CN-370000-HW684-DC009A.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW684|68b160b8827755ddf560142dd2a41e53
Contract number
HW684
Issued by
Florida

About this file

This is a Task Assignment (TA) document entered into between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. under Contract Number HW684. The task assignment, identified as DC009A, is for groundwater sampling and well installation activities at the former Sargents One Hour Cleaners site located at 45 E. Washington Street in Orlando, Orange County, Florida. Kevin Kane serves as the FDEP Department Project Manager, while Brian Moore is the Contractor's Project Manager. The work is governed by the underlying Contract HW684 and will be executed in accordance with the scope of work and cost proposal submitted on March 8, 2022.

Task Assignment DC009A authorizes GHD Services, Inc. to conduct well installation and annual groundwater monitoring activities with a fixed unit rate total value of $13,131.10. The work is divided into two subtasks: Subtask 1 involves project management calculated at 13% of direct labor costs ($784.23), and Subtask 2 encompasses well installation and groundwater monitoring ($12,346.87). The scope includes installation of two intermediate depth monitor wells to depths of 56 and 35 feet, followed by groundwater sampling at 12 monitor wells analyzed for volatile organic compounds by EPA Method 8260. The primary deliverable is a Groundwater Monitoring Report with project management documentation due June 17, 2022, with full task completion by September 16, 2022. Invoice submission is contingent upon completion of groundwater sampling activities and FDEP approval of the monitoring report. The task assignment was signed on March 24, 2022, by Brian Moore (Contractor) and William E. Burns, Jr. (FDEP Secretary or Designee).

View the file

Other files

File Type Posted
CN-370000-HW684-BIL02F.pdf PDF
CN-370000-HW684-BIL2CC03.pdf PDF
CN-370000-HW684-BIL2ECO1.pdf PDF
CN-370000-HW684-BIL2FCO1.pdf PDF
CN-370000-HW684-BIL2GCO1.pdf PDF
CN-370000-HW684-CSS02A.pdf PDF
CN-370000-HW684-CSS03B.pdf PDF
CN-370000-HW684-D033CCO1.pdf PDF
CN-370000-HW684-DC001A.pdf PDF
CN-370000-HW684-DC001F.pdf PDF
CN-370000-HW684-DC002B.pdf PDF
CN-370000-HW684-DC002C.pdf PDF
CN-370000-HW684-DC002D.pdf PDF
CN-370000-HW684-DC003D.pdf PDF
CN-370000-HW684-DC004D.pdf PDF
CN-370000-HW684-DC005A.pdf PDF
CN-370000-HW684-DC005D.pdf PDF
CN-370000-HW684-DC006B.pdf PDF
CN-370000-HW684-DC009C.pdf PDF
CN-370000-HW684-DC009D.pdf PDF
CN-370000-HW684-DC009E.pdf PDF
CN-370000-HW684-DC011A.pdf PDF
CN-370000-HW684-DC011C.pdf PDF
CN-370000-HW684-DC012D.pdf PDF
CN-370000-HW684-DC013B.pdf PDF
CN-370000-HW684-DC014D.pdf PDF
CN-370000-HW684-DC014F.pdf PDF
CN-370000-HW684-DC015A.pdf PDF
CN-370000-HW684-DC015C.pdf PDF
CN-370000-HW684-DC016B.pdf PDF
CN-370000-HW684-DC016C.pdf PDF
CN-370000-HW684-DC017C.pdf PDF
CN-370000-HW684-DC018C.pdf PDF
CN-370000-HW684-DC019C.pdf PDF
CN-370000-HW684-DC019D.pdf PDF
CN-370000-HW684-DC01ACO2.pdf PDF
CN-370000-HW684-DC020B.pdf PDF
CN-370000-HW684-DC025A.pdf PDF
CN-370000-HW684-DC026B.pdf PDF
CN-370000-HW684-DC026D.pdf PDF
CN-370000-HW684-DC027C.pdf PDF
CN-370000-HW684-DC028C.pdf PDF
CN-370000-HW684-DC029C.pdf PDF
CN-370000-HW684-DC031A.pdf PDF
CN-370000-HW684-DC034B.pdf PDF
CN-370000-HW684-DC03ACO1.pdf PDF
CN-370000-HW684-DC03CCO1.pdf PDF
CN-370000-HW684-DC03CCO2.pdf PDF
CN-370000-HW684-DC040A.pdf PDF
CN-370000-HW684-DC045B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW684

DC009A Completion September 16, 2022

GHD Services, Inc. will conduct groundwater sampling and well installation activities at the former Sargents One Hour Cleaners site located in Orlando, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on March 8, 2022.

