About this file

This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to GHD Services, Inc. for environmental remediation work at a contaminated site. The Task Assignment Number is DC024A, issued under the parent Contract Number HW684, with Kevin Kane serving as the FDEP Project Manager and Brian Moore as the contractor's Project Manager. The work is located at the former Nu-Touch Cleaners site at 190 Barton Boulevard in Rockledge, Brevard County, Florida, with a project number of ERIC_4023.

The Task Assignment authorizes GHD Services, Inc. to conduct a groundwater sampling event and prepare associated monitoring and closure documentation. The work is divided into two subtasks: Subtask 1 covers Project Management (calculated at 13% of direct labor), and Subtask 2 covers Groundwater Monitoring, which includes depth-to-water measurements at seven monitor wells, groundwater sampling at three wells (MW003, MW004, MW005) analyzed for volatile organic halocarbons by EPA Method 8260, and preparation of a Groundwater Monitoring Report with potential Site Rehabilitation Completion Report if closure criteria are met. The total contract value is $3,783.50 on a fixed unit rate basis, with the primary deliverable—the Groundwater Monitoring Report and Project Management documentation—due September 8, 2022, and task completion by December 9, 2022. The cost includes labor (approximately $2,556.81), travel expenses ($120.00), subcontractor services for Investigation Derived Waste disposal ($121.00), laboratory analytical costs ($277.50), field equipment and expendables ($452.50), and a completion fee ($255.69). The work is based on GHD's proposal dated June 22, 2022, and an executed Access Agreement with the current property owner.

View the file

Other files

File Type Posted
CN-370000-HW684-BIL02F.pdf PDF
CN-370000-HW684-BIL2CC03.pdf PDF
CN-370000-HW684-BIL2ECO1.pdf PDF
CN-370000-HW684-BIL2FCO1.pdf PDF
CN-370000-HW684-BIL2GCO1.pdf PDF
CN-370000-HW684-CSS02A.pdf PDF
CN-370000-HW684-CSS03B.pdf PDF
CN-370000-HW684-D033CCO1.pdf PDF
CN-370000-HW684-DC001A.pdf PDF
CN-370000-HW684-DC001F.pdf PDF
CN-370000-HW684-DC002B.pdf PDF
CN-370000-HW684-DC002C.pdf PDF
CN-370000-HW684-DC002D.pdf PDF
CN-370000-HW684-DC003D.pdf PDF
CN-370000-HW684-DC004D.pdf PDF
CN-370000-HW684-DC005A.pdf PDF
CN-370000-HW684-DC005D.pdf PDF
CN-370000-HW684-DC006B.pdf PDF
CN-370000-HW684-DC009C.pdf PDF
CN-370000-HW684-DC009D.pdf PDF
CN-370000-HW684-DC009E.pdf PDF
CN-370000-HW684-DC011A.pdf PDF
CN-370000-HW684-DC011C.pdf PDF
CN-370000-HW684-DC012D.pdf PDF
CN-370000-HW684-DC013B.pdf PDF
CN-370000-HW684-DC014D.pdf PDF
CN-370000-HW684-DC014F.pdf PDF
CN-370000-HW684-DC015A.pdf PDF
CN-370000-HW684-DC015C.pdf PDF
CN-370000-HW684-DC016B.pdf PDF
CN-370000-HW684-DC016C.pdf PDF
CN-370000-HW684-DC017C.pdf PDF
CN-370000-HW684-DC018C.pdf PDF
CN-370000-HW684-DC019C.pdf PDF
CN-370000-HW684-DC019D.pdf PDF
CN-370000-HW684-DC01ACO2.pdf PDF
CN-370000-HW684-DC020B.pdf PDF
CN-370000-HW684-DC025A.pdf PDF
CN-370000-HW684-DC026B.pdf PDF
CN-370000-HW684-DC026D.pdf PDF
CN-370000-HW684-DC027C.pdf PDF
CN-370000-HW684-DC028C.pdf PDF
CN-370000-HW684-DC029C.pdf PDF
CN-370000-HW684-DC031A.pdf PDF
CN-370000-HW684-DC034B.pdf PDF
CN-370000-HW684-DC03ACO1.pdf PDF
CN-370000-HW684-DC03CCO1.pdf PDF
CN-370000-HW684-DC03CCO2.pdf PDF
CN-370000-HW684-DC040A.pdf PDF
CN-370000-HW684-DC045B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW684

DC024A Completion December 9, 2022

This Task Assignment authorizes GHD Services, Inc. to conduct a groundwater sampling event at the former Nu-Touch Cleaners site located in Rockledge, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on June 22, 2022.

