CN-370000-HW684-DC02A.pdf
PDF 2 MB Posted
- Contract number
- HW684
- Issued by
- Florida
About this file
This is a Task Assignment (TA) document executed between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. The task assignment is issued under Contract Number HW684 and is identified as Task Assignment DC002A. The contract is managed by Kevin Kane for FDEP and Brian Moore for GHD Services, Inc., with the work to be performed at the Wash House site located at 670 S Tamiami Trail, Venice, Sarasota County, Florida (Project Number ERIC_5444).
The scope of work consists of two subtasks: Project Management (Subtask 1) calculated at 12.5 percent of direct labor costs, and Groundwater Monitoring (Subtask 2) involving annual sampling at seven monitoring wells (MW002, MW003, MW006, MW013, MW014, MW015, and MW016) with depth-to-water measurements and analysis of volatile organic halocarbons using EPA Method 8260. The total task assignment value is $6,816.06 on a fixed unit rate basis, with payment contingent upon submission and FDEP approval of the Groundwater Monitoring Report. The deliverable is due March 31, 2022, with overall task completion by June 30, 2022. Labor costs total $4,751.96, supplemented by travel ($120.00), subcontractor services including investigation derived waste disposal ($110.00), laboratory analysis ($636.00), and field equipment expenses ($722.90), with a completion fee of $475.20. Subcontractors for IDW disposal were selected on a lowest-cost basis.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC002A Completion June 30, 2022
GHD Services, Inc. will conduct annual groundwater sampling at the Wash House site located in Venice, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on January 10, 2022.
Kevin Kane (850) 245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore (813) 257-0658
ERIC_5444
670 S Tamiami Trl, Venice, Sarasota County
Wash House
✔ $ 6,816.06
$ 6,816.06
Scope of Work
Brian Moore
Contract Manager
Brian Moore Digitally signed by Brian Moore Date: 2022.01.26 14:59:05 -05'00'
William E. Burns Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.01.26 10:47:44 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report + Project Management 03/31/2022
Subtasks 1 and 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 6,816.06
$ 6,816.06
HW684
DC002A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
TO: HW684 Contract File
FROM: Kevin Kane, Contract Manager
DATE: January 26, 2022
SUBJECT: Task Assignment DC002A
Wash House
ERIC_5444
Monitoring
GHD Services, Inc. (GHD) will annual groundwater sampling. Specific subtasks are detailed below:
Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.
Subtask 2: Groundwater Monitoring Groundwater sampling will be conducted at 7 monitoring wells (MW002, MW003, MW006, MW013, MW014, MW015, and MW016) in accordance with previous GHD recommendations and Department comments. Prior to groundwater sampling, depth to water measurements will be gathered from all available wells. Samples will be submitted to a Florida-certified laboratory and analyzed for VOHs by EPA Method 8260. IDW disposal is anticipated and has been accounted for under this subtask. Upon completion of groundwater sampling activities, a Groundwater Monitoring Report will be generated and submitted to the Department.
Subcontractors for investigation derived waste (IDW) disposal were chosen on a lowest-cost basis.
The Florida Department of Environmental Protection (FDEP) has a current and valid Site Access Agreement for this site, signed July 28, 2017.
This work will be conducted in line with the scope of work included with GHD’s proposal, received January 10, 2022.
Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is March 31, 2022, and the completion date for the task assignment is June 30, 2022.
The final cost total for Task Assignment DC002A is $6,816.06.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 01/25/22
Task #: DC002A SubTask 1 Project Management SubTask 6
Site: Wash House SubTask 2 Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.12 Project Manager JM 5.10 5.1 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$46.33 Sr Professional Engineer JH 1.50 1.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$43.28 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 17.00 17.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 11.50 11.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 13.00 13.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 4.75 4.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 59 5 54 0 0 0 0 0 0 0 0
Direct Labor $1,775.77 $204.29 $1,571.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $2,304.95 $265.17 $2,039.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $671.24 $77.22 $594.02 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,751.96 $546.68 $4,205.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF GHD Page 1
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 01/25/22
Task #: DC002A SubTask 1 Project Management SubTask 6
Site: Wash House SubTask 2 Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $584.00 $584.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $52.00 $52.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $636.00 $636.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $682.90 $682.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $722.90 $722.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,340.86 $546.68 $5,794.18 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $475.20 $54.67 $420.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $6,816.06 $601.35 $6,214.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF GHD Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Wash House
SUBTASK 2:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer JH Conclusions/Recommendations 1.5 1.5
Professional Engineer JM Specify laboratory data deliverable/Sample Kit 1 Professional Engineer JM Site Access 1 Professional Engineer JM Field sampling SOW/coordinate site access 1 Professional Engineer JM QA/QC field and laboratory data 1 Professional Engineer JM IDW profiling 1 Professional Engineer JM Project Background 2 Professional Engineer JM Groundwater Sampling Methods 1 Professional Engineer JM Groundwater flow evaluation (shallow, intermediate, deep) 3 Professional Engineer JM Water Quality Parameter Summary 1 Professional Engineer JM Groundwater Analtycial Results 3 Professional Engineer JM QA/QC Laboratory Data 1 Professional Engineer JM Conclusions/Recommendations 1
Senior Technician WM Mob/demob 4 Senior Technician WM Water Levels (all wells - 28 total) 3 Senior Technician WM Groundwater Sampling (4 wells) 6
Senior Technician SA Mob/demob 4 Senior Technician SA Water Levels (all wells - 28 total) 3 Senior Technician SA Groundwater Sampling (3 wells) 4.5
11.5
Drafting Technician PM Prepare GW Flow maps (shallow, intermediate, deep) 4 Drafting Technician PM Prepare VOC plume figures with updated concentration data 2
Staff Assistant DA Data Entry (28 wls, and 7 monitor wells) 1.25 Staff Assistant DA Update summary tables (elevation, parameter, analytical) 1.5 Staff Assistant DA Document Preparation/Publishing 2
4.75
TOTAL LABOR 53.75
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Disposal (1 drum) $100.00 $100.00
TOTAL $100.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs EPA 8260 $73.00 7 1 $584.00 Sample Shipping Small Cooler (2 day) $52.00 1 $52.00
TOTAL LAB $636.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables Expendables $40.00 Day 1 $40.00
Analytical Related Groundwater Sampling Kit $290.00 day 2 $580.00 Poly Tubing (HDPE) $0.30 ft 273 $81.90 Silicon Tubing $3.00 ft 7 $21.00
TOTAL EQUIPMENT $722.90
01/25/22 Monitoring
FINAL --7/24/96
COST PROPOSAL FOR TASK DC002A
<Wash House/FDEP ERIC_5444>
< Groundwater Monitoring>
1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >
GHD Services Inc. (GHD) completed additional assessment activities and submitted a Supplemental Site Assessment Report (SSAR) for the Wash House site located in Venice, Sarasota County, in May 2020. In accordance with GHD recommendations and FDEP comments, additional monitoring was conducted and the latest Groundwater Monitoring Report was submitted in March 2021. Task DC002A includes annual groundwater monitoring per GHD’s recommendation and Department approval dated April 12, 2021.
Subtask 1: Project Management Subtask 1 includes all tasks associated with project management of the groundwater monitoring activities at the Wash House site.
Subtask 2: Groundwater Monitoring As part of subtask 2, GHD will sample monitor wells MW002, MW003, MW006, MW013, MW014, MW015, and MW016. Prior to sampling, depth to water measurements will be gathered at all site wells. Groundwater sampling will be conducted in general accordance with FDEP SOPs. All groundwater samples will be analyzed for the presence of volatile organic halocarbons (VOHs) by EPA Method 8260.
Upon receipt of analytical data, a Groundwater Monitoring Report (GWMR) will be prepared.
The GWMR will include a summary of field methodology and laboratory analytical results.
The GWMR will also include conclusions and recommendations.
Deliverables:
Deliverable Deliverable Due Date
Groundwater Monitoring Report 3/31/22
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway – Suite F
Tampa, FL 33610
March 16, 2020
Re: IP Cleaners - Miami, FL
Mr. Moore:
The price for disposal of two (2) drums of non-hazardous groundwater located in Miami, FL will be $100.00 per drum, or $200.00 total, for both transportation and disposal.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png
$95.00 per drum plus $150.00 stop charge Have a great day
Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.
P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com
From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami
Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks
Brian Moore, PE
GHD
Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect
WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION
mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
This e-mail has been scanned for viruses
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Mon 1/10/22Fri 1/21/22
2 Subtask 1: Project Management
72 days Mon 1/24/22
Tue 5/3/22
3 Subtask 2:
Groundwater Monitoring
49 days Mon 1/24/22
Thu 3/31/22
4 Field Work Preparation2 wks Mon 1/24/22Fri 2/4/22
5 Groundwater Sampling1 day Wed 2/9/22 Wed 2/9/22
6 Groundwater Monitoring Report
6 wks Fri 2/18/22 Thu 3/31/22
J
1/2 1/9 1/16 1/23 1/30 nuary February
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC002A at the Wash House site located in Venice, Sarasota County
Project: TA_051G Date: Mon 1/10/22
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Mon 1/10/22Fri 1/21/22
2 Subtask 1: Project Management
72 days Mon 1/24/22
Tue 5/3/22
3 Subtask 2:
Groundwater Monitoring
49 days Mon 1/24/22
Thu 3/31/22
4 Field Work Preparation2 wks Mon 1/24/22Fri 2/4/22
5 Groundwater Sampling1 day Wed 2/9/22 Wed 2/9/22
6 Groundwater Monitoring Report
6 wks Fri 2/18/22 Thu 3/31/22
Jenna Martin
Skylar Albritton,William McKinney
2/6 2/13 2/20 2/27 3/6 March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC002A at the Wash House site located in Venice, Sarasota County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Mon 1/10/22Fri 1/21/22
2 Subtask 1: Project Management
72 days Mon 1/24/22
Tue 5/3/22
3 Subtask 2:
Groundwater Monitoring
49 days Mon 1/24/22
Thu 3/31/22
4 Field Work Preparation2 wks Mon 1/24/22Fri 2/4/22
5 Groundwater Sampling1 day Wed 2/9/22 Wed 2/9/22
6 Groundwater Monitoring Report
6 wks Fri 2/18/22 Thu 3/31/22 Jenna Martin,Peter McLean,Je
3/13 3/20 3/27 4/3 4/10 April
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC002A at the Wash House site located in Venice, Sarasota County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Mon 1/10/22Fri 1/21/22
2 Subtask 1: Project Management
72 days Mon 1/24/22
Tue 5/3/22
3 Subtask 2:
Groundwater Monitoring
49 days Mon 1/24/22
Thu 3/31/22
4 Field Work Preparation2 wks Mon 1/24/22Fri 2/4/22
5 Groundwater Sampling1 day Wed 2/9/22 Wed 2/9/22
6 Groundwater Monitoring Report
6 wks Fri 2/18/22 Thu 3/31/22eremy Hess,Debra Andrews
4/17 4/24 5/1 5/8 5/15 May
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC002A at the Wash House site located in Venice, Sarasota County
File details come from the government source that posted it. Updated .