CN-370000-HW684-DC031B.pdf
PDF 2 MB Posted
- Contract number
- HW684
- Issued by
- Florida
About this file
This Task Assignment (TA) is a contractual document entered into between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc., a contractor selected under Contract Number HW684. The task assignment, identified as DC031B, is effective through March 4, 2024, and designates Nicole Knutson as the FDEP Project Manager and Brian Moore as the contractor's Project Manager. The project site is located at 1034 US Highway 19, Holiday, Pasco County, Florida, specifically at the Holiday Square Shopping Center.
Under this task assignment, GHD Services, Inc. will complete groundwater monitoring activities at the Holiday Square Shopping Center site as detailed in a September 20, 2023 proposal. The scope of work includes two subtasks: Subtask 1 encompasses project management of groundwater monitoring activities, and Subtask 2 comprises the groundwater monitoring work itself, including water level measurements from all 23 monitoring wells and groundwater sampling from nine designated wells (MW011, MW016, MW021, MW023, MW024, MW027, MW028, MW029, and MW030) with analytical testing for volatile organic hydrocarbons. The deliverable is a Groundwater Monitoring Report with a due date of January 3, 2024. The total task value is $6,853.68 on a fixed unit rate basis, with payment structured to occur upon delivery of the groundwater monitoring report and completion of project management subtasks. The cost estimate includes direct labor ($4,596.62), travel ($120.00), subcontractor costs for IDW disposal through Erwin Remediation ($137.50), laboratory analytical services ($733.50), and field equipment and expenses ($806.40), with a completion fee of $459.66.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC031B Completion March 4, 2024
GHD will complete groundwater monitoring activities at the Holiday Square Shopping Center site, as detailed in the September 20, 2023 proposal.
Nicole Knutson 850-245-8763 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore 813 257 0658
ERIC_5248
1034 US Highway 19, Holiday, Pasco County
Holiday Square Shopping Center
✔ $ 6,853.68
$ 6,853.68
Scope of Work
Brian Moore Digitally signed by Brian Moore Date: 2023.09.29 09:50:33 -04'00' Kelly Crain Digitally signed by Kelly Crain
Date: 2023.09.28 16:23:43 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report & PM 01/03/2024
Groundwater Monitoring Report & PM - Subtasks 1 & 2 $ 6,853.68
$ 6,853.68
HW684
DC031B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: ERIC_5248
Holiday Square Shopping Center
FROM: Nicole Knutson, Project Manager
SUBJECT: Negotiation Summary
HW684 DC031B
DATE: September 26, 2023
GHD will complete groundwater monitoring activities at the Holiday Square Shopping Center site, as detailed in the September 20, 2023 proposal. Erwin Remediation will be tasked with IDW transportation and disposal.
Total task amount is $6,853.68. GHD’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is January 3, 2024.
Task completion date is March 4, 2024.
FDEP COST ESTIMATEContractor:
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 SubTask 7
Activity/Phase: SubTask 3 SubTask 8
Project Manager: SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$49.53 Project Manager JM 3.99 3.99 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$56.19 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$45.07 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.28 Project Engineer/Scientis CH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.53 Project Manager/ Enginee JM 14.50 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $31.78 Staff Engineer/Scientist JW 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.21 Senior Technician SA 12.50 12.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $26.63 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.55 Senior Technician DC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.21 Junior Technician WO 11.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.00 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 5.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $21.63 Administrative Assistant JJ 4.50 4.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 52.49 3.99 48.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,717.72 $197.61 $1,520.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $2,229.60 $256.50 $1,973.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $649.30 $74.70 $574.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,596.62 $528.81 $4,067.81 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
FDEP COST ESTIMATEContractor:
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 SubTask 7
Activity/Phase: SubTask 3 SubTask 8
Project Manager: SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $125.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $125.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $12.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $137.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $657.00 $657.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $76.50 $76.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $733.50 $733.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $666.40 $666.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $806.40 $806.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,394.02 $528.81 $5,865.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $459.66 $52.88 $406.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $6,853.68 $581.69 $6,271.99 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $6,853.68 Auto-Calculated