Kevin Kane (850) 245-8971 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

GHD Services, Inc.

GHD Services, Inc.

Brian Moore (813) 257-0658

ERIC_4023

190 Barton Blvd, Rockledge, Brevard County

Nu-Touch Cleaners

✔ $ 3,783.50

$ 3,783.50

Scope of Work

Brian Moore

Project Manager

Brian Moore Digitally signed by Brian Moore Date: 2022.07.18 22:00:33 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.07.18 16:21:52 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report + Project Management 09/08/2022

Subtasks 1 & 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 3,783.50

$ 3,783.50

HW684

DC024A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

TO: HW684 Contract File

FROM: Kevin Kane, Contract Manager

DATE: July 18, 2022

SUBJECT: Task Assignment DC024A

Nu-Touch Cleaners

ERIC_4023

Monitoring

GHD Services, Inc. (GHD) will conduct a groundwater sampling event at the former Nu- Touch Cleaners site located in Rockledge, Florida. Specific subtasks are detailed below:

Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.

Subtask 2: Groundwater Monitoring Groundwater monitoring will be conducted in accordance with GHD’s recommendations provided in the RASR and FDEP recommendations. Prior to groundwater sampling, depth to water measurements will be gathered from all site monitor wells (7 total).

Groundwater sampling will be conducted in accordance with FDEP Standard Operating Procedures at monitor wells MW003, MW004, and MW005. Groundwater samples will be submitted for analysis for the presence of volatile organic halocarbons by EPA Method 8260. Upon receipt of analytical data, a Groundwater Monitoring Report will be prepared. The report will include a summary of groundwater sampling methodology along with the laboratory analytical results. If the criteria for site closure are met, the report will also include a Site Rehabilitation Completion Report (SRCR) section detailing closure requirements. Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis.

GHD and the FDEP confirmed on July 18, 2022, that an Access Agreement with the current real property owner of the aforementioned site has been executed.

This work will be conducted in line with the scope of work included with GHD’s proposal, received June 22, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is September 8, 2022, and the completion date for the task assignment is December 9, 2022.

The final cost total for Task Assignment DC024A is $3,783.50.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 07/14/22

Task #: DC024A SubTask 1 Project Management SubTask 6

Site: Nu-Touch Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$40.12 Project Manager JM 2.70 2.7 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$46.33 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$43.28 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 11.50 11.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 9.75 9.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 3.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 2.50 2.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 30.45 2.70 27.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $955.46 $109.92 $845.54 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 129.80% $1,240.19 $142.68 $1,097.51 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $361.16 $41.55 $319.61 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $2,556.81 $294.15 $2,262.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 07/14/22

Task #: DC024A SubTask 1 Project Management SubTask 6

Site: Nu-Touch Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.00 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.00 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $219.00 $219.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $58.50 $58.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $277.50 $277.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $412.50 $412.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $452.50 $452.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $3,527.81 $294.15 $3,233.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $255.69 $29.42 $226.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $3,783.50 $323.57 $3,459.93 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Nu-Touch Cleaners SUBTASK 2: Groundwater Monitoring

DATE: 07/14/22

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer JH Conclusion/Recommendations 1

Project Manager JM Field Event Preparation 0.5 Project Manager JM Groundwater sampling metholdology 1 Project Manager JM Groundwater flow evaluation 1 Project Manager JM Groundwater flow evaluation 2 Project Manager JM Groundwater Analytical Results 2 Project Manager JM profile IDW for disposal 1 Project Manager JM Laboratory QA/QC 1 Project Manager JM SRCR text 2 Project Manager JM Conclusion/Recommendations 1

