CN-370000-HW684-DC012B.pdf
PDF 10 MB Posted
- Contract number
- HW684
- Issued by
- Florida
About this file
Task Assignment Summary
This is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to GHD Services, Inc. authorizing remedial action implementation work at the Nu-Way Cleaners, Inc. site located at 1219 West Reynolds Street, Plant City, Hillsborough County, Florida. The task operates under Contract Number HW684 and is designated as TA DC012B with a completion date of June 23, 2023. The primary contacts are Kevin Kane (FDEP Project Manager, 850-245-8971) and Brian Moore (Contractor's Project Manager, 813-257-0658).
The task assignment authorizes GHD Services, Inc. to oversee the installation of seventeen remedial injection wells (three interior vertical, ten exterior vertical, and four exterior angled wells at depths of 24-44 feet), conduct baseline and performance groundwater sampling at 42 wells, execute remedial injections using EOSPRO substrate and dechlorinating microbes, and prepare a Construction Completion Report. The total contract value is $165,548.46 on a fixed unit rate basis, broken down into five subtasks: Project Management ($4,830.42), Injection Well Installation ($41,803.69), Baseline Groundwater Sampling ($19,816.16), Remedial Injections ($85,243.84), and Quarter 1 Performance Groundwater Sampling and Construction Completion Report ($13,854.35). Work commenced June 22, 2022, with major deliverables due on September 20, 2022 (well installation), October 13, 2022 (baseline sampling), November 18, 2022 (remedial injections), and March 21, 2023 (construction completion report).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC012B Completion June 23, 2023
This Task Assignment authorizes GHD Services, Inc. to oversee the installation of remedial injection wells, conduct remedial injections, and conduct baseline and performance groundwater sampling at the Nu-Way Cleaners site located in Plant City, FL. All work will be conducted in accordance with the scope of work and cost proposal submitted on June 17, 2022.
Kevin Kane (850) 245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore (813) 257-0658
ERIC_4701
1219 W Reynolds St, Plant City, Hillsborough County
Nu-Way Cleaners, Inc.
✔ $ 165,548.46
$ 165,548.46
Scope of Work
Brian Moore
Project Manager
Brian Moore Digitally signed by Brian Moore Date: 2022.06.22 09:02:19 -04'00'
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2022.06.21 16:27:49 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Injection Well Installation Summary 09/20/2022
Baseline Groundwater Sampling Summary 10/13/2022
Remedial Injection Summary 11/18/2022
Construction Completion Report + Project Management 03/21/2023
Subtask 2: Upon completion and FDEP approval of the Injection Well Installation Summary $ 41,803.69
Subtask 3: Upon completion and FDEP approval of the Baseline Groundwater Sampling Summary $ 19,816.16
Subtask 4: Upon completion and FDEP approval of the Remedial Injection Summary $ 85,243.84
Subtasks 1 & 5: Upon completion and FDEP approval of the Construction Completion Report + Project Management $ 18,684.77
$ 165,548.46
HW684
DC012B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
TO: HW684 Contract File Nu-Way Cleaners Plant City, Hillsborough County
ERIC_4701
FROM: Kevin Kane, Contract Manager
DATE: June 21, 2022
SUBJECT: Task Assignment Summary
HW684 DC012B
Construction
This Task Assignment authorizes GHD Services, Inc. (GHD) to oversee the installation of remedial injection wells, conduct remedial injections, and conduct baseline and performance groundwater sampling. Specific subtasks are detailed below:
Subtask 1 - Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2 - Injection Well Installation GHD will oversee the installation of remedial injection wells within the subject facility and to the west. In total, three (3) interior vertical injection wells, ten (10) exterior vertical injection wells, and four (4) exterior angled injection wells will be installed. The wells will be installed using direct-push technology to depths of 24, 43, or 44 feet bls as specified in the RAP. The wells will be completed in flush-mounted stainless steel manhole covers. Following installation, the remedial injection wells will be developed and the development water and cuttings will be containerized for off-site disposal. Upon completion of well installation activities, field notes and well construction permits/logs will be submitted to the FDEP.
Subtask 3 - Baseline Groundwater Sampling As proposed in the approved RAP, GHD personnel will conduct baseline groundwater sampling. Prior to groundwater sampling, a full round of depth to water measurements will be gathered from all available monitoring wells (49 total). Following depth-to-water measurements, groundwater sampling will be conducted at a total of forty-two wells (42) including 32 monitor wells and 10 injection wells as specified in the RAP. Groundwater sampling will be conducted in accordance with FDEP standard operating procedures.
Groundwater samples will be analyzed for the presence of volatile organic halocarbons, total organic carbon, total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrate, molybdenum, chloride, sulfate, iron, and/or dissolved gases per the RAP. Upon receipt of analytical data, the field notes and laboratory data will be provided to the FDEP along with recommendations for RAP implementation.