Final Total Cost: $6,853.68 Auto-Calculated
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Holiday Square Shopping Center SUBTASK 2: Groundwater Monitoring
DATE: 9/26/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Professional Engineer JH Conclusions/Recommendations 1
Project Manager JM Site Access 1 Project Manager JM Field Work Preparation 1 Project Manager JM Update HASP 1 Project Manager JM Profile IDW 1 Project Manager JM Project Background (GWMR) 1 Project Manager JM Groundwater Sampling Methods (GWMR) 1 Project Manager JM Groundwater flow evaluation (shallow, intermediate, deep) - GWMR 2 Project Manager JM Water Quality Parameter Summary (GWMR) 2 Project Manager JM Groundwater Analtycial Results (GWMR) 2 Project Manager JM Laboratory data validation (GWMR) 1.5 Project Manager JM Conclusions/Recommendations 1
14.5
Senior Technician SA Mob/demob 2 Senior Technician SA Water Levels (all wells - 23 total) 3 Senior Technician SA Groundwater Sampling (5 wells) 7.5
12.5
Junior Technician WO Mob/demob 2 Junior Technician WO Waterl Levels (all wells - 23 total) 3 Junior Technician WO Groundwater Sampling (4 wells) 6
Drafting Technician PM Prepare GW Flow maps (shallow, intermediate, deep) 3 Drafting Technician PM Prepare VOC plume figures with updated concentration data 2
Staff Assistant JJ Data Entry (23 wls, and 9 monitor wells) 1.5 Staff Assistant JJ Update tables (wl, water quality, analytical) 1 Staff Assistant JJ Document Preparation/Publishing 2
4.5
TOTAL LABOR 48.5
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Disposal $125.00 drum 1 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs EPA 8260 $73.00 9 $657.00 Sample Shipping Large Cooler (2 day) $70.00 1 $70.00
Ice $6.50 1 $6.50
TOTAL LAB $733.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 1 $40.00
Groundwater Sampling Kit $290.00 day 2 $580.00 Poly Tubing (HDPE) $0.30 ft 198 $59.40 Silicon Tubing $3.00 ft 9 $27.00
Drum $100.00 drum 1 $100.00
TOTAL EQUIPMENT $806.40
FINAL --7/24/96
COST PROPOSAL FOR TASK DC031B
<Holiday Square Shopping Center/FDEP #51-9700641>
< Groundwater Monitoring>
1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >
GHD Services Inc. (GHD) submitted a Site Assessment Report and Interim Source Removal Plan (SAR/ISRP) for the Holiday Square Shopping Center site located in Holiday, Pinellas County, in July 2017. The SAR/ISRP detailed the results of the assessment and detailed a plan to remove contaminated soil near a sewer cleanout. The ISRP activities were implemented in January 2018 and an Interim Source Removal Report (ISRR) was submitted in March 2018.
Additional Assessment was conducted late in 2018 and a SSAR was submitted in early 2019.
GHD’s latest groundwater monitoring report was submitted in January 2023, which recommended additional groundwater monitoring. The FDEP provided comments on the monitoring report in correspondence dated April 18, 2023. Task DC031B proposes annual groundwater sampling.
Subtask 1: Project Management Subtask 1 includes all tasks associated with project management of the groundwater monitoring activities at the Holiday Square Shopping Center site.
Subtask 2: Groundwater Monitoring In accordance with GHD recommendations, groundwater sampling is proposed at monitoring wells MW011, MW016, MW021, MW023, MW024, MW027, MW028, MW029, and MW030 will be sampled in accordance with FDEP SOPs. Prior to sampling, a complete round of water levels will be gathered from all site monitor wells. Groundwater sampling will be conducted in accordance with FDEP SOPs. The groundwater samples will be submitted to a fixed laboratory for VOH analysis.
Upon receipt of analytical data, a Groundwater Monitoring Report (GMR) will be prepared.
The GMR will include a summary of field methodology, field screening data, and laboratory analytical results. The GMR will also include conclusions and recommendations.
Deliverables:
Deliverable Deliverable Due Date
Groundwater Monitoring Report 1/3/24
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway, Suite F Tampa, FL 33610
June 13, 2023
Re: Non-Hazardous Drum Disposal – State of Florida
Mr. Moore:
The price for the transportation and disposal (T&D) of drums of non-hazardous soil and water located in the State of Florida is listed below.
Non-Hazardous Drums:
Description Rate Unit
False Mobilization (No drum found) $ 85.00 Per Stop
T&D - Non-Haz Soil $ 110.00 Per Drum
T&D - Non-Haz Water $ 125.00 Per Drum
The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida Keys. Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
The lab data we require for the disposal of drums of petroleum impacted soils are totals for BTEX and the 4 RCRA metals (arsenic, cadmium, chromium, and lead), with analyses no older than 1 year from the estimated disposal date.
We do not require analyticals for the disposal of Petroleum Contact Water (PCW) as long as it has only been impacted with petroleum - not pesticides, herbicides or dry-cleaning solvents etc.
Please ensure that all drum lids are properly secured and that drums are on a level surface like the surrounding area (i.e., not on a pallet, etc.). A single False Mobilization fee will apply if our driver is not able to locate a drum on site or if we are unable to access the property due to a locked gate, etc.