Kevin Kane (850) 245-8971 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

GHD Services, Inc.

GHD Services, Inc.

Brian Moore (813) 257-0658

ERIC_5061

45 E. Washington St., Orlando, Orange County

Sargents One Hour Cleaners (Formerly)

✔ $ 13,131.10

$ 13,131.10

Scope of Work

Brian Moore

Contract Manager

Brian Moore Digitally signed by Brian Moore Date: 2022.03.24 16:08:29 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.03.24 11:08:52 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report + Project Management 06/17/2022

Subtasks 1 & 2: Upon completion of groundwater sampling activities and FDEP approval of the Groundwater Monitoring Report + Project Management $ 13,131.10

$ 13,131.10

HW684

DC009A

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

TO:

FROM:

DATE:

SUBJECT:

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

HW684 Contract File Sargent’s One Hour Cleaners (Formerly)

ERIC_5061

Orlando, Orange County

Kevin Kane, Contract Manager

March 24, 2022

Task Assignment Summary

HW684 DC009A

Monitoring

GHD Services, Inc. will conduct groundwater sampling and well installation activities at the subject site. Specific subtasks are detailed below:

Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.

Subtask 2: Well Installation and Groundwater Sampling GHD will conduct monitor well installation and groundwater sampling. Specifically, new intermediate depth monitor wells will be installed at two locations. One well will be installed in the vicinity of on-site well MW012 and one well will be installed within the right of way area north of abandoned well MW021 (located downgradient of the site). The wells will be installed to depths of 56 and 35 feet bls, respectively. The well near MW012 will be constructed with 10 feet of well screen and the well near MW021 will be constructed with 5 feet of screen. The wells will be developed following construction.

Following well installation, groundwater sampling will be conducted at 12 monitor wells. All samples will be sent to a certified lab and analyzed for the presence of VOCs by EPA Method 8260. Depth to water measurements will be gathered from all available site monitor wells (18 total). Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Following completion of field sampling, a Groundwater Monitoring Report will be prepared and submitted to the Department.

The Florida Department of Environmental Protection (FDEP) has a current and valid Site Access Agreement for this site, signed April 19, 2005.

Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is June 17, 2022, and the completion date for the task assignment is September 16, 2022.

The final cost total for Task Assignment DC009A is $13,131.10.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 03/21/22

Task #: DC009A SubTask 1 Project Management SubTask 6

Site: Sargents One Hour Clea SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$40.12 Project Manager JM 6.60 6.6 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$46.33 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$40.00 Professional Engineer/Sc ES 16.50 16.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 27.00 27.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 8.50 8.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 4.50 4.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 6.50 6.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 70.60 6.60 64.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $2,315.77 $266.42 $2,049.35 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 129.80% $3,005.87 $345.81 $2,660.06 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $875.36 $100.71 $774.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,197.00 $712.94 $5,484.06 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF ARCADIS Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 03/21/22

Task #: DC009A SubTask 1 Project Management SubTask 6

Site: Sargents One Hour Clea SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $3,742.00 $3,742.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $3,942.00 $3,942.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $394.20 $394.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $4,336.20 $4,336.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $876.00 $876.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $76.50 $76.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $952.50 $952.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $625.70 $625.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $665.70 $665.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $12,511.40 $712.94 $11,798.46 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $619.70 $71.29 $548.41 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $13,131.10 $784.23 $12,346.87 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF ARCADIS Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Sargents One Hour Cleaners (formerly) SUBTASK 2: Groundwater Monitoring

DATE: 03/21/22

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer JH Conclusions/Recommendations 1

Professional Geologist ES Coordinate site access with City and current property owner 1 Professional Geologist ES Right of Way Permitting with City of Orlando 4 Professional Geologist ES Sample kit procurement-scope of work 0.5 Professional Geologist ES Verify analytical tables/field sampling methods/QA/QC 2 Professional Geologist ES General groundwater montioring report text update/sampling methods 2 Professional Geologist ES Field parameters (3 wells with traditional sampling) 1 Professional Geologist ES Groundwater flow evaluation (shallow/deep) 2 Professional Geologist ES Groundwater analytical summary (shallow/intermediate/deep) 3 Professional Geologist ES Conclusions and recommendations 1

16.5

Staff Engineer/Scientist DB Mob/demob from Orlando (3 days) 3 Staff Engineer/Scientist DB Oversee well installation 12 Staff Engineer/Scientist DB water levels all wells (18 total) 2 Staff Engineer/Scientist DB Groundwater sampling (5 wells with traditional method) 7.5 Staff Engineer/Scientist DB Groundwater sampling (7 wells)/requires 2 techs 20 min each 2.5

Senior Technician SA Mob/demob from Tampa (1 day) 4 Senior Technician SA water levels all wells (18 total) 2 Senior Technician SA Groundwater sampling (7 wells) 2.5

8.5

Drafting Technician PM Add new wells to the site plan 0.5 Drafting Technician PM Update Groundwater Flow figures (shallow/deep) 2 Drafting Technician PM Update Groundwater Analytical (shallow/intermediate/deep) 2

4.5

Staff Assistants DA Data Entry (12 sample points/18 water levels) 2 Staff Assistants DA Update summary tables for gw elevation and analytical data 1.5 Staff Assistants DA ADAPT/GIS Update 1 Staff Assistants DA Document Preparation/Publishing/generate pdf 2

6.5

TOTAL LABOR 64

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Groundwater Protection Mobilization 1 each $500.00 $500.00 Groundwater Protection DPT Rig/crew 1 day $1,600.00 $1,600.00 Groundwater Protection Materials 18 each $3.00 $54.00 Groundwater Protection Well Install 91 ft $5.00 $455.00 Groundwater Protection Prepack screens 1 each $95.00 $95.00 Groundwater Protection Prepack screens 1 each $170.00 $170.00 Groundwater Protection well completion 2 each $125.00 $250.00 Groundwater Protection development 2 each $75.00 $150.00 Groundwater Protection drums 2 each $65.00 $130.00 Groundwater Protection Landing map 1 each $250.00 $250.00 Groundwater Protection Permits 2 each $44.00 $88.00 Erwin IDW Drum 2 drum $100.00 $200.00

TOTAL $3,942.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs EPA Method 8021 $73.00 12 $876.00 sample shipping (Two Day-large cooler) $70.00 1 $70.00

Ice $6.50 1 $6.50

TOTAL LAB $952.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

Expendables $40.00 day 1 $40.00

Equipment (Analytical Related)

Difusion Samplers (small diameter) $36.00 each 7 $252.00 Groundwater Sampling kit $290.00 day 1 $290.00 Poly Tubing $0.30 ft 229 $68.70 Silicon tubing $3.00 ft 5 $15.00

Equipment (Other)

TOTAL EQUIPMENT $665.70

FINAL --7/24/96

COST PROPOSAL FOR TASK DC009A

Sargent’s, ERIC_5061

Groundwater Monitoring (Annual)

1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >

GHD completed active remediation at the Sargent’s One Hour Cleaners (Formerly) site located in Orlando, Orange County. The active remediation included operation of a Soil Vapor Extraction (SVE) system that successfully remediated shallow PCE impacts. Although shallow groundwater PCE concentrations have decreased, the Sargent’s site is situated within a larger area-wide groundwater plume. As such, annual groundwater monitoring was implemented in order to evaluate groundwater quality conditions over time. Task DC009A includes well installation and annual groundwater monitoring in accordance with GHD recommendations from June 2021 and FDEP comments dated July 16, 2021.

Subtask1: Project Management Subtask 1 includes all project management tasks associated with the groundwater sampling event and reporting.

Subtask 2: Well Installation and Groundwater Sampling Subtask 2 includes monitor well installation. Specifically, new intermediate depth monitor wells will be installed at two locations. One well will be installed in the vicinity of on-site well MW012 and one well will be installed within the right of way area north of abandoned well MW021 (located downgradient of the site). The wells will be installed to depths of 56 and 35 feet bls, respectively. The well near MW012 will be constructed with 10 feet of well screen and the well near MW021 will be constructed with 5 feet of screen. The wells will be developed following construction.

Following well installation, annual groundwater monitoring will be conducted at monitoring wells MW002, MW006, MW009, MW010, MW012, MW013, MW014, MW017, MW018, MW019, and the 2 newly installed wells. GHD personnel will mobilize to the site and gather water levels from all available site monitoring wells (18 total). Following water level measurements, groundwater samples will be gathered from the diffusion bag samplers directly for wells MW006, MW009, MW012, MW013, MW014, MW018, and MW019. Groundwater sampling will be conducted at MW002, MW010, MW017, and the 2 new wells using FDEP SOPs. All samples will be submitted to a Florida-certified laboratory for analysis for the presence of volatile organic halocarbons by EPA Method 8021/8260.

Following receipt of analytical data, a summary report will be prepared. The summary report will include a discussion of well installation, field sampling methodology and analytical results.

The report will also include recommendations regarding additional sampling and/or remediation.

Deliverable Deliverable Date Groundwater Monitoring Report, ADaPT and GIS data tables 6/17/22

Sonic Auger DPT Injection Well Abandonment

DATE: 3/1/2022

ESTIMATE #: 322003

Project Description:

ID QTY Unit Rate TOTAL

1 1 ls 500.00$ 500.00$

2 0 night 225.00$ -$

3 1 day 1,600.00$ 1,600.00$

4 18 each 3.00$ 54.00$

5 91 foot 5.00$ 455.00$

6 1 each 95.00$ 95.00$

7 1 each 170.00$ 170.00$

8 2 each 125.00$ 250.00$

9 2 each 75.00$ 150.00$

10 55 gallon drums (Soil) (Estimated) 1 each 65.00$ 65.00$

11 55 gallon drums (Water) (Estimated) 1 each 65.00$ 65.00$

12 Landing Mats (If Needed due to Pavers and Brick Paving at site) 1 ls 250.00$ 250.00$

13 Permits: Orange County 2 each 44.00$ 88.00$

Completion: Subtotal 3,742.00$

Todd Hodgson

TOTAL 3,742.00$

Partner

PROJECT

Sargents One Hour Cleaners 45 E. Washington Street

Damages to utilities on private property during borehole clearance are the responsibility of the client

5904 Hampton Oaks Pkwy Suite F

CUSTOMER

GHD

Brian Moore

Tampa, Florida 33610 Orlando, Florida

DPT Well Installation

2' x 2' Concrete Pad w/8" BD Completion

(813) 971-3882

(1) 1" x 35' PVC Well w/ 5' of .010 Slot Prepack Screen, 2' x 2' Pad w/8" BD Completion, Soil Sampling

(1) 1" x 56' PVC Well w/10' of .010 Slot Prepack Screen, 2' x 2' Pad w/8" BD Completion, Soil Sampling

Materials: (2) 1" x 5' PVC .010 Slot Prepack Screen, 3" Exp Point

Materials: Soil Sample Liners

If you have any questions concerning this proposal contact Todd Hodgson at (407) 426-7885 or Todd@drillprollc.com.

Not Responsible for Damage to Bricks or Pavers

THANK YOU FOR YOUR BUSINESS!

Todd Hodgson

DPT Rig and Crew

"Actual quantities used and days on site will be invoiced"

1 Day

DESCRIPTION

Mobilization

Utility Locates on Private Property is the responsibility of the client Borehole Clearance to 5’ bgs beyond 20 minutes may require a change order for additional time and cost.

Per Diem (2 man crew)

Materials: 1" PVC Well Installation

Materials: 1" x 5' PVC .010 Slot Prepack Screen, 3" Exp Point

Well Development (up to 1/2 hour w/Pump)

2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586

Preferred Drilling Solutions, Inc.

8820 66th St. North, Pinellas Park, FL 33782

Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com

DIRECT PUSH TECHNOLOGY QUOTE FORM

Date: 3/2/22

Unit Unit Rate Number of Units Extended Price whole day $1,700.00 1 $1,700.00 half day $1,375.00 1 $1,375.00 per foot $17.00 $0.00 each $95.00 3 $285.00 each $45.00 $0.00 each $20.00 16 $320.00 per well $110.00 2 $220.00 roundtrip $600.00 2 $1,200.00 per crew / per night $0.00 $0.00 each $65.00 2 $130.00 each $50.00 2 $100.00

$0.00

$0.00

$0.00

TOTAL QUOTE PRICE $5,330.00

Notes: 1. Includes expendables, tubing, points, liners, caps, plugs, saw cuts, development, standby time, steam cleaning decon, and grouting.

Project No.:

Subcontract Company Name: Preferred Drilling Solutions, Inc. (727) 561-7477

Subcontract Mailing Address: 8820 66th St, Pinellas Park, FL 33782

Signature and Title of Person Submitting Quote: ___________________________________Kevin Bonacum, Estimator Date: 3/2/22

Days to Complete Scope of Work: 1.5

Direct Push Daily Rate 1 - on-site day

Equipment Type: Geoprobe 8040DT, Geoprobe 3230DT

*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner

Other (specify)

Other (specify)

Other (specify)

Permits

DOT Approved 55-gal Drum

Per Diem Mobilization

DIRECT PUSH TECHNOLOGY

MISCELLANEOUS

Site Name and Location: Sargents One Hour Cleaners

Consultant Name: GHD

PROPOSED SCOPE OF WORK:

(1) 1" x 35' MW with 5' .010 prepacked screen, soil sampling as needed, pad and 8" manhole, drum any excess cuttings and development water

(1) 1" x 56' MW with 10' .010 prepacked screen, soil sampling as needed, pad and 8" manhole, drum any excess cuttings and development water

45 E Washington St, Orlando, FL

Well Completion (includes MH w/ cover, concrete pad, and locking well cap)

Well Riser (includes all materials) ID 1" 5' Length

Slotted PVC Well Screen (includes all materials) 5' Length Pack OD 3.5"

Pre-Packed Well Screen (includes all materials) ID 1" 5' Length Pack OD 3.5"

Auger Attachment, 2" Well Install

Direct Push Half-Day Rate 1 - on-site half day

GHD 3/1/2022

5904 Hampton Oaks Parkway PN220301-110600 Suite F Tampa, Florida 33610 Sergeants One Hour Cleaners

Brian Moore 45 East Washington Street brian.moore@ghd.com Orlando

813.335.2147 Florida

Cascade Rep Contact Information

Scope of Work

Quantity Unit Sales Price Subtotal Mobilization 1 Each 1,750.00$ 1,750.00$ Demobilization 1 Each 1,750.00$ 1,750.00$ DPT Rig and Crew Daily Rate (up to 10hrs onsite) 1 Days 2,250.00$ 2,250.00$ Per Diem and Lodging (per worker) 6 Man/Day 200.00$ 1,200.00$ Macrocore Liners 18 Feet 5.00$ 90.00$ 1" PVC Well Riser Installation 76 Feet 7.00$ 532.00$ 1"x5' Prepack Screens 3 Each 105.00$ 315.00$ Flush Mount Completion w/ 2'x2' pad 2 Each 250.00$ 500.00$ 55-Gallon DOT Drums 1 Each 70.00$ 70.00$ Skidsteer/Bobcat if needed Days 500.00$ Overtime (over 10hrs onsite) Hours 225.00$ State of Florida / Orange County Drilling Permits Each (at cost)

Pre-Tax Total

Tax Percentage

Taxes

Quote Total

Contact Name Project Address Email Project City Phone Project State

DPT drill with continuous macrocore sampling to 56' and 35'. Install 1" Sch40 PVC wells with prepack .010 slot screens (2 screens on 56' well, 1 screen on 35' well).

Complete with 8" flushmount and 2'x2' pad. Contain all waste in a 55-gallon drum. Drum will remain on site for disposal by others.

Cascade estimates 1 day to complete the project and 1 day of travel each way to mobilize/demobilize. All quantities are estimates. Actual accrued totals will be invoiced.

Description

$8,457.00

Account Name Bid Date Address Quote Number

Quote Revision Date

Bill To Account Project Zip

Project Name

Number

Prepared By Email wburdette@cascade-env.comWill Burdette, Southeast Region Estimator

This quote is based on information provided by you and is valid for 45 days from the bid date. Unless previously agreed, Cascade requires a 2-week notice prior to mobilization. Your firm is responsible for 1) Obtaining any site specific permits, 2) Locating and clearly marking underground installations or utilities, 3) Furnishing dig

Alert numbers at least three working days prior to scheduled start date and proof of private locating services, 4) Obtaining access to site with no overhead wires within 20' of the holes. Cascade Drilling shall not be responsible for damages to underground improvements not clearly and accurately marked. If bedrock, cobbles, flowing sands or other adverse or unsafe drilling conditions are encountered, drilling may continue on a time and materials basis or be terminated at the discretion of Cascade.

Additional costs may apply if scope is significantly changed. Well development by others may void some or all of Cascade warranties of workmanship and materials.

Prices assume standard labor rates and no work hour restrictions.

South Carolina: 905 SOUTH MAIN ST, NEW ELLENTON SC 29809 ♦ (803) 617-8534

$8,457.00

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

April 15, 2021

Re: Non-Hazardous Drum Disposal Quote – South and Central Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in south and central

Florida will be $100.00 per drum, total, for both transportation and disposal.

Pricing for the Florida Keys will be quoted separately on a case-by-case basis.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png

$95.00 per drum plus $150.00 stop charge Have a great day

Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.

P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com

From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami

Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks

Brian Moore, PE

GHD

Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect

WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION

mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx

Please consider our environment before printing this email

CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.

This e-mail has been scanned for viruses

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/8/22 Mon 3/21/22

2 Subtask 1: Project Management

78 days Tue 3/22/22 Thu 7/7/22

3 Subtask 2: Groundwater Monitoring

78 days Tue 3/22/22 Thu 7/7/22

4 Right of Way Permitting 6 wks Tue 3/22/22 Mon 5/2/22

5 Field Work Preparation 2 wks Mon 5/2/22 Fri 5/13/22

6 Well Installation 1.5 days Mon 5/16/22Tue 5/17/22

7 Groundwater Sampling 2 days Wed 5/18/22Thu 5/19/22

8 Groundwater Monitoring Report

6 wks Fri 5/27/22 Thu 7/7/22

2/27 3/6 3/13 3/20 March

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009A a the Sargents One Hour Cleaners (formerly) site located in Orlando, Orange County

Project: TA_009A Date: Tue 3/8/22

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/8/22 Mon 3/21/22

2 Subtask 1: Project Management

78 days Tue 3/22/22 Thu 7/7/22

3 Subtask 2: Groundwater Monitoring

78 days Tue 3/22/22 Thu 7/7/22

4 Right of Way Permitting 6 wks Tue 3/22/22 Mon 5/2/22

5 Field Work Preparation 2 wks Mon 5/2/22 Fri 5/13/22

6 Well Installation 1.5 days Mon 5/16/22Tue 5/17/22

7 Groundwater Sampling 2 days Wed 5/18/22Thu 5/19/22

8 Groundwater Monitoring Report

6 wks Fri 5/27/22 Thu 7/7/22

3/27 4/3 4/10 4/17 April

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009A a the Sargents One Hour Cleaners (formerly) site located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/8/22 Mon 3/21/22

2 Subtask 1: Project Management

78 days Tue 3/22/22 Thu 7/7/22

3 Subtask 2: Groundwater Monitoring

78 days Tue 3/22/22 Thu 7/7/22

4 Right of Way Permitting 6 wks Tue 3/22/22 Mon 5/2/22

5 Field Work Preparation 2 wks Mon 5/2/22 Fri 5/13/22

6 Well Installation 1.5 days Mon 5/16/22Tue 5/17/22

7 Groundwater Sampling 2 days Wed 5/18/22Thu 5/19/22

8 Groundwater Monitoring Report

6 wks Fri 5/27/22 Thu 7/7/22

Ed Siersema

Ed Siersema

Derek Barr

Derek

4/24 5/1 5/8 5/15 May

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009A a the Sargents One Hour Cleaners (formerly) site located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/8/22 Mon 3/21/22

2 Subtask 1: Project Management

78 days Tue 3/22/22 Thu 7/7/22

3 Subtask 2: Groundwater Monitoring

78 days Tue 3/22/22 Thu 7/7/22

4 Right of Way Permