This document is a Task Assignment (TA) entered into between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. (GHD), a private environmental consulting firm. The task assignment is identified as DC010B under Contract Number HW684 and pertains to groundwater monitoring services at the former Town & Country Cleaners site located at 8490 W Hillsborough Avenue in Tampa, Hillsborough County, Florida. The project is designated as ERIC_4730 within FDEP's environmental remediation program. Kevin Kane serves as the Department Project Manager, while Brian Moore represents GHD as the contractor's project manager.
The scope of work consists of two subtasks: Project Management (Subtask 1) calculated at 13 percent of direct labor costs, and Groundwater Sampling (Subtask 2) involving annual groundwater sampling at ten monitoring wells (MW001, MW003, MW004, MW005, MW006, MW007, MW009, MW011, MW012, and MW013). Work includes depth-to-water measurements, groundwater sample analysis for volatile organic halocarbons using EPA Method 8260, and preparation of a comprehensive monitoring report with groundwater elevation and analytical figures. The total task assignment value is $6,666.06 on a fixed unit rate basis, with the deliverable (Groundwater Monitoring Report) due on August 31, 2023, and overall task completion by September 30, 2023. Invoice payment is contingent upon FDEP approval of the submitted Groundwater Monitoring Report and Project Management documentation. Cost estimates include labor ($4,351.78), travel ($120.00), laboratory analysis ($806.50), subcontractor services for investigation-derived waste disposal ($121.00), field equipment and expenses ($831.60), and a completion fee ($435.18).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC010B Completion September 30, 2023
GHD Services, Inc. will conduct groundwater sampling at the former Town & Country Cleaners site located in Tampa, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on June 13, 2023.
Kevin Kane (850) 245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore (813) 257-0658
ERIC_4730
8490 W Hillsborough Ave, Tampa, Hillsborough County
Town & Country Cleaners
✔ $ 6,666.06
$ 6,666.06
Scope of Work
Brian Moore
Contract Manager
Brian Moore Digitally signed by Brian Moore Date: 2023.06.30 13:24:00 -04'00'
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.06.30 11:30:29 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report + Project Management 08/31/2023
Subtasks 1 and 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 6,666.06
$ 6,666.06
HW684
DC010B
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO:
FROM:
DATE:
SUBJECT:
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
HW684 Contract File
Kevin Kane, Contract Manager
June 30, 2023
Task Assignment DC010B Town & Country Cleaners
ERIC_4730
Monitoring
GHD Services, Inc. (GHD) will conduct annual groundwater sampling. Specific subtasks are detailed below:
Subtask 1: Project Management Project management is calculated at 13% of the direct labor.
Subtask 2: Groundwater Sampling Annual groundwater sampling will be conducted at (10) site monitoring wells MW001, MW003, MW004, MW005, MW006, MW007, MW009, MW011, MW012, and MW013.
Prior to sampling, depth to water measurements will be gathered from all existing wells.
Groundwater sampling will then be conducted in accordance with FDEP SOPs. All groundwater samples will be analyzed for the presence of volatile organic halocarbons by EPA Method 8260. Following receipt of groundwater analytical results, a summary report will be prepared. The summary report will include a description of field sampling methodology and analytical results. Groundwater elevation and analytical figures will also be prepared. The report will also include recommendations regarding the next step toward site rehabilitation.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis.
The Florida Department of Environmental Protection (FDEP) has a current and valid Site Access Agreement for this site, signed January 11, 2013.
This work will be conducted in line with the scope of work included with GHD’s proposal, received June 13, 2023. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is August 31, 2023, and the completion date for the task assignment is September, 2023.
The final cost total for Task Assignment DC010B is $6,666.06.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 6/30/2023
Task #: DC010B SubTask 1 Project Management SubTask 6
Site: Town & Country SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$44.81 Project Manager JM 4.18 4.18 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$51.08 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$43.28 Professional Engineer/Sc GE 14.50 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.11 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $44.81 Project Manager/ Enginee JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $35.16 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.53 Senior Technician SA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.35 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.89 Senior Technician WM 9.50 9.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.25 Junior Technician WO 10.75 10.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.00 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.16 Administrative Assistant DA 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 51.93 4.18 47.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,626.23 $187.09 $1,439.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $2,110.84 $242.84 $1,868.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $614.71 $70.72 $543.99 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,351.78 $500.65 $3,851.13 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 6/30/2023
Task #: DC010B SubTask 1 Project Management SubTask 6
Site: Town & Country SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.00 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.00 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $730.00 $730.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $76.50 $76.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $806.50 $806.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $691.60 $691.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $831.60 $831.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,230.88 $500.65 $5,730.23 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $435.18 $50.07 $385.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $6,666.06 $550.72 $6,115.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $6,666.06 Auto-Calculated
Final Total Cost: $6,666.06 Auto-Calculated
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Town & Country Cleaners SUBTASK 2: Groundwater Monitoring
DATE: 6/30/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Professional Engineer JH Conclusions/Recommendations 1
Professional Geologist GE Coordinate site access to the interior 0.5 Professional Geologist GE Field work preparation 1 Professional Geologist GE characterize IDW 1 Professional Geologist GE Groundwater sampling methdology 2 Professional Geologist GE Groundwater Elevation evaluation (shallow/intermediate) 4 Professional Geologist GE Groundwater analytical evaluation (shallow/intermediate) 4 Professional Geologist GE Laboratory Data Validation 1 Professional Geologist GE Conclusions and Recommendations 1
14.5
Senior Technician WM Mob/Demob 1 Senior Technician WM Equipment Calibration/COC forms 1 Senior Technician WM Groundwater Sampling (5 wells) 7.5
9.5
Junior Technician WO Mob/Demob 1 Junior Technician WO Water Levels (all wells - 14 total) 2.25 Junior Technician WO Groundwater Sampling (5 wells) 7.5
10.75
Drafting Technician PM Prepare Groundwater Contour Figures (shallow/intermediate) 3 Drafting Technician PM Prepare Groundwater Analytical Figures (shallow/intermediate) 3
Staff Assistants DA Data Entry (10 wells + water levels) 1.5 Staff Assistants DA Update summary tables 1 Staff Assistants DA Document Preparation/Publishing/PDF 2 Staff Assistants DA GIS/Adapt update 1.5
TOTAL LABOR 47.75
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Disposal $110 drum 1 $110.00
TOTAL $110.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
EPA Method 8260 VOHs $73.00 10 $730.00 sample shipping (two day - large cooler) $70.00 1 $70.00 Ice $6.50 1 $6.50
TOTAL LAB $806.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 1 $40.00
Groundwater Sampling Kit $290.00 Day 2 $580.00 Poly Tubing (HDPE) $0.30 Ft 272 $81.60 Silicon Tubing $3.00 Ft 10 $30.00
55-gallon drum $100.00 drum 1 $100.00
TOTAL EQUIPMENT $831.60
FINAL --7/24/96
COST PROPOSAL FOR TASK DC010B
<Town & Country Cleaners/FDEP ERIC_4730>
<Groundwater Monitoring >
1. INTRODUCTION:
GHD submitted a Supplemental Site Assessment Report (SSAR) in February 2020 for the Town & Country Cleaners site located in Tampa, Hillsborough County. The results of the groundwater sampling conducted identified Vinyl Chloride as the primary contaminant of concern at the site. The SSAR was approved along with the assessment for the site and periodic groundwater sampling was recommended. Task assignment DC015B includes annual groundwater sampling at selected site monitoring wells in accordance with recommendations from GHD’s September 13, 2022.
Subtask 1: Project Management Subtask 1 includes all activities associated with completion of groundwater sampling and preparation of a Groundwater Monitoring Report.
Subtask 2: Groundwater Sampling Groundwater sampling is recommended in order to evaluate concentration trends over time.
Annual groundwater sampling will be conducted at site monitoring wells MW001, MW003, MW004, MW005, MW006, MW007, MW009, MW011, MW012, and MW013. Prior to sampling, depth to water measurements will be gathered from all existing wells. Groundwater sampling will then be conducted in accordance with FDEP SOPs. All groundwater samples will be analyzed for the presence of volatile organic halocarbons by EPA Method 8260.
Following receipt of groundwater analytical results, a summary report will be prepared. The summary report will include a description of field sampling methodology and analytical results. Groundwater elevation and analytical figures will also be prepared. The report will also include recommendations regarding the next step toward site rehabilitation.
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
Groundwater Monitoring Report 8/31/23
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway – Suite F
Tampa, FL 33610
May 23, 2022
Re: Transportation and Disposal of Non-Hazardous Soil and Water – Florida
Mr. Moore:
The price for disposal of drums of non-hazardous soil or groundwater located in the State of Florida will be $110.00 per drum, for both transportation and disposal.
This pricing is valid for all regions in the State of Florida except for the Florida Keys.
Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
This quote is valid for 180 days.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
6/28/22, 10:23 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 1/2
Quote Number: 19644
QUOTE
QUOTED TO: Brian Moore
QUOTE DATE: 1/1/2022
COMPANY NAME: GHD - 2022 QUOTED BY: Craig Burns
PHONE NUMBER:
Ext.
FAX NUMBER:
PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS
CUSTOMER PO:
CONTACT EMAIL:
SITE ADDRESS: TBD
CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING
COST ESTIMATE FOR
THE SITE/ PROJECT LISTED ABOVE.
DESCRIPTION PRICE QTY. UNIT TOTAL
NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00
NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00
TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$30.00 DRUM $0.00
TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$40.00 DRUM $0.00
TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site
$50.00 DRUM $0.00
Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax
$0.00 . $0.00
HAZ Drums to be quoted case-by-case $0.00 . $0.00
OPTIONAL LINE ITEMS
***10% FSC applied to the total cost of the invoice*** $0.00 . $0.00
TOTAL REQUIRED ITEMS $0.00
TOTAL OPTIONAL ITEMS $0.00
GRAND TOTAL $0.00
NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.
**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns
863.327.6289 - cburns@clarkenv.com
This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.
quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 2/2
Name (print) Title
Signature Date
CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854
WWW.ClarkEnvironmental.com
From: Craig Burns To: Brian Moore Subject: GHD_IDW Drum Rates FL Date: Tuesday, June 28, 2022 10:26:46 AM Attachments: image001.png image002.png image003.png image004.png image005.png GHD Drum Rates FL 2022.pdf
Here you go Brian. I do this for a lot of engineering/consulting firms.
Be aware of the low stop less than 6 drums at $50/flat Be aware of the 10% to the total cost for FSC (implemented April 15).
Pass around the GHD Florida offices
From: Brian Moore <Brian.Moore@ghd.com> Sent: Tuesday, June 28, 2022 10:05 AM To: Craig Burns <cburns@clarkenvironmental.com> Subject: IDW Drums
Craig, Is it possible to provide a generic quote for IDW water disposal.
Assumption is non-haz with necessary analytical Maybe provide a range of locations
South florida or central florida, or both?