This quote is valid for 90 days.
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
Respectfully, Robert Donado Erwin Remediation, Inc.
Email: Robert@erwinremediation.com Office: (850) 466-2358
6/28/22, 10:23 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 1/2
Quote Number: 19644
QUOTE
QUOTED TO: Brian Moore
QUOTE DATE: 1/1/2022
COMPANY NAME: GHD - 2022 QUOTED BY: Craig Burns
PHONE NUMBER:
Ext.
FAX NUMBER:
PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS
CUSTOMER PO:
CONTACT EMAIL:
SITE ADDRESS: TBD
CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING
COST ESTIMATE FOR
THE SITE/ PROJECT LISTED ABOVE.
DESCRIPTION PRICE QTY. UNIT TOTAL
NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00
NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00
TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$30.00 DRUM $0.00
TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$40.00 DRUM $0.00
TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site
$50.00 DRUM $0.00
Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax
$0.00 . $0.00
HAZ Drums to be quoted case-by-case $0.00 . $0.00
OPTIONAL LINE ITEMS
***10% FSC applied to the total cost of the invoice*** $0.00 . $0.00
TOTAL REQUIRED ITEMS $0.00
TOTAL OPTIONAL ITEMS $0.00
GRAND TOTAL $0.00
NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.
**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns
863.327.6289 - cburns@clarkenv.com
This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.
quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 2/2
Name (print) Title
Signature Date
CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854
WWW.ClarkEnvironmental.com
From: Craig Burns To: Brian Moore Subject: GHD_IDW Drum Rates FL Date: Tuesday, June 28, 2022 10:26:46 AM Attachments: image001.png image002.png image003.png image004.png image005.png GHD Drum Rates FL 2022.pdf
Here you go Brian. I do this for a lot of engineering/consulting firms.
Be aware of the low stop less than 6 drums at $50/flat Be aware of the 10% to the total cost for FSC (implemented April 15).
Pass around the GHD Florida offices
From: Brian Moore <Brian.Moore@ghd.com> Sent: Tuesday, June 28, 2022 10:05 AM To: Craig Burns <cburns@clarkenvironmental.com> Subject: IDW Drums
Craig, Is it possible to provide a generic quote for IDW water disposal.
Assumption is non-haz with necessary analytical Maybe provide a range of locations
South florida or central florida, or both?
Thanks in advance
We have many sites that we generate 1 gw drum of IDW and would like to streamline the vendor coordination
BRIAN MOORE PE
GHD
Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com
The Power of Commitment
Connect
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please mailto:cburns@clarkenvironmental.com mailto:Brian.Moore@ghd.com https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttp-253A-252F-252Fwww.ghd.com-252F-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093857306-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DorO8Q-252BVqTyo6Ej-252F8ZwSbVyQzLpZtJywYELQonaQNZfo-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DsMxOUn-szAtJTATQBUgjjDdI6e6b1jo5alN-ez9vKSM%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=K3MyGMhP6XEk1ApT%2FRIPjGR%2BUFJFG9ahCVCi8Z9R1n0%3D&reserved=0 mailto:brian.moore@ghd.com https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.linkedin.com-252Fcompany-252Fghd-252F-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093857306-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3D5HB99sCNyHUdh3ySqo-252BMbX9lHf94JW-252BuI1gRPH6qLGY-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DBQdX3FW3jjZZNHH7wbXXUS30LUnS3GtU1HJ8G56Snwo%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=%2BQlcPM%2FGtFT%2FrIbbuGi0PnSgurtBD8yqWgV1hvkvk00%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.facebook.com-252FGHDGroup-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093867263-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DKXDgOYLYSf-252BwLLtpvQNMpyPzR3DV5-252FDBogAW3HWif9Y-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DdHZdva6F1f6cSXNf7WLXU9x5VBxbTV01G78hKDk-cSA%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=142JKLTMfwfz%2FAO%2FXHrz%2FUodXSRzYWWBygfbg7vBIWs%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Ftwitter.com-252FGHDspeaks-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093877221-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3Duwh4lLmvdNCQkyPoUgiL7r2l9-252BmFgEv2JbZPLM3ptM0-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3D6FLD5pJDe4zG94aUPcPkIB9mx5JTMUxrAOX-fjV9l3o%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=O7BUsLKToxyyPXzZcLcBA1z3Q7%2FKvVsiCNGMGHOzln0%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.youtube.com-252Fchannel-252FUCwUGfe6zgaddIXqA7entIwQ-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093877221-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DVTPo9BdB-252FyUkff7ZLoE6J99Jt9f-252Fvtuta-252Fsm1KEOuNc-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3D9S3nI6ai6gtzPu1y34Kb_OuqwixCpq0TgIkmYlOz0gk%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=YX45%2BiFGXo7axCd4VDmEIFdcmHajQE6n8KvktA7llOs%3D&reserved=0 quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 1/2
Quote Number: 19644
QUOTE
QUOTED TO: Brian Moore
QUOTE DATE: 1/1/2022
COMPANY NAME: GHD - 2022 QUOTED BY: Craig Burns
PHONE NUMBER:
Ext.