Subtask 4 - Remedial Injections Following baseline sampling, substrate injections will commence. The injections will include the selected substrate (EOSPRO) along with selected nutrients. In accordance with the design, 3,080 to 3,115 gallons of solution will be injected into each well. A total of 880 gallons of EOSPRO substrate is specified. In addition to substrate, nutrients, and dechlorinating microbes will be injected into the subsurface. A total of 17 liters of dechlorinating culture is specified.
Subtask 5 - Quarter 1 Performance Groundwater Sampling Approximately 3 months following the injections, groundwater performance monitoring will be conducted. Groundwater sampling will be conducted at ten (10) monitor wells including: MW001, MW006, MW029, MW031, MW032, MW033, MW007, MW024, MW025, and MW028. A full round of water levels will not be gathered during this sampling event. Samples will be analyzed for the presence of volatile organic halocarbons, total organic carbon, total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrate, molybdenum, chloride, sulfate, iron, and/or dissolved gases per the RAP. Following receipt of analytical data, an injection summary and performance monitoring report (Construction Completion Report) will be prepared.
The report will include a summary of injection activities along with a summary and evaluation of analytical data. The report will also include recommendations for additional testing and/or remediation.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors were chosen on a lowest-cost and availability basis.
The Florida Department of Environmental Protection (FDEP) has a current and valid site access agreement for this site, signed December 31, 2013.
Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is March 21, 2023, and the completion date for the Task Assignment is June 23, 2023.
The final cost total for Task Assignment DC012B is $165,548.46.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 06/20/22
Task #: DC012B SubTask 1 Project Management SubTask 6
Site: Nu-Way Cleaners, Inc. SubTask 2 Well Installation SubTask 7
Activity/Phase: Construction SubTask 3 Baseline Sampling SubTask 8
Project Manager: Brian Moore, PE SubTask 4 Injections SubTask 9
SubTask 5 Q1 Sampling and Construction Completion Report SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.12 Project Manager JM 40.90 40.9 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$46.33 Sr Professional Engineer JH 65.25 2.00 12.00 11.25 40.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$43.28 Professional Engineer/Sc GE 61.50 61.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 2.00 0.00 0.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 51.25 0.00 42.50 0.00 8.75 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 205.00 0.00 42.50 153.75 8.75 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 18.00 2.00 8.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 20.25 2.00 8.00 3.00 7.25 0.00 0.00 0.00 0.00 0.00
$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 464.15 40.90 67.50 113.00 168.00 74.75 0.00 0.00 0.00 0.00 0.00
Direct Labor $14,263.97 $1,640.99 $2,858.64 $2,819.63 $4,230.87 $2,713.84 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $18,514.63 $2,130.01 $3,710.51 $3,659.88 $5,491.67 $3,522.56 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $5,391.78 $620.29 $1,080.57 $1,065.82 $1,599.27 $1,025.83 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $38,170.38 $4,391.29 $7,649.72 $7,545.33 $11,321.81 $7,262.23 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $2,640.00 $600.00 $480.00 $1,440.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 1
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 06/20/22
Task #: DC012B SubTask 1 Project Management SubTask 6
Site: Nu-Way Cleaners, Inc. SubTask 2 Well Installation SubTask 7
Activity/Phase: Construction SubTask 3 Baseline Sampling SubTask 8
Project Manager: Brian Moore, PE SubTask 4 Injections SubTask 9
SubTask 5 Q1 Sampling and Construction Completion Report SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,640.00 $600.00 $480.00 $1,440.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $27,755.00 $27,755.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $1,320.00 $1,100.00 $110.00 $0.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Groundwater Proteciton $44,750.00 $0.00 $0.00 $44,750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sirem $5,378.25 $0.00 $0.00 $5,378.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 EOS Remediation $12,542.29 $0.00 $0.00 $12,542.29 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Chem Direct $1,647.50 $0.00 $0.00 $1,647.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $93,393.04 $28,855.00 $110.00 $64,318.04 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $9,339.31 $2,885.50 $11.00 $6,431.81 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $102,732.35 $31,740.50 $121.00 $70,749.85 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $12,107.50 $300.00 $7,338.00 $0.00 $4,469.50 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $684.50 $58.50 $313.00 $0.00 $313.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $12,792.00 $358.50 $7,651.00 $0.00 $4,782.50 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $1,040.00 $240.00 $160.00 $600.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,706.70 $0.00 $3,004.30 $0.00 $702.40 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $650.00 $450.00 $100.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $5,396.70 $690.00 $3,264.30 $600.00 $842.40 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $161,731.43 $4,391.29 $41,038.72 $19,061.63 $84,111.66 $13,128.13 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $3,817.03 $439.13 $764.97 $754.53 $1,132.18 $726.22 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $165,548.46 $4,830.42 $41,803.69 $19,816.16 $85,243.84 $13,854.35 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Nu-Way Cleaners, Inc.