Thanks in advance
We have many sites that we generate 1 gw drum of IDW and would like to streamline the vendor coordination
BRIAN MOORE PE
GHD
Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com
The Power of Commitment
Connect
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please mailto:cburns@clarkenvironmental.com mailto:Brian.Moore@ghd.com https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttp-253A-252F-252Fwww.ghd.com-252F-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093857306-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DorO8Q-252BVqTyo6Ej-252F8ZwSbVyQzLpZtJywYELQonaQNZfo-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DsMxOUn-szAtJTATQBUgjjDdI6e6b1jo5alN-ez9vKSM%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=K3MyGMhP6XEk1ApT%2FRIPjGR%2BUFJFG9ahCVCi8Z9R1n0%3D&reserved=0 mailto:brian.moore@ghd.com https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.linkedin.com-252Fcompany-252Fghd-252F-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093857306-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3D5HB99sCNyHUdh3ySqo-252BMbX9lHf94JW-252BuI1gRPH6qLGY-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DBQdX3FW3jjZZNHH7wbXXUS30LUnS3GtU1HJ8G56Snwo%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=%2BQlcPM%2FGtFT%2FrIbbuGi0PnSgurtBD8yqWgV1hvkvk00%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.facebook.com-252FGHDGroup-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093867263-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DKXDgOYLYSf-252BwLLtpvQNMpyPzR3DV5-252FDBogAW3HWif9Y-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DdHZdva6F1f6cSXNf7WLXU9x5VBxbTV01G78hKDk-cSA%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=142JKLTMfwfz%2FAO%2FXHrz%2FUodXSRzYWWBygfbg7vBIWs%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Ftwitter.com-252FGHDspeaks-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093877221-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3Duwh4lLmvdNCQkyPoUgiL7r2l9-252BmFgEv2JbZPLM3ptM0-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3D6FLD5pJDe4zG94aUPcPkIB9mx5JTMUxrAOX-fjV9l3o%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=O7BUsLKToxyyPXzZcLcBA1z3Q7%2FKvVsiCNGMGHOzln0%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.youtube.com-252Fchannel-252FUCwUGfe6zgaddIXqA7entIwQ-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093877221-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DVTPo9BdB-252FyUkff7ZLoE6J99Jt9f-252Fvtuta-252Fsm1KEOuNc-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3D9S3nI6ai6gtzPu1y34Kb_OuqwixCpq0TgIkmYlOz0gk%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=YX45%2BiFGXo7axCd4VDmEIFdcmHajQE6n8KvktA7llOs%3D&reserved=0 quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 1/2
Quote Number: 19644
QUOTE
QUOTED TO: Brian Moore
QUOTE DATE: 1/1/2022
COMPANY NAME: GHD - 2022 QUOTED BY: Craig Burns
PHONE NUMBER:
Ext.
FAX NUMBER:
PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS
CUSTOMER PO:
CONTACT EMAIL:
SITE ADDRESS: TBD
CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING
COST ESTIMATE FOR
THE SITE/ PROJECT LISTED ABOVE.
DESCRIPTION PRICE QTY. UNIT TOTAL
NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00
NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00
TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$30.00 DRUM $0.00
TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site
$40.00 DRUM $0.00
TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site
$50.00 DRUM $0.00
Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax
$0.00 . $0.00
HAZ Drums to be quoted case-by-case $0.00 . $0.00
OPTIONAL LINE ITEMS
***10% FSC applied to the total cost of the invoice*** $0.00 . $0.00
TOTAL REQUIRED ITEMS $0.00
TOTAL OPTIONAL ITEMS $0.00
GRAND TOTAL $0.00
NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.
**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns
863.327.6289 - cburns@clarkenv.com
This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.
quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 2/2
Name (print) Title
Signature Date
CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854
WWW.ClarkEnvironmental.com delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
Whatever Waste, LLC 3834 Mandarin Woods Dr. No.