FAX NUMBER:
PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS
CUSTOMER PO:
CONTACT EMAIL:
SITE ADDRESS: TBD
CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING
COST ESTIMATE FOR
THE SITE/ PROJECT LISTED ABOVE.
DESCRIPTION PRICE QTY. UNIT TOTAL
NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00
NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00
TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$30.00 DRUM $0.00
TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$40.00 DRUM $0.00
TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site
$50.00 DRUM $0.00
Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax
$0.00 . $0.00
HAZ Drums to be quoted case-by-case $0.00 . $0.00
OPTIONAL LINE ITEMS
***10% FSC applied to the total cost of the invoice*** $0.00 . $0.00
TOTAL REQUIRED ITEMS $0.00
TOTAL OPTIONAL ITEMS $0.00
GRAND TOTAL $0.00
NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.
**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns
863.327.6289 - cburns@clarkenv.com
This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.
quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 2/2
Name (print) Title
Signature Date
CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854
WWW.ClarkEnvironmental.com delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
Whatever Waste, LLC 3834 Mandarin Woods Dr. No.
Jacksonville, Florida 32223 United States 904.881.1957
Brian Moore PE
GHD
5904 Hampton Road Parkway Suite F Tampa, FL 33610
Estimate Number 062922.1
Notes Dry Cleaner Site Locations: Central and South Florida Regions excluding Florida Keys Required analytical data for non-haz disposal acceptance would be VOCs and includes waste profiling assistance if the IDW-GW drums don't fall under a blanket waste profile DOT shippable drums must be on a hard surface at each accessible location
Terms Non-hazardous IDW drum pickup, transport and disposal pricing is based on per service event No-load drum fee if unable to pickup drums on any site in Central FL is $150; in South FL is $200 Pricing is valid or subject to change on a monthly basis in part due to escalating fuel prices Payment required within 45 days after email receipt of invoice
Indemnification: Each party agrees to indemnify, defend and hold harmless each other for and from any loss
Estimate Date 06/29/2022
Description Rate Qty Line Total
IDW-GW Drum Transport & Disposal - Central FL Sites
(1) Regional Stop Fee $600 - then $150 per 55-gal drum < 10 drums
$150.00 1 $150.00
IDW-GW Drum Transport & Disposal - Central FL Sites
(1) Regional Stop Fee $300 - then $150 per 55-gal drum > 10 drums
$150.00 1 $150.00
IDW-GW Drum Transport & Disposal - South FL Sites
(1) Regional Stop Fee $850 - then $200 per 55-gal drum < 10 drums
$200.00 1 $200.00
IDW-GW Drum Transport & Disposal - South FL Sites
(1) Regional Stop Fee $425 - then $200 per 55-gal drum > 10 drums
$200.00 1 $200.00
Subtotal
Tax
700.00
0.00
Estimate Total (USD) $700.00 or liability arising out of the party's breach of this agreement, scope of work, except for gross negligence, willful misconduct or bad faith.
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_v2.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v1.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Subtask 5 |
| Subtask 6 |
| 2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev1_12-12-22.pdf |
| Table 1 for SAWP |
| Monitoring Well Locations |
| Utility Locate Bids_Compiled.pdf |
| Geosyntec Utility-272_Geotek_1500 |
| Geoview Utility Quote_2000_COT FTF SIS |
| Tallahassee Fire Training Division_V1_Bloodhound_3700 |
| Drilling Bids_Compiled.pdf |
| PDS_Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (sonic) |
| Direct Push |
| City of Tallahassee Fire Training Site_GW Protection PFAS Free Water Estimate Email |
| Cascade_Geosyntec Consultants, Inc. - City of Tallahassee Fire Training Facility - PN221026-118844 |
| GW Protection_Geosyntec (T) 1022060 S.pdf |
| Invoice |
| Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (MOT).xlsx.pdf |
| Sheet1 |
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v1.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v2.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v2.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Subtask 5 |
| Subtask 6 |
| 2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev2.pdf |
| Table 1 for SAWP |
| Monitoring Well Locations |
File details come from the government source that posted it. Updated .