SUBTASK 2: Well Installation
DATE: 06/20/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Professional Engineer JH Well installation scope of work and site access 1 Sr. Professional Engineer JH IDW Profiling and Disposal 1
Professional Engineer/Sci GE Mob/demob from Tampa (6 days) 7.5 Professional Engineer/Sci GE Oversee Well Installation (DPT) - 4 days 36 Professional Engineer/Sci GE Oversee Well Installation (Sonic) - 2 days 18
61.5
Drafting Technician PM Update site plan with well locations 2
Staff Assistant DA Data Entry (New Well Entry - 17 wells) 2
6 TOTAL LABOR 67.5
VEHICLE TYPE RATE UNIT USEAGE
Truck $480.00 week 1 $480.00 Truck $120.00 day 1 $120.00
TOTAL VEHICLE $600.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Groundwater Protection Mobilizaiton (DP indoor rig) 1 each $800.00 $800.00 Groundwater Protection Per Diem (2 man crew) 4 night $250.00 $1,000.00 Groundwater Protection DPT rig and crew 4 day $1,600.00 $6,400.00 Groundwater Protection Indoor Rig 1 day $500.00 $500.00 Groundwater Protection 1" PVC material 13 each $20.00 $260.00 Groundwater Protection 1" PVC well install 512 ft $5.00 $2,560.00 Groundwater Protection 3" expandable point 13 each $20.00 $260.00 Groundwater Protection 2x2 concrete pad 17 each $125.00 $2,125.00 Groundwater Protection Well Development 13 each $50.00 $650.00 Groundwater Protection Drums 10 drum $65.00 $650.00 Groundwater Protection Mobilizattion (sonic) 1 each $1,000.00 $1,000.00 Groundwater Protection Per Diem (3 man crew) 2 night $375.00 $750.00 Groundwater Protection Sonic rig and crew 2 day $4,250.00 $8,500.00 Groundwater Protection 1" PVC well install 200 ft $8.00 $1,600.00 Groundwater Protection Centralizers 8 each $40.00 $320.00 Groundwater Protection 1" female plug 4 each $20.00 $80.00 Groundwater Protection Well Development 4 each $75.00 $300.00 Erwin Remediation IDW Drum (soil) 6 drum $110.00 $660.00 Erwin Remediation IDW Drum (water) 4 drum $110.00 $440.00
TOTAL $28,855.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOC Full List EPA Method 8260 $150.00 2 $300.00 IDW samples (soil and gw) Shipping Small Cooler (2 day) $52.00 1 $52.00
Ice $6.50 1 $6.50
TOTAL LAB $358.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 6 $240.00
Equipment (Analytical Related)
Equipment (Other)
Total Survey Station $50.00 day 2 $100.00 Total GPS Station $175.00 day 2 $350.00
TOTAL EQUIPMENT $690.00
FINAL --7/24/96
SUBTASK 3: Baseline Sampling
DATE: 06/20/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Professional Engineer JH Specify laboratory data deliverable/Sample Kit 1 Sr. Professional Engineer JH Field sampling SOW/coordinate site access 1 Sr. Professional Engineer JH QA/QC field and laboratory data 1 Sr. Professional Engineer JH IDW Profile and Disposal 1 Sr. Professional Engineer JH Summarize data and present to FDEP prior to Injections 8
Senior Technician WM Mob/demob from Tampa (4 days) 5 Senior Technician WM Water Levels (All Wells - 49 total) 6 Senior Technician WM Groundwater Sampling (21 wells) 31.5
42.5
Senior Technician SA Mob/demob from Tampa (4 days) 5 Senior Technician SA Water Levels (All Wells - 49 total) 6 Senior Technician SA Groundwater Sampling (21 wells) 31.5
42.5
Drafting Technician PM Prepare GW Flow Maps (5 zones) 4 Drafting Technician PM Prepare GW Analytical Figures (5 zones) 4
Staff Assistant DA Data Entry (49 water levels and 42 gw samples) 5 Staff Assistant DA Update summary tables (wl, parameter, analytical, uic) 3
TOTAL LABOR 113
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $480.00 week 1 $480.00
TOTAL VEHICLE $480.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin IDW Disposal 1 drum $110.00 $110.00
TOTAL $110.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs EPA Method 8260 $73.00 41 $2,993.00 41 wells VOC Full List EPA Method 8260 $150.00 2 $300.00 1 well and IDW sample
TOC 9060 $30.00 8 $240.00
TDS SM2540C $16.00 10 $160.00
TRPH FL-PRO $88.00 10 $880.00
sodium 6010 $13.50 10 $135.00 ammonia EPA 350.1 $24.00 10 $240.00 nitrate 353.2 $23.00 10 $230.00 molbdenum 6010 $13.50 10 $135.00 chloride 300 $24.00 10 $240.00 sulfate 300 $21.00 10 $210.00 iron 6010 $13.50 10 $135.00 dissolved gases RSK175 $180.00 8 $1,440.00 Shipping Large Cooler $150.00 2 $300.00
Ice $6.50 2 $13.00
TOTAL LAB $7,651.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 4 $160.00
Equipment (Analytical Related)
Groundwater Sampling Kit $1,160.00 week 2 $2,320.00 1 per technician Poly Tubing $0.30 ft 1861 $558.30 Silicon Tubing $3.00 ft 42 $126.00
Equipment (Other)
Drum $100.00 drum 1 $100.00
TOTAL EQUIPMENT $3,264.30
SUBTASK 4: Injections
DATE: 06/20/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Professional Engineer JH Remedial injection scope of work and site access 2 Sr. Professional Engineer JH mob/demob 1.25 Sr. Professional Engineer JH Initial site visit to kickoff injections 8
11.25
Senior Technician WM Mob/demob from Tampa (15 days) 18.75 Senior Technician WM Oversee remedial injections (15 days) 135
153.75
Staff Assistant DA Data Entry (Injection details at 17 wells) 3
TOTAL LABOR 168
VEHICLE TYPE RATE UNIT USEAGE
Truck $480.00 week 3 $1,440.00
TOTAL VEHICLE $1,440.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Groundwater Protection Mobilization / Demobilization 1 ls $3,000.00 $3,000.00 Groundwater Protection Per Diem (2 Man Crew) 12 night $250.00 $3,000.00 Groundwater Protection Injection Trailer/2 Man Crew/In 15 day $2,450.00 $36,750.00 Groundwater Protection Water Meter Rental and Use 1 each $1,000.00 $1,000.00 Groundwater Protection Bobcat Loader 1 day $1,000.00 $1,000.00 Groundwater Protection Permits: Not Applicable each $0.00 $0.00 EOS Remediation LLC EOSPRO 16 drums $604.80 $9,676.80 EOS Remediation LLC Shipping 1 each $2,100.00 $2,100.00 EOS Remediation LLC taxes 6.5% $765.49 Sirem KB-1 Plus 17 liters $250.00 $4,250.00 Sirem Shipping 1 each $800.00 $800.00 Sirem taxes 6.5% $328.25 Chem Direct mono potassium phosphate 5 1 kg bag $40.00 $200.00 Chem Direct ammonium bicarbonate 1 45 kg bag $843.75 $843.75 Chem Direct ammonium bicarbonate 1 12 kg bag $475.00 $475.00 Chem Direct sodium thiosulfate 1 2.5 kg bag $128.75 $128.75
TOTAL $64,318.04
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 15 $600.00
Equipment (Analytical Related) $2.00 $0.00 $0.00
Equipment (Other) $0.00 $0.00
TOTAL EQUIPMENT $602.00
SUBTASK 4: Q1 Sampling and Construction Completion Report
DATE: 06/20/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager JM Conclusions/Recommendations 2
Sr. Professional Engineer JH Field Scope of work and order sample kits 1 Sr. Professional Engineer JH Review field data, verify COC 1 Sr. Professional Engineer JH Baseline groundwater sampling summary 4 Sr. Professional Engineer JH Summarize injection well installation 4 Sr. Professional Engineer JH Summarize remedial injections 6 Sr. Professional Engineer JH Post injection sampling event summary 3 Sr. Professional Engineer JH Groundwater sampling parameters (2 events) 4 Sr. Professional Engineer JH Water level data and flow evaluations (5 zones - 2 events) 5 Sr. Professional Engineer JH Groundwater Analytical summary (5 zones - 2 events) 6 Sr. Professional Engineer JH UIC parameters and TOC data summary 2 Sr. Professional Engineer JH QA/QC 2 Sr. Professional Engineer JH Conclusions/Recommendations 2
Senior Technician WM Mob/demob from Tampa (1 day) 1.25 Senior Technician WM Groundwater Sampling (5 wells) 7.5
8.75
Senior Technician SA Mob/demob from Tampa (1 day) 1.25 Senior Technician SA Groundwater Sampling (5 wells) 7.5
8.75
Drafting Technician PM Prepare GW Flow Maps (5 zones) 4 Drafting Technician PM Prepare GW Analytical Figures (5 zones) 4
Staff Assistant DA Data Entry (10 gw samples) 1.25 Staff Assistant DA Update summary tables (wl, parameter, analytical, uic) 2 Staff Assistant DA Publish CCR 4
7.25
TOTAL LABOR 74.75
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 day 1 $120.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin IDW Disposal 1 drum $110.00 $110.00
TOTAL $110.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs EPA Method 8260 $73.00 7 $511.00 MW006, MW007, MW029, MW031, MW033, MW025, MW028 VOC Full List EPA Method 8260 $150.00 1 $150.00 MW001
TOC 9060 $30.00 8 $240.00 MW001, 6, 7, 25, 28, 29, 31, 33
TDS SM2540C $16.00 9 $144.00 MW001, 7, 24, 25, 28, 29, 31, 32, 33
TRPH FL-PRO $88.00 9 $792.00 MW001, 7, 24, 25, 28, 29, 31, 32, 33