11.5

Senior Technician SA mob/demob 4 Senior Technician SA Depth to water measurements (7 wells) 1.25 Senior Technician SA Groundwater Sampling (3 wells) 4.5

9.75

Drafting Technician PM Groundwater Elevation Plan 2 Drafting Technician PM Groundwater Analytical Plan 1

Administrative Assistant DA Data Entry (3 gw and elevations) 0.5 Administrative Assistant DA Update summary tables 1 Administrative Assistant DA Finalize GWMR 1

2.5

TOTAL LABOR 27.75

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $120.00 day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin IDW Disposal 1 drum $110.00 $110.00

TOTAL $110.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs EPA 8260 $73.00 3 $219.00 small cooler (2 day) $52.00 1 $52.00 Ice $6.50 1 $6.50

TOTAL LAB $277.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

Expendables $40.00 day 1 $40.00

Equipment (Analytical Related)

Shallow Groundwater Sampling Kit $290.00 day 1 $290.00 poly tubing $0.30 ft 45 $13.50 silicon tubing $3.00 ft 3 $9.00 drum $100.00 drum 1 $100.00

Equipment (Other) $0.00 $0.00

TOTAL EQUIPMENT $452.50

FINAL --7/24/96

COST PROPOSAL FOR TASK DC024A

< Nu-Touch Cleaners, ERIC_4023>

Groundwater Monitoring

1. INTRODUCTION:

GHD recently completed SVE system operations at the Nu-Touch Cleaners site located in Rockledge, Brevard County. A Remedial Action Status Report (RASR) dated March 1, 2022 recommended cessation of operations and completion of groundwater sampling. Task DC024A includes groundwater sampling as detailed below.

Subtask 1 Project Management Sub Task 1 includes all tasks associated with managing the groundwater sampling and reporting for the Nu-Touch Cleaners facility.

Subtask 2 Groundwater Monitoring Groundwater monitoring will be conducted in accordance with GHD’s recommendations provided in the RASR. Prior to groundwater sampling, depth to water measurements will be gathered from all site monitor wells (7 total). Groundwater sampling will be conducted in accordance with FDEP Standard Operating Procedures at monitor wells MW003, MW004, and MW005. Groundwater samples will be submitted for analysis for the presence of volatile organic halocarbons by EPA Method 8260.

Upon receipt of analytical data, a Groundwater Monitoring Report (GMR) will be prepared.

The GMR will include a summary of groundwater sampling methodology along with the laboratory analytical results. If the criteria for site closure are met, the GMR will also include a Site Rehabilitation Completion Report (SRCR) section detailing closure requirements.

Deliverables:

Deliverable Deliverable Due Date

Groundwater Monitoring Report 9/8/22

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

May 23, 2022

Re: Transportation and Disposal of Non-Hazardous Soil and Water – Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in the State of Florida will be $110.00 per drum, for both transportation and disposal.

This pricing is valid for all regions in the State of Florida except for the Florida Keys.

Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

6/28/22, 10:23 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 1/2

Quote Number: 19644

QUOTE

QUOTED TO: Brian Moore

QUOTE DATE: 1/1/2022

COMPANY NAME: GHD - 2022 QUOTED BY: Craig Burns

PHONE NUMBER:

Ext.

FAX NUMBER:

PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS

CUSTOMER PO:

CONTACT EMAIL:

SITE ADDRESS: TBD

CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING

COST ESTIMATE FOR

THE SITE/ PROJECT LISTED ABOVE.

DESCRIPTION PRICE QTY. UNIT TOTAL

NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00

NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00

TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site

$30.00 DRUM $0.00

TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site

$40.00 DRUM $0.00

TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site

$50.00 DRUM $0.00

Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax

$0.00 . $0.00

HAZ Drums to be quoted case-by-case $0.00 . $0.00

OPTIONAL LINE ITEMS

***10% FSC applied to the total cost of the invoice*** $0.00 . $0.00

TOTAL REQUIRED ITEMS $0.00

TOTAL OPTIONAL ITEMS $0.00

GRAND TOTAL $0.00

NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.

**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns

863.327.6289 - cburns@clarkenv.com

This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.

