per Day 1 $325.00 Shallow Groundwater Sampling Kit $290.00 Per Day 1 $290.00 Tubing, Poly HDPE $0.30 Per Day 280 $84.00 Tubing, Silicon 3/16 x 3/8 $3.00 Per Day 6 $18.00 Drum, 55-gallon $100.00 Per Day 2 $200.00

TOTAL EQUIPMENT $997.00

Verification of property ownership prior to groundwater sampling (1 hour). Prepare and submit email summary with field documentation and certified laboratory report with CVOC results (2 hours).

Conduct groundwater sampling event and oversee monitoring well installation. Round trip from Jacksonville to Miami (12 hours). Field event preparation (1 hour). Well installation oversight;

Instrument calibration; measure water levels; sample 7 wells, including three shallow zone wells (MW001, MW002, and MW010), three intermediate zone wells (MW005, MW007, and MW006R), and one deep zone well (MW009); and secure and sample the IDW drum(s) (12 hours).

Conduct groundwater sampling event and oversee monitoring well installation. Round trip from Jacksonville to Miami (12 hours). Well installation oversight; Instrument calibration; measure water levels; sample 7 wells, including three shallow zone wells (MW001, MW002, and MW010), three intermediate zone wells (MW005, MW007, and MW006R), and one deep zone well (MW009); and secure and sample the IDW drum(s) (12 hours).

LEVEL OF EFFORT/EXPENSE WORKSHEET

SUBTASK 3: PFAS Related Costs and IDW T&D

DATE: 10/30/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Sci/Eng (S. Sider) 6

Project Sci/Eng (J. Spengler) 2

Staff Sci/Eng (L. Swindle) 2

TOTAL LABOR 10

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin Profile Fee $350.00 LS 1 $350.00 Erwin T&D - Non-Haz PFOS/PFAS Water $195.00 per drum 2 $390.00

TOTAL $740.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Complete forms to arrange for PFAS sample bottle order delivery and shipment from DEP Central Laboratory (1 hour). Characterize IDW and prepare waste profile for transportation and disposal of IDW (3 hours). Prepare and submit email summary with field documentation and certified laboratory report with PFAS results (2 hours).

Package and deliver PFAS samples to shipping point for DEP Central Laboratory (2 hours).

Package and deliver PFAS samples to shipping point for DEP Central Laboratory (2 hours).

FINAL --7/24/96

LEVEL OF EFFORT/EXPENSE WORKSHEET

SUBTASK 4: Reporting

DATE: 10/30/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Consultant (M. Crews) 3

Senior Sci/Eng (S. Sider) 16

Senior Project Sci/Eng (B. Lucero) 4

Staff Sci/Eng (A. Strayer) 2

TOTAL LABOR 25

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Develop conclusions and recommendations and prepare final Annual Monitoring Report.

Data entry, prepare tables and figures, and draft Annual Monitoring Report

CADD Update Figures (two groundwater flow and three CVOC detections) format.

Reporting: Updating tables, document production, binding and shipping. Create pdf for

OCULUS

FINAL --7/24/96

WSP USA Inc.

9428 Baymeadows Road, Suite 400, Jacksonville, Florida 32256 USA

T: +1 904 363-3430 F: +1 904 363-3445 wsp.com

October 30, 2023 Proposal No. 202208346

Ms. Kelly Crain Florida Department of Environmental Protection Division of Waste Management Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

RE: COST PROPOSAL FOR ANNUAL GROUNDWATER MONITORING

AND PFAS SCREENING

KIMCO OF NORTH MIAMI INC.

19911 N.W. 2ND AVENUE

MIAMI, DADE COUNTY, FLORIDA

DEP FACILITY ID NUMBER: ERIC_4487

PROPOSED TASK ASSIGNMENT: DC018B

Dear Ms. Crain:

WSP USA Inc. (WSP) is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal for groundwater monitoring well installation, annual groundwater monitoring, and Per- and Polyfluoroalkyl Substances (PFAS) screening activities at the above-referenced site. This proposal includes a description of the proposed scope of services, level of effort sheets for each subtask, and a cost estimate form that summarizes the costs of the proposed services. The proposed scope of services is described below.

SUBTASK 1 – PROJECT MANAGEMENT

To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP and the field team. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submittal of project invoices in accordance with DEP Waste Site Cleanup Section requirements. The project manager will oversee the work so that it is conducted in a manner that is consistent with the requirements of the DEP-approved task assignment.