sodium 6010 $13.50 9 $121.50 MW001, 7, 24, 25, 28, 29, 31, 32, 33 ammonia EPA 350.1 $24.00 9 $216.00 MW001, 7, 24, 25, 28, 29, 31, 32, 33 nitrate 353.2 $23.00 9 $207.00 MW001, 7, 24, 25, 28, 29, 31, 32, 33 molbdenum 6010 $13.50 9 $121.50 MW001, 7, 24, 25, 28, 29, 31, 32, 33 chloride 300 $24.00 9 $216.00 MW001, 7, 24, 25, 28, 29, 31, 32, 33 sulfate 300 $21.00 9 $189.00 MW001, 7, 24, 25, 28, 29, 31, 32, 33 iron 6010 $13.50 9 $121.50 MW001, 7, 24, 25, 28, 29, 31, 32, 33 dissolved gases RSK175 $180.00 8 $1,440.00 MW001, 6, 7, 25, 28, 29, 31, 33 Shipping Large Cooler $150.00 2 $300.00
Ice $6.50 2 $13.00
TOTAL LAB $4,782.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 1 $40.00
Equipment (Analytical Related)
Groundwater Sampling Kit $290.00 day 2 $580.00 1 per technician Poly Tubing $0.30 ft 308 $92.40 Silicon Tubing $3.00 ft 10 $30.00
Equipment (Other)
Drum $100.00 drum 1 $100.00
TOTAL EQUIPMENT $842.40
COST PROPOSAL FOR TASK DC012B
Nu-Way Cleaners Inc., ERIC_4701
Construction (Injection well installation, Baseline Sampling, Injections, Groundwater Monitoring)
1. INTRODUCTION:
A Remedial Action Plan (RAP) was submitted for the Nu-Way Cleaners facility located in Plant City, Hillsborough County, Florida. The RAP proposed well installation and remedial injections for groundwater treatment. The RAP was approved in January 2022. Task DC012B includes costs associated with RAP implementation.
Subtask 1-Project Management Sub Task 1 includes all tasks associated with implementation of well installation, baseline sampling, remedial injections, and one quarter of groundwater monitoring and reporting.
Subtask 2-Injection Well Installation As specified, GHD will oversee the installation of remedial injection wells within the subject facility and to the west. In total, three (3) vertical interior injection wells, ten (10) exterior vertical injection wells, and four (4) exterior angled injection wells will be installed. The wells will be installed using direct-push technology to depths of 24, 43, or 44 feet bls as specified in the RAP. The wells will be completed in flush-mounted stainless steel manhole covers.
Following installation, the remedial inject wells will be developed and the development water and cuttings will be containerized for off-site disposal.
Upon completion of well installation activities, field notes and well construction permits/logs will be submitted to the FDEP.
Subtask 3-Baseline Groundwater Sampling As proposed in the approved RAP, GHD personnel will conduct baseline groundwater sampling. Prior to groundwater sampling, a full round of depth to water measurements will be gathered from all available monitoring wells (49 total). Following depth-to-water measurements, groundwater sampling will be conducted at a total of forty-two wells (42) including 32 monitor wells and 10 injection wells as specified in the RAP. Groundwater sampling will be conducted in accordance with FDEP standard operating procedures.
Groundwater samples will be analyzed for the presence of volatile organic halocarbons, total organic carbon, total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrate, molybdenum, chloride, sulfate, iron, and/or dissolved gases per the RAP.
Upon receipt of analytical data, the field notes and laboratory data will be provided to the FDEP along with recommendations for RAP implementation.
Subtask 4 - Remedial Injections
Following baseline sampling, substrate injections will commence. The injections will include the selected substrate (EOSPRO) along with selected nutrients. In accordance with the design, 3,080 to 3,115 gallons of solution will be injected into each well. A total of 880 gallons of EOSPRO substrate is specified. In addition to substrate, nutrients, and dechlorinating microbes will be injected into the subsurface. A total of 17 liters of dechlorinating culture is specified.
Subtask 5-Quarter 1 Performance Groundwater Sampling Approximately 3 months following the injections, groundwater performance monitoring will be conducted. Groundwater sampling will be conducted at ten (10) monitor wells including:
MW001, MW006, MW029, MW031, MW032, MW033, MW007, MW024, MW025, and MW028. A full round of water levels will not be gathered during this sampling event. Samples will be analyzed for the presence of volatile organic halocarbons, total organic carbon, total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrate, molybdenum, chloride, sulfate, iron, and/or dissolved gases per the RAP.