Jacksonville, Florida 32223 United States 904.881.1957
Brian Moore PE
GHD
5904 Hampton Road Parkway Suite F Tampa, FL 33610
Estimate Number 062922.1
Notes Dry Cleaner Site Locations: Central and South Florida Regions excluding Florida Keys Required analytical data for non-haz disposal acceptance would be VOCs and includes waste profiling assistance if the IDW-GW drums don't fall under a blanket waste profile DOT shippable drums must be on a hard surface at each accessible location
Terms Non-hazardous IDW drum pickup, transport and disposal pricing is based on per service event No-load drum fee if unable to pickup drums on any site in Central FL is $150; in South FL is $200 Pricing is valid or subject to change on a monthly basis in part due to escalating fuel prices Payment required within 45 days after email receipt of invoice
Indemnification: Each party agrees to indemnify, defend and hold harmless each other for and from any loss
Estimate Date 06/29/2022
Description Rate Qty Line Total
IDW-GW Drum Transport & Disposal - Central FL Sites
(1) Regional Stop Fee $600 - then $150 per 55-gal drum < 10 drums
$150.00 1 $150.00
IDW-GW Drum Transport & Disposal - Central FL Sites
(1) Regional Stop Fee $300 - then $150 per 55-gal drum > 10 drums
$150.00 1 $150.00
IDW-GW Drum Transport & Disposal - South FL Sites
(1) Regional Stop Fee $850 - then $200 per 55-gal drum < 10 drums
$200.00 1 $200.00
IDW-GW Drum Transport & Disposal - South FL Sites
(1) Regional Stop Fee $425 - then $200 per 55-gal drum > 10 drums
$200.00 1 $200.00
Subtotal
Tax
700.00
0.00
Estimate Total (USD) $700.00 or liability arising out of the party's breach of this agreement, scope of work, except for gross negligence, willful misconduct or bad faith.
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Tue 6/13/23 Mon 6/26/23
2 Subtask 1: Project Management
49 days Mon 6/26/23
Thu 8/31/23
3 Subtask 2: Groundwter Monitoring
49 days Mon 6/26/23
Thu 8/31/23
4 Field Work Preparation 3 wks Mon 6/26/23Fri 7/14/23
5 Groundwater Sampling 1 day Mon 7/17/23Mon 7/17/23
6 Groundwater Monitoring Report
5 wks Fri 7/28/23 Thu 8/31/23
6/4 6/11 6/18 6/25 Jul
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC010B at the Town & Country Cleaners site located in Tampa, Hillsborough County
Project: TA_010B Date: Tue 6/13/23
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Tue 6/13/23 Mon 6/26/23
2 Subtask 1: Project Management
49 days Mon 6/26/23
Thu 8/31/23
3 Subtask 2: Groundwter Monitoring
49 days Mon 6/26/23
Thu 8/31/23
4 Field Work Preparation 3 wks Mon 6/26/23Fri 7/14/23
5 Groundwater Sampling 1 day Mon 7/17/23Mon 7/17/23
6 Groundwater Monitoring Report
5 wks Fri 7/28/23 Thu 8/31/23
Gabrielle Enos
William McKinney,William O
7/2 7/9 7/16 7/23 ly
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC010B at the Town & Country Cleaners site located in Tampa, Hillsborough County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Tue 6/13/23 Mon 6/26/23
2 Subtask 1: Project Management
49 days Mon 6/26/23
Thu 8/31/23
3 Subtask 2: Groundwter Monitoring
49 days Mon 6/26/23
Thu 8/31/23
4 Field Work Preparation 3 wks Mon 6/26/23Fri 7/14/23
5 Groundwater Sampling 1 day Mon 7/17/23Mon 7/17/23
6 Groundwater Monitoring Report
5 wks Fri 7/28/23 Thu 8/31/23
Ouchie
7/30 8/6 8/13 8/20 August
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC010B at the Town & Country Cleaners site located in Tampa, Hillsborough County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Tue 6/13/23 Mon 6/26/23
2 Subtask 1: Project Management
49 days Mon 6/26/23
Thu 8/31/23
3 Subtask 2: Groundwter Monitoring
49 days Mon 6/26/23
Thu 8/31/23
4 Field Work Preparation 3 wks Mon 6/26/23Fri 7/14/23
5 Groundwater Sampling 1 day Mon 7/17/23Mon 7/17/23
6 Groundwater Monitoring Report
5 wks Fri 7/28/23 Thu 8/31/23 Jeremy Hess,Gabrielle Enos,Peter McLean,Debra Andre
8/27 9/3 9/10 9/17 September
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC010B at the Town & Country Cleaners site located in Tampa, Hillsborough County
File details come from the government source that posted it. Updated .