Ms. Kelly Crain Proposal No. 202208346

Florida Department of Environmental Protection October 30, 2023

SUBTASK 2 – MONITORING WELL INSTALLATION AND GROUNDWATER MONITORING

Monitoring Well Installation Following authorization to proceed, WSP will coordinate with the real property owner and tenant for access to complete the scope of work. WSP will obtain the applicable local, county, and state-required permits prior to implementing the proposed scope of work. The location of underground utilities will be identified and marked.

Sunshine State One Call, a utility location service provider, will be contacted at least three working days (72 hours) before any subsurface work begins. Given that work will be conducted on private property, Sunshine State One Call might not be able to provide details regarding specific utilities in the proposed well location area. Therefore, WSP will use a private utility location company to locate and map shallow subsurface anomalies present near the proposed well location.

WSP will oversee the installation of one shallow monitoring well (MW010) located adjacent to monitoring well MW005, as presented on Figure 2. The well will be installed by a Florida-licensed well driller. The well screens will consist of 10 feet of 0.5-inch diameter, Schedule 40 PVC well screen (0.010-inch slot size). The well riser will consist of 0.5-inch diameter, Schedule 40 PVC. The well risers will be connected to the screens with flush-threaded joints, using an appropriate length to reach the ground surface. The annular space between the borehole wall and the well screen will be filled with a 20/30 grade silica sand filter pack to a level above the top of the well screen (minimum 1 foot above). A minimum one-foot thick, fine (30/65) grade silica sand seal will be placed above the sand filter pack, and the remainder of the annular space will be filled with a Portland Cement Type II grout seal. For cost estimating purposes and based on existing shallow monitoring well construction information, as well as the historical depth to groundwater, WSP has assumed the shallow monitoring well will be installed to a total depth of 15 feet bgs (i.e., screened from 5 to 15 feet bgs).

The monitoring well will be finished with flush-mounted surface completion and an 8-inch diameter bolt-down steel cover. The risers will be capped with water-tight expandable locking plugs. A 2-foot by 2-foot concrete pad will be constructed around the well to secure the flush-mounted vault, which will be sloped away from the well to prevent surface water infiltration. To remove fine-grained particles in the filter pack and those adhered to the borehole walls, and to establish a good hydraulic connection with the aquifer, the monitoring wells will be developed until the purged water remains visibly clear and free of suspended particulate matter.

Groundwater Monitoring Following monitoring well installation activities, WSP will collect groundwater samples from three shallow zone monitoring wells (MW001, MW002, and MW010), two intermediate zone monitoring well (MW005 and MW007), and one deep zone monitoring well (MW009). WSP will not sample monitoring well MW010 until 24 hours after the completion of well development activities. The attached figures (Figures 3 through 5) from the October 2022 sampling event show the monitoring well locations and chlorinated VOC results for each zone. Prior to groundwater sampling, the depth-to-groundwater will be measured at two accessible monitoring well locations (MW003 and MW008) in addition to the wells sampled using an electronic water level indicator to determine groundwater elevations and flow direction. During the sampling event, the locks and well caps will be inspected for damage or degradation and repaired or replaced, as necessary.

Groundwater sampling activities will be completed in accordance with DEP Standard Operating Procedures (SOPs) for Field Activities (DEP SOP-001/01), dated January 2017 (effective April 16, 2018) and DEP SOPs for Sampling with and Analysis of Perfluoroalkyl and Polyfluoroalkyl Substances (PFAS), dated August 2020. Prior to collecting the groundwater sample, each well will be purged and field parameters including temperature, pH, specific conductance, dissolved oxygen, turbidity, and oxidation-reduction potential will be monitored. Purge volumes and field parameters will be recorded on field data sheets, and the field monitoring equipment will be calibrated in accordance with the manufacturer’s recommended procedures.

The groundwater samples to be analyzed for chlorinated VOCs will be delivered to a Florida Department of Health and National Environmental Laboratory Accreditation Program certified, fixed-base laboratory along with the completed chain-of-custody documentation. The selected groundwater samples to be analyzed for PFAS will be shipped to the DEP Central Laboratory in Tallahassee, Florida. Upon receipt of the laboratory analytical results, WSP will evaluate the constituent concentrations to determine if off-site notification is required.