Following receipt of analytical data, an injection summary and performance monitoring report (Construction Completion Report) will be prepared. The report will include a summary of injection activities along with a summary and evaluation of analytical data. The report will also include recommendations for additional testing and/or remediation.
Deliverables:
Deliverable Deliverable Due Date
Field notes and subcontractor invoices for injection well installation 9/20/22
Field notes and laboratory data for baseline sampling 10/13/22
Field notes and subcontractor invoices for remedial injections 11/18/22
Construction Completion Report 3/21/23
Drilling Number Unit Unit Rate Total Number Unit Unit Rate Total Number Unit Unit Rate Total
Mobilization 2 each $1,500.00 $3,000.00 VerticalShallow Injection Well 3 well $1,350.00 $4,050.00 Vertical Intermediate Well 10 well $1,850.00 $18,500.00 No response Angled Intermediate Well 4 well $2,050.00 $8,200.00 Mobilization (Includes 420M Indoor Rig) 1 ls $800.00 $800.00 Per Diem (2 man crew) 4 night $250.00 $1,000.00 DPT Rig and Crew 4 day $1,600.00 $6,400.00 Daily Rate: DPT Rig w/ 2-man Crew 0 1/2 day $1,050.00 $0.00 420 M Indoor Rig (Interior Wells) 1 ls $500.00 $500.00 Materials: 1" PVC Female Adapter and Threaded Plug 13 each $20.00 $260.00 Materials: 1" PVC Well Installation 512 foot $5.00 $2,560.00 Materials: 3" Expendable Points 13 foot $20.00 $260.00 2' x 2' Concrete Pad w/8" BD Completion 13 each $125.00 $1,625.00 Well Development (up to 1/2 hour w/Pump) 13 each $50.00 $650.00 20 drum $75.00 $1,500.00 55 gallon drums (Soil) 2 each $65.00 $130.00 55 gallon drums (Water) 4 each $65.00 $260.00 Permits: SWFLWMD-Not Required for Injection wells 3 each $100.00 $300.00 Mobilization 1 ls $1,000.00 $1,000.00 Per Diem (3 Man Crew) 2 night $375.00 $750.00 Daily Rate: Sonic Rig w/ Crew 2 day $4,250.00 $8,500.00 Daily Rate: Sonic Rig w/ Crew 1/2 day 0 1/2 day $2,000.00 $0.00 Materials: 1"' Sch 40 PVC Well Installation 200 foot $8.00 $1,600.00 Materials: Centralizers for Screened Interval 8 each $40.00 $320.00 Materials: 1" Female and Threaded Plug 4 each $20.00 $80.00 2' x 2' Concrete Pad w/8" Flush Completion 4 each $125.00 $500.00 Well Development (Includes up to 1/2 Hr w/ Pump) 4 each $75.00 $300.00 Additional Well Development 0 1/2 hour $75.00 $0.00 Bobcat for IDW & Tooling Management 1 ls $1,000.00 $0.00 55 gallon drums (Soil) 2 each $65.00 $130.00 55 gallon drums (Water) 2 each $65.00 $130.00 Fire Hydrant Meter (Rental & Usage) (If Needed) 0 ls $500.00 $0.00 Mobilization / Demobilization 1 ls $3,000.00 $3,000.00 Per Diem (2 Man Crew) 12 night $250.00 $3,000.00 Injection Trailer/2 Man Crew/Injection Equipment, Meters, Hoses, Tank 15 day $2,450.00 $36,750.00 Drums Soil 0 each $65.00 $0.00 Drums Water 0 each $65.00 $0.00 Water Meter Rental and Use 1 each $1,000.00 $1,000.00 Bobcat Loader 1 day $1,000.00 $1,000.00 Lump Sum per injeciton location 17 well $7,100.00 $120,700.00 Permits: Not Applicable each $0.00 $0.00
$72,505.00 $156,250.00 $0.00
IDW
Number Unit Unit Rate Total Number Unit Unit Rate Total Number Unit Unit Rate Total
IDW Soil Drum 6 drum $110.00 $660.00 6 drum $110.00 $660.00 6 drum $144.00 $864.00 IDW Water Drum 6 drum $110.00 $660.00 6 drum $90.00 $540.00 6 drum $178.00 $1,068.00 Transportation Fees $120.00 $662.82 Transportation 12 each $36.00 $432.00
$1,320.00 $1,320.00 $3,026.82