6/28/22, 10:23 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 2/2

Name (print) Title

Signature Date

CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854

WWW.ClarkEnvironmental.com

Whatever Waste, LLC 3834 Mandarin Woods Dr. No.

Jacksonville, Florida 32223 United States 904.881.1957

Brian Moore PE

GHD

5904 Hampton Road Parkway Suite F Tampa, FL 33610

Estimate Number 062922.1

Notes Dry Cleaner Site Locations: Central and South Florida Regions excluding Florida Keys Required analytical data for non-haz disposal acceptance would be VOCs and includes waste profiling assistance if the IDW-GW drums don't fall under a blanket waste profile DOT shippable drums must be on a hard surface at each accessible location

Terms Non-hazardous IDW drum pickup, transport and disposal pricing is based on per service event No-load drum fee if unable to pickup drums on any site in Central FL is $150; in South FL is $200 Pricing is valid or subject to change on a monthly basis in part due to escalating fuel prices Payment required within 45 days after email receipt of invoice

Indemnification: Each party agrees to indemnify, defend and hold harmless each other for and from any loss

Estimate Date 06/29/2022

Description Rate Qty Line Total

IDW-GW Drum Transport & Disposal - Central FL Sites

(1) Regional Stop Fee $600 - then $150 per 55-gal drum < 10 drums

$150.00 1 $150.00

IDW-GW Drum Transport & Disposal - Central FL Sites

(1) Regional Stop Fee $300 - then $150 per 55-gal drum > 10 drums

$150.00 1 $150.00

IDW-GW Drum Transport & Disposal - South FL Sites

(1) Regional Stop Fee $850 - then $200 per 55-gal drum < 10 drums

$200.00 1 $200.00

IDW-GW Drum Transport & Disposal - South FL Sites

(1) Regional Stop Fee $425 - then $200 per 55-gal drum > 10 drums

$200.00 1 $200.00

Subtotal

Tax

700.00

0.00

Estimate Total (USD) $700.00 or liability arising out of the party's breach of this agreement, scope of work, except for gross negligence, willful misconduct or bad faith.

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Wed 6/22/22Tue 7/5/22

2 Subtask 1: Project Management

47 days Wed 7/6/22 Thu 9/8/22

3 Subtask 2: Groundwater Monitoring

47 days Wed 7/6/22 Thu 9/8/22

4 Field Work Preparation 2 wks Wed 7/6/22 Tue 7/19/22

5 Groundwater Sampling 1 day Fri 7/22/22 Fri 7/22/22

6 Groundwater Monitoring Report

6 wks Fri 7/29/22 Thu 9/8/22

6/12 6/19 6/26 7/3 7/10 July

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC024A at the Nu-Touch Cleaners site located in Rockledge, Brevard County

Project: TA_024A Date: Wed 6/22/22

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Wed 6/22/22Tue 7/5/22

2 Subtask 1: Project Management

47 days Wed 7/6/22 Thu 9/8/22

3 Subtask 2: Groundwater Monitoring

47 days Wed 7/6/22 Thu 9/8/22

4 Field Work Preparation 2 wks Wed 7/6/22 Tue 7/19/22

5 Groundwater Sampling 1 day Fri 7/22/22 Fri 7/22/22

6 Groundwater Monitoring Report

6 wks Fri 7/29/22 Thu 9/8/22

Jenna Martin

Skylar Albritton

7/17 7/24 7/31 8/7 8/14 August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC024A at the Nu-Touch Cleaners site located in Rockledge, Brevard County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Wed 6/22/22Tue 7/5/22

2 Subtask 1: Project Management

47 days Wed 7/6/22 Thu 9/8/22

3 Subtask 2: Groundwater Monitoring

47 days Wed 7/6/22 Thu 9/8/22

4 Field Work Preparation 2 wks Wed 7/6/22 Tue 7/19/22

5 Groundwater Sampling 1 day Fri 7/22/22 Fri 7/22/22

6 Groundwater Monitoring Report

6 wks Fri 7/29/22 Thu 9/8/22 Jeremy Hess,Jenna Martin,Pe

8/21 8/28 9/4 9/11 9/18 September

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC024A at the Nu-Touch Cleaners site located in Rockledge, Brevard County