The samples will be analyzed as follows:

Sample ID Chlorinated VOCs (EPA Method 8260B)

PFAS*

(EPA Method 8321 or Similar)

MW001 X

MW002 X

MW003 No Sample - Water Level Only

MW005 X X

MW007 X X

MW008 No Sample - Water Level Only

MW009 X

MW010 (New Well) X

Equipment Blank X

IDW Total VOCs X

*Selected wells approved by DEP via e-mail on March 22, 2023

Quality Assurance/Quality Control WSP will collect one equipment blank sample during the groundwater sampling event. The equipment blank will be collected by pumping (peristaltic pump) PFAS-free water through silicon and/or HDPE tubing and into laboratory-supplied containers. The equipment blank will be analyzed for PFAS using EPA Method 8321 (or similar), as shown in the above table.

Interim Deliverable Upon completion of Subtask 2, an e-mail deliverable will be submitted for the chlorinated VOC samples and include copies of the field data sheets, equipment calibration forms, field notes, laboratory analytical report, and laboratory chain-of-custody documentation.

SUBTASK 3 – PFAS RELATED COSTS AND IDW TRANSPORTATION & DISPOSAL

WSP will include costs associated with PFAS screening activities in this subtask. These activities include completing bottle order requests with the DEP Central Laboratory; waste characterization and waste profiling; packaging and shipping PFAS samples to the DEP Central Laboratory; and investigation-derived waste transportation and disposal.

IDW Transportation and Disposal WSP will containerize the IDW purge water, well development, and decontamination water in a 55-gallon drum(s).

WSP will collect a waste characterization sample from the drum for analysis of total VOCs using EPA Method 8260 and PFAS using EPA Method 8321 (or similar), as shown in the above table. The drum(s) will be temporarily staged onsite, pending waste characterization. For cost estimating purposes, WSP has assumed that the IDW can be transported and disposed of as non-hazardous waste at an approved facility. The IDW transportation and disposal subcontractor will provide WSP with a non-hazardous waste manifest upon delivery to the disposal facility. WSP estimates two drums of IDW purge water, well development water, and decontamination water will be generated during the field activities.

Interim Deliverable WSP will submit an e-mail deliverable within two working days upon receipt of the certified laboratory analytical report, if PFAS concentrations exceed the DEP Provisional Groundwater Cleanup Target Level (PGCTL) of 70 nanograms per liter for perfluoro-n-octanoic acid (PFOA), perfluorooctanesulfonic acid (PFOS), or the sum of PFOA and PFOS concentrations. The deliverable will consist of an e-mail summary and will include a figure with the sampling locations and PFOA/PFOS results, field documentation, and the certified laboratory analytical report.

If the PFAS concentrations do not exceed the DEP PGCTL, WSP will submit the interim deliverable, along with the non-hazardous waste manifest, by the due date specified in the Cost and Schedule section.

SUBTASK 4 – REPORTING

WSP will prepare an Annual Groundwater Monitoring Report that will include a description of the sampling procedures, evaluation of the analytical results; comparison of current to historical data; tabulated summary of the current and historical analytical data; a site map showing the groundwater analytical results; water level elevation information in tables and figures; laboratory analytical data; and conclusions and recommendations.

HEALTH AND SAFETY

WSP will update the existing site-specific Health and Safety Plan for the fieldwork. The work will be completed in accordance with WSP’s safety policies and procedures. At a minimum, WSP will wear safety glasses, high visibility safety vests, and steel-toed boots. A safety job briefing will be conducted prior to the start of work activities, and anytime the scope of work or site conditions change.

COST AND SCHEDULE

The estimated cost to complete the proposed scope of work is $18,910.09. WSP anticipates the monitoring well installation and groundwater monitoring event will take place in November or December of 2023. The level of effort sheets and cost estimate form are included in Attachment A. The monitoring well installation, utility location, and IDW disposal subcontractor quotes are included in Attachment B. The following table summarizes the proposed costs and deliverable schedule.

Task Proposed Cost Proposed Schedule/Deliverables

Subtask 1 – Project Management $ 1,343.33 March 29, 2024

Subtask 2 – Monitoring Well Installation and Groundwater Monitoring

$ 12,328.66 January 26, 2024 (E-mail summary with field documentation and certified laboratory analytical report)

Subtask 3 – PFAS Related Costs and IDW Transportation & Disposal

$ 1,980.14 February 23, 2024 (E-mail summary with PFAS data figure; field documentation; certified laboratory analytical report)

Subtask 4 – Reporting $ 3,257.96 March 29, 2024 (Annual Groundwater Monitoring and PFAS Screening Report)

Total/Completion Date $ 18,910.09 May 24, 2024

WSP appreciates the opportunity to provide services to the DEP. Should you require additional information or clarifications, please contact us at (904) 363-3430.