EOSPRO (specified in the RAP)
EOS PRO 16 drum $604.80 $9,676.80 specified in RAP Shipping 1 load $2,100.00 $2,100.00 Taxes 6.50% $765.49
$12,542.29
Sirem (KB-1 specified in the RAP)
KB-1 Plus 17 liters 250 $4,250.00 specified in RAP Shipping 1 each 800 $800.00 Taxes 6.50% $328.25
$5,378.25
Chemicals Number Unit Unit Rate Total Number Unit Unit Rate Total Number Unit Unit Rate Total
Monopotassium phosphate (9.1 lbs or 4.1 kg) 5 1 kg $40.00 $200.00 5 2.5 kg $330.50 $1,652.50 2 2.5 kg $532.00 $1,064.00
Ammonium bicarbonate (130 lbs or 58.5 kg) Number Unit Unit Rate Total Number Unit Unit Rate Total Number Unit Unit Rate Total 1 45 kg $843.75 $843.75 1 50 kg $1,496.00 $1,496.00 5 12 kg $730.77 $3,653.85 1 12 kg $475.00 $475.00 3 0.5 kg $646.50 $1,939.50
$1,318.75 $3,435.50 $3,653.85
Sodium thiosulfate (4 lbs or 1.8 kg) Number Unit Unit Rate Total Number Unit Unit Rate Total Number Unit Unit Rate Total 1 2.5 kg $128.75 $128.75 3 1 kg $76.96 $230.88 1 2.5 kg $330.50 $330.50
Fisher Chemical Grainger
Groundwater Protection
Sonic
Preferred Cascade
Injections
DPT
Chem Direct SpectrumGrainger
Erwin Clark Clean Management
Milipore SigmaTermo ScientificChem Direct
Chem Direct
ID Task Mode
Task Name Duration Start Finish
1 LOE submittal/approval 2 wks Thu 6/16/22 Wed 6/29/22 2 Subtask 1: Project
Management 189 days Thu 6/30/22 Tue 3/21/23
3 Subtask 2: Injection Well Installation
54 days Thu 7/7/22 Tue 9/20/22
4 Field Work Preparation 6 wks Thu 7/7/22 Wed 8/17/22 5 Well Installation 6 days Mon 8/22/22 Mon 8/29/22 6 Prepare Task Deliverable 3 wks Wed 8/31/22 Tue 9/20/22 7 Subtask 3: Baseline Samplin32 days Wed 8/31/22 Thu 10/13/22 8 Field Work Preparation 2 wks Wed 8/31/22 Tue 9/13/22 9 Groundwater Sampling 4 days Tue 9/13/22 Fri 9/16/22 10 Data Review/Evaluation 3 wks Fri 9/23/22 Thu 10/13/22 11 Subtask 4: Remedial
Injections 46 days Fri 9/16/22 Fri 11/18/22
12 Field Work Preparation 2 wks Fri 9/16/22 Thu 9/29/22 13 Remedial Injections 3 wks Mon 10/3/22 Fri 10/21/22 14 Perpare Task Deliverable 3 wks Mon 10/31/22 Fri 11/18/22 15 Subtask 5: Groundwater
Sampling and CCR 47 days Mon 1/16/23 Tue 3/21/23
16 Field Work Preparation 2 wks Mon 1/16/23 Fri 1/27/23 17 Groundwater Sampling 1 day Mon 1/30/23 Mon 1/30/23 18 Construction Completion
Report 6 wks Wed 2/8/23 Tue 3/21/23
J
6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 8/14 e July August
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC012B at the Nu-Way Cleaners, Inc. site located in Plant City, Hillsborough
Project: TA_012B Date: Thu 6/16/22
Task Name Duration Start Finish
1 LOE submittal/approval 2 wks Thu 6/16/22 Wed 6/29/22 2 Subtask 1: Project
Management 189 days Thu 6/30/22 Tue 3/21/23
3 Subtask 2: Injection Well Installation
54 days Thu 7/7/22 Tue 9/20/22
4 Field Work Preparation 6 wks Thu 7/7/22 Wed 8/17/22 5 Well Installation 6 days Mon 8/22/22 Mon 8/29/22 6 Prepare Task Deliverable 3 wks Wed 8/31/22 Tue 9/20/22 7 Subtask 3: Baseline Samplin32 days Wed 8/31/22 Thu 10/13/22 8 Field Work Preparation 2 wks Wed 8/31/22 Tue 9/13/22 9 Groundwater Sampling 4 days Tue 9/13/22 Fri 9/16/22 10 Data Review/Evaluation 3 wks Fri 9/23/22 Thu 10/13/22 11 Subtask 4: Remedial
Injections 46 days Fri 9/16/22 Fri 11/18/22
12 Field Work Preparation 2 wks Fri 9/16/22 Thu 9/29/22 13 Remedial Injections 3 wks Mon 10/3/22 Fri 10/21/22 14 Perpare Task Deliverable 3 wks Mon 10/31/22 Fri 11/18/22 15 Subtask 5: Groundwater
Sampling and CCR 47 days Mon 1/16/23 Tue 3/21/23
16 Field Work Preparation 2 wks Mon 1/16/23 Fri 1/27/23 17 Groundwater Sampling 1 day Mon 1/30/23 Mon 1/30/23 18 Construction Completion
Report 6 wks Wed 2/8/23 Tue 3/21/23
Jeremy Hess Gabrielle Enos
Jeremy Hess,Peter McLean,Debra An
Jeremy Hess William McKinney,Skylar Albritton
Jeremy Hess,Pete
Jeremy Hess William Mc
8/21 8/28 9/4 9/11 9/18 9/25 10/2 10/9 10/16 10/23 10/30 September October Nove
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC012B at the Nu-Way Cleaners, Inc. site located in Plant City, Hillsborough
Task Name Duration Start Finish
1 LOE submittal/approval 2 wks Thu 6/16/22 Wed 6/29/22 2 Subtask 1: Project
Management 189 days Thu 6/30/22 Tue 3/21/23
3 Subtask 2: Injection Well Installation
54 days Thu 7/7/22 Tue 9/20/22
4 Field Work Preparation 6 wks Thu 7/7/22 Wed 8/17/22 5 Well Installation 6 days Mon 8/22/22 Mon 8/29/22 6 Prepare Task Deliverable 3 wks Wed 8/31/22 Tue 9/20/22 7 Subtask 3: Baseline Samplin32 days Wed 8/31/22 Thu 10/13/22 8 Field Work Preparation 2 wks Wed 8/31/22 Tue 9/13/22 9 Groundwater Sampling 4 days Tue 9/13/22 Fri 9/16/22 10 Data Review/Evaluation 3 wks Fri 9/23/22 Thu 10/13/22 11 Subtask 4: Remedial
Injections 46 days Fri 9/16/22 Fri 11/18/22
12 Field Work Preparation 2 wks Fri 9/16/22 Thu 9/29/22 13 Remedial Injections 3 wks Mon 10/3/22 Fri 10/21/22 14 Perpare Task Deliverable 3 wks Mon 10/31/22 Fri 11/18/22 15 Subtask 5: Groundwater
Sampling and CCR 47 days Mon 1/16/23 Tue 3/21/23
16 Field Work Preparation 2 wks Mon 1/16/23 Fri 1/27/23 17 Groundwater Sampling 1 day Mon 1/30/23 Mon 1/30/23 18 Construction Completion
Report 6 wks Wed 2/8/23 Tue 3/21/23 ndrews er McLean,Debra Andrews cKinney Jeremy Hess,Peter McLean,Debra Andrews
11/6 11/13 11/20 11/27 12/4 12/11 12/18 12/25 1/1 1/8 1/15 ember December January
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC012B at the Nu-Way Cleaners, Inc. site located in Plant City, Hillsborough
Task Name Duration Start Finish
1 LOE submittal/approval 2 wks Thu 6/16/22 Wed 6/29/22 2 Subtask 1: Project
Management 189 days Thu 6/30/22 Tue 3/21/23
3 Subtask 2: Injection Well Installation
54 days Thu 7/7/22 Tue 9/20/22
4 Field Work Preparation 6 wks Thu 7/7/22 Wed 8/17/22 5 Well Installation 6 days Mon 8/22/22 Mon 8/29/22 6 Prepare Task Deliverable 3 wks Wed 8/31/22 Tue 9/20/22 7 Subtask 3: Baseline Samplin32 days Wed 8/31/22 Thu 10/13/22 8 Field Work Preparation 2 wks Wed 8/31/22 Tue 9/13/22 9 Groundwater Sampling 4 days Tue 9/13/22 Fri 9/16/22 10 Data Review/Evaluation 3 wks Fri 9/23/22 Thu 10/13/22 11 Subtask 4: Remedial
Injections 46 days Fri 9/16/22 Fri 11/18/22
12 Field Work Preparation 2 wks Fri 9/16/22 Thu 9/29/22 13 Remedial Injections 3 wks Mon 10/3/22 Fri 10/21/22 14 Perpare Task Deliverable 3 wks Mon 10/31/22 Fri 11/18/22 15 Subtask 5: Groundwater
Sampling and CCR 47 days Mon 1/16/23 Tue 3/21/23
16 Field Work Preparation 2 wks Mon 1/16/23 Fri 1/27/23 17 Groundwater Sampling 1 day Mon 1/30/23 Mon 1/30/23 18 Construction Completion
Report 6 wks Wed 2/8/23 Tue 3/21/23
Jeremy Hess William McKinney,Skylar Albritton
Jenna Martin
1/22 1/29 2/5 2/12 2/19 2/26 3/5 3/12 3/19 3/26 4/2 February March April
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC012B at the Nu-Way Cleaners, Inc. site located in Plant City, Hillsborough
File details come from the government source that posted it. Updated .