Sincerely, Stephen J.R. Sider, GISP, GIT Matthew C. Crews, PE Senior Geologist Vice President, Environmental Engineer

SJRS/MCC/as

Attachments: Figure 1 – Site Location Map Figure 2 – Proposed Monitoring Well Installation Map Figure 3 – VOC Analytical Summary of the Shallow Zone of the Surficial Aquifer (October 10, 2022) Figure 4 – VOC Analytical Summary of the Intermediate Zone of the Surficial Aquifer (October 10, 2022) Figure 5 – VOC Analytical Summary of the Deep Zone of the Surficial Aquifer (October 10, 2022)

Attachment A – Level of Effort Sheets and Cost Estimate Form Attachment B – Subcontractor Quotes

G:\Projects\DEP-Drycleaning\Projects\Miami\Kimco of North Miami\DC018B - 2023 Ann GW Mon & PFAS Screening\Proposal\DC018B - Kimco of North Miami Ann GW Mon & PFAS Screening Proposal.rev1.docx

9428 Baymeadows Road, Suite 400, Jacksonville, Florida 32256 USA

T: +1 904 363-3430 F: +1 904 363-3445

October 30, 2023 Proposal No. 202208346

Ms. Kelly Crain Florida Department of Environmental Protection Division of Waste Management Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

RE: COST PROPOSAL FOR ANNUAL GROUNDWATER MONITORING

AND PFAS SCREENING

KIMCO OF NORTH MIAMI INC.

19911 N.W. 2ND AVENUE

MIAMI, DADE COUNTY, FLORIDA

DEP FACILITY ID NUMBER: ERIC_4487

PROPOSED TASK ASSIGNMENT: DC018B

Dear Ms. Crain:

WSP USA Inc. (WSP) is pleased to provide the Florida Department of Environmental Protection (DEP) with this cost proposal for groundwater monitoring well installation, annual groundwater monitoring, and Per- and Polyfluoroalkyl Substances (PFAS) screening activities at the above-referenced site. This proposal includes a description of the proposed scope of services, level of effort sheets for each subtask, and a cost estimate form that summarizes the costs of the proposed services. The proposed scope of services is described below.

SUBTASK 1 – PROJECT MANAGEMENT

To facilitate project quality and satisfactory completion of the proposed scope of work, all aspects of this project will be overseen by an experienced project manager. The project manager will be responsible for the schedule, budget, invoicing, project activities, and communications with DEP and the field team. Project management will include coordination of field activities; resource allocation to confirm the work is conducted by qualified professionals in accordance with the project schedule; cost control and tracking of the budget status; and submittal of project invoices in accordance with DEP Waste Site Cleanup Section requirements. The project manager will oversee the work so that it is conducted in a manner that is consistent with the requirements of the DEP-approved task assignment.

Sonic Auger DPT Injection Well Abandonment

DATE: 10/6/2023

ESTIMATE #: 1023017

WSP

ID QTY Unit Rate TOTAL

1 1 each 1,200.00$ 1,200.00$

2 night 300.00$ -$

3 DPT Rig and Crew (DPT Sampling) 1 1/2 day 1,250.00$ 1,250.00$

4 Materials: Macrocore Sleeves (if Needed) each 3.00$ -$

5 Materials: 0.5" PVC Well Installation 15 each 6.00$ 90.00$

6 Materials: 3" Expendable Point 1 each 20.00$ 20.00$

7 2' x 2' Concrete Pad w/8" BD Completion 1 each 200.00$ 200.00$

8 Well Development (Up to 1/2 hour with pump) MW Well 1 each 75.00$ Included

9 Drums (Soil) As Needed 0 each 65.00$ -$

10 Drums (Development Water) Estimated 1 each 65.00$ 65.00$

11 Permits (Miami Dade County) 1 each 95.00$ 95.00$

Subtotal 2,920.00$

Todd Hodgson Todd Hodgson TOTAL 2,920.00$

Partner

Jacksonville, Florida Miami, Florida 9428 Baymeadows Road, Ste 400

(904) 363-3430 DPT Well Installation

PROJECT

Kimco of N Miami 19935 NW 2nd Ave

Stephen Sider

CUSTOMER

THANK YOU FOR YOUR BUSINESS!

DESCRIPTION

If you have any questions concerning this proposal contact Todd Hodgson at (407) 426-7885 at Todd@drillprollc.com.

Project Description:

(1) 0.5" x 15' PVC Well w/10' of .010 Screen, 2' x 2' Concrete Pad w/8" BD, No Sampling.

Drum for Soils Only.

"Actual quantities used and days onsite will be invoiced"

Completion: 1/2 day

Mobilization

Locations must be accessible with track mounted DPT Rig

Damage to utilities on private property are the responsibility of the client Utility Locates on Private Property are the responsibility of the client

Borehole Clearance to 5’ bgs beyond 20 minutes will require a change order for additional time and cost

Per Diem - Est. 2 Man Crew Est. (Hotel Cost + $50/per man)

2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586

DATE: 10/05/23

CONTRACTOR NAME: WSP

SITE NAME & LOCATION: Kimco - North Miami

PROJECT NO:

PROPOSED SCOPE OF WORK:

1) .5"x15' Well, DPT Samples, Development and 8" BD Manhole

Drums charged as needed

UNIT UNIT RATE QUANTITY EXT. PRICE

DIRECT PUSH DAILY RATE FULL DAY $3,500.00 1.0 $3,500.00

DIRECT PUSH HALF-DAY RATE HALF DAY $0.00 0.0 $0.00

AUGER ATTACHMENT, 2" WELL INSTALL PER FOOT $0.00 0.0 $0.00

PRE-PACKED WELL SCREEN 1"x5' pre-pack screen EACH $0.00 0.0 $0.00

SLOTTED PVC WELL SCREEN 2"x10' .010 EACH $0.00 0.0 $0.00

WELL RISER 2"x5' riser EACH $0.00 0.0 $0.00

WELL COMPLETION 8" BD Manhole/Pad PER WELL $110.00 1.0 $110.00

MOBILIZATION ROUNDTRIP $900.00 1.0 $900.00

PER DIEM PER CREW $340.00 0.0 $0.00

55-GAL DRUM* EACH $67.90 0.0 $0.00

CUT/PATCH* EACH $12.00 0.0 $0.00

GROUT* Abandonment EACH $0.00 0.0 $0.00

SAMPLE LINERS* EACH $6.47 2.0 $12.94

SAMPLE POINTS* 3.25" Exp. Points EACH $0.00 0.0 $0.00

TUBING* (DEVELOPMENT) EACH $0.48 20.0 $9.60

PERMITS EACH $125.00 1.0 $125.00

OTHER .5"x15' Well Material EACH $299.00 1.0 $299.00

OTHER DECON PIT EACH $350.00 0.0 $0.00

OTHER Sand for Backfill EACH $9.98 0.0 $0.00

TOTAL ALL WELLS $4,956.54

DAYS TO COMPLETE SCOPE OF WORK: 1 Day

INVOICE SETTLEMENT IS NET 60 DAYS

100 KID ELLIS ROAD, MULBERRY, FL 33860

(863) 425-9600 ● FAX: (863) 425-9620 ● TOLL FREE: 800-532-5008

DIRECT PUSH TECHNOLOGY QUOTE FORM

DIRECT PUSH TECHNOLOGY

Equipment Type: GEOPROBE 7822 DT

MISCELLANEOUS

Sider, Stephen

From: Austin Bonacum <austin@pdsflorida.com> Sent: Thursday, October 5, 2023 8:50 AM To: Sider, Stephen Subject: RE: Drilling Quote Request - Kimco of North Miami

Hi Stephen, Thank you for the opportunity, but we’re going to decline to bid on this project. The size of scope is isn’t enough work for us to travel the distance. Please keep us in mind for future projects. Thank you!

Best Regards, Austin Bonacum Project Estimator Preferred Drilling Solutions, Inc.

8820 66th Street North Pinellas Park, FL 33782 Ph: 727‐561‐7477 Cell: 210‐819‐8474 austin@pdsflorida.com www.pdsflorida.com

From: Sider, Stephen <stephen.sider@wsp.com> Sent: Thursday, October 5, 2023 8:45 AM To: Austin Bonacum <austin@pdsflorida.com> Subject: RE: Drilling Quote Request ‐ Kimco of North Miami

AusƟn, Please quote this as 10‐Ō of regular 0.010” sloƩed screen (1/2 inch diameter), not prepack. Thanks.

Stephen J.R. Sider, GIT, GISP Senior Consultant, Geologist

T+ 1 904-363-3430 D+ 1 904-207-6019 M+ 1 904-570-6476

From: Sider, Stephen Sent: Wednesday, October 4, 2023 2:04 PM To: 'Austin Bonacum' <austin@pdsflorida.com> Cc: Crews, Matt <matt.crews@wsp.com> Subject: Drilling Quote Request ‐ Kimco of North Miami

AusƟn, Can you please provide a quote for installaƟon of one shallow monitoring well at the Kimco of North Miami site, located at 19935 NW 2nd Ave, Miami, FL 33169? The well will be installed adjacent to MW005, located in front of the Walgreens drive thru awning (not under).

Shallow monitoring well:

‐ 15 Ō bgs total depth ‐ 5 Ō of 0.5“ diameter PVC casing (0 ‐ 5 Ō bgs) ‐ 10 Ō prepack 0.010” sloƩed screen (5 ‐ 15 Ō bgs) ‐ Manhole and 2’x2’ concrete pad ‐ Develop well and drum development water

Thank you, WSP Global Inc.

9428 Baymeadows Road, Suite 400 Jacksonville, Florida, 32223

NOTICE: This communication and any attachments ("this message") may contain information which is privileged, confidential, proprietary or otherwise subject to restricted disclosure under applicable law. This message is for the sole use of the intended recipient(s). Any unauthorized use, disclosure, viewing, copying, alteration, dissemination or distribution of, or reliance on, this message is strictly prohibited. If you have received this message in error, or you are not an authorized or intended recipient, please notify the sender immediately by replying to this message, delete this message and all copies from your e-mail system and destroy any printed copies.

-LAEmHhHzdJzBlTWfa4Hgs7pbKl

90294Estimate Number

1/7/2024Expiration Date

10/9/2023Created Date

ESTIMATE

Blood Hound 6500 Technology Center Dr.

Suite 200 Indianapolis, IN 46278

Email: BHI@bhug.com bhug.com Website:

Phone #: 888-858-9830 888-858-9829 Fax #:

Customer has requested an estimate for the following scope of work:

Client has requested an estimate to horizontally locate detectable underground utilities within a 10' radius of one (1) proposed monitoring well in areas as shown on the provided exhibit and as directed on site.

A print or image was provided to review to assist with the estimate. However, pre-marking or a meet on site will be required to confirm the locate area and assist with access.

Client will only be invoiced for time needed to complete the stated SOW with a two-hour minimum.

Customer is advised if less time onsite is required than estimated, invoicing will be reduced to no less than the minimum fee. Any additional time required on site to complete the task beyond the estimated / minimum time will be invoiced in 15-minute increments of the provided hourly rates, upon customer approval.

EM and Real-Time GPR Locating equipment will both be utilized to locate and mark any detectable underground utilities and / or anomalies. A not to scale digital field sketch and photos will be provided of our discoveries for surveying and documentation purposes.

Customer has requested approximate depths to be noted on site sketch. Please note that all depths are approximate and can only be verified using vacuum excavation.

Customer is advised that Blood Hound utilizes water-based paint and flags to identify any discoveries onsite. If this is an issue, Blood Hound must be made aware of this when scheduling.

The performance of BHUG’s services is limited to full and unobstructed access to include but not limited to: mechanical rooms, manholes, hand holes, vaults, meter rooms, telecom rooms, fixtures (plumbing, electrical, communication), dispensers, fenced compounds, tanks and structures. Full cooperation from the on-site personnel is necessary to perform a complete scan. Should access not be provided or it is delayed, this could impact time to safely complete and accuracy of work.

Results are dependent upon field conditions at the time of locating services. It may be necessary to have parked vehicles or machinery moved to allow for a full scan and to access structures.

Quoted rates are exclusive to this estimate only. Rates quoted by Call Center Representatives are in effect unless otherwise stipulated within a formal estimate.

BHUG SOW

$505.00Grand Total stephen.sider@wsp.comEmail

904-610-8761Phone

Stephen SiderName

19935 NW 2nd Ave., Miami, FL, 33169Job Site Location

9428 Baymeadows Road Jacksonville, FL 32258

US

Billing Address

904-610-8761Billing Phone

WSP USA Inc.Customer

Product Invoice Description Quantity Sales Price Total Price

Advantage Locate (hourly) EM / GPR Locating (hourly rate) 2.00 $220.00 $440.00

Trip Charge Trip Charge 1.00 $65.00 $65.00

Scope of Work

90294Estimate Number

1/7/2024Expiration Date

10/9/2023Created Date

ESTIMATE

Blood Hound 6500 Technology Center Dr.

Suite 200 Indianapolis, IN 46278

Email: BHI@bhug.com bhug.com Website:

Phone #: 888-858-9830 888-858-9829 Fax #:

By signing this Estimate the client acknowledges that they accept the scope of work listed on the estimate, as well as the service rates provided and are providing Blood Hound with a Notice To Proceed (NTP) for the listed Project. If the scope of work should change while the work is in progress, any changes will be documented on the technician’s field notes and signed off on by the client. Signing this estimate also acknowledges that the client agrees to the terms and conditions as they relate to payment for services rendered.

Signature: ______________________________________________________________________________________

Printed Name: ___________________________________________________________________________________

Date Signed: ____________________________________________________________________________________

Payment is due at the time of service, unless you already have an account with us. If you do have an account with us, payment terms are Net 30 days, unless otherwise stated in a pre-approved contract. To learn more, please call the office at 888-858-9830.

PRICE MAY VARY BASED ON ACTUAL TIME ON SITE. The above pricing is based only on the information supplied by the customer.

If a site walk through has not been conducted, this may affect the price.

If this is a prevailing wage job, please contact our office for a revised quote as this pricing does not reflect prevailing wage rates. If at some later date a project is determined to be a prevailing wage job, then any extra expense incurred by Blood Hound will be billed to the client.

The project estimate outlined in this specific proposal is valid for 90 days from the date of the proposal. Blood Hound reserves the right to review and adjust this estimate if client does not approve of the proposal within 90 days.

Please send all POs / Contracts to .BHUGContracts@bhug.com

We look forward to working with you.

Blood Hound will use electromagnetic (EM) and ground-penetrating-radar (GPR) equipment to locate private underground utilities at site indicated by client. All findings will be marked according to APWA standard. Customer is responsible for calling 811 for locates of any public utilities. If the scope of work should change or is different than that listed on estimate, please call our office for a revised estimate.

Unless expressly noted, Vacuum Excavation estimates do not include any of the following services: Permitting, Traffic Control, Restoration, Special Restoration, Special Backfill or Waste Disposal. If you need any of those services please call our office for a revised estimate.

Blood Hound is not responsible for the condition of the pipes or structures before or after jetting/clearing service is performed. Unsatisfactory conditions could be present within the structure and any services may bring those deficiencies to light.

In the event of inclement weather, if the client still requests for crew to arrive on site, then the client will be responsible for minimum charges even if no work is performed.

Corporate Location:

Terms, Conditions, and Limitations of Service

6500 Technology Center Drive, Suite 200 Office # 888-858-9830

Indianapolis, IN 46278 Fax # 888-858-9829 http://www.BHUG.com

Blood Hound strives to provide quality and accurate locating services to its customers and uses several different methods and forms of equipment to locate private facilities but, due to the nature of the work, perfection is neither possible nor guaranteed. By retaining Blood Hound’s services, the Customer acknowledges, understands, and agrees to be bound by the terms, conditions, and limitations in this document. These Terms, Conditions, and Limitations are a condition of Blood Hound’s willingness to perform work for Customer.

Factors Impacting Reliability of Locating Services

Factors beyond ’s control can impact the effectiveness of Blood Hound’s efforts, including but not limited to:

Target Utility Composition – Electromagnetic (EM) locating is effective only if the target utility is composed of continuous conductive material.

Plastic, concrete, clay, or other non-conductive materials cannot be located using EM techniques. In addition, some metals (for example, cast iron) are not highly conductive and some pipes are gasketed resulting in non-continuous conductive material, which makes locating using EM techniques difficult and potentially unreliable. Similarly for Ground Penetrating Radar (GPR), electrostatic reflectivity of a target will impact the effective identification. Lightweight target material, such as PVC, are generally more transparent to radio waves and will reflect a substantially smaller percentage of the radiated signal making effective interpretation more difficult. Some materials are completely transparent to radio waves and can only be identified if a conductive material (i.e. water) is contained within the target facility.

Shielding of Target Utility– Unshielded lines directly buried in the soil (often water, sewer, and gas facilities) can be problematic to locate, especially for significant distance due to the continuous loss of transmitted signal directly to the ground. The greater the distance between the transmitter and the location point on an unshielded line, the more degraded the signal will be.

Conductive Pathway to Ground – EM locating is accomplished by creating a complete circuit; the transmitted signal must be able to return to ground. An open circuit is generally much more difficult to locate since the circuit is not complete, and the emitted signal cannot return to ground resulting in an unreliable and inaccurate locate.

Depth – For both EM and GPR locating, deeper facilities are inherently more difficult to locate due to the distance through the soil to the receiver at the surface. Similarly, shielding between the target utility and the receiver can affect the signal reception and create a loss of signal.

Subsurface Material / Soil Composition / Moisture Content– Soil composition and subsurface material is the most important factor impacting the effectiveness of GPR. The more conductive the subsurface material, the less effective the GPR survey will be. GPR works best in sandy soils, and is least effective in heavy clay soils or where the subsurface material contains a large volume of highly conductive backfilled debris or material (i.e.

metal scraps or slag sand). As a general rule, the smaller the particulate matter that the subsurface material is composed of, the greater the inhibiting effect on the GPR signal. Water, when combined with dissolved ions (salt) has an inhibiting effect on GPR signals, and signals can often not effectively penetrate saturated soil material, when the soil is slightly conductive. The addition of more water increases the conductivity of the soil and more significantly inhibits effective signal penetration.

Target Size – The smaller the target facility, the lower the probability of successful identification of the target during a GPR survey. The smaller the target, the less of a signal that will be reflected, decreasing the probability of a positive identification of the subsurface target. As a general (but not absolute) rule of thumb, for every 1 foot of depth you must have 1 inch in diameter in order to be observable. For example, a 3” diameter pipe must be less than 3 feet below grade in order to be observable during a GPR survey.

Surface Materials and Obstructions – The presence of surface metal, including vehicles, fences, and debris, can swamp other readings and prevent the identification of subsurface targets. In addition, the presence of rebar reinforcement within concrete can have a similar effect and prevent identification of other structures.

Customer Responsibilities

REGARDLESS OF THE SCOPE OF BLOOD HOUND’S WORK, CUSTOMER MUST COMPLY WITH AND FOLLOW THE APPLICABLE

STATE’S ONE CALL LAW BEFORE BEGINNING EXCAVATION. HIRING BLOOD HOUND DOES NOT REPLACE CUSTOMER’S

LEGAL OBLIGATION TO COMPLY WITH STATE LAW.

Customer represents and warrants that it is the owner of the facilities that Customer is hiring Blood Hound to locate.

Customer must provide Blood Hound with all information in its possession, custody, and control regarding the target facilities. This includes, but is not limited, all facility maps and prints (regardless of whether customer can guarantee the accuracy of such documents) and any anecdotal information regarding facility locations and paths. Providing all available information increases the likelihood of success of Blood Hound’s locating efforts, and failing to disclose available information increases the likelihood that facilities will either be missed or mis-located.

Customer must identify and provide Blood Hound access to any and all available facility access points, including but not limited to manholes, hand holes, transformers, cleanouts, tracer wires, service entrances, electric switchgears, electric sectionalizing cabinets, electric meters, test valves, and test stations. Failing to identify known access point and/or failing to provide Blood Hound with access to those access points increases the likelihood that facilities with either be missed or mis-located.

Customer understands that facility markings are not always precise, and Customer and any excavator utilized by Customer will expose all marked facilities prior to excavation, and will use soft excavation techniques anywhere within twenty-four (24) inches of a facility path marked by Blood

Hound.

Once markings are placed, Customer and any excavator utilized by Customer are responsible for ensuring that all marks are maintained and not destroyed or altered. If marks are destroyed or altered, Customer should contact Blood Hound for re-markings at an additional cost to Customer.

If Customer or any excavator utilized by Customer believe any facility has been missed or mis-marked, Customer will immediately notify Blood

Hound and cease all excavation activity until Blood Hound responds to the site.

Customers will pay invoices within thirty (30) days of receipt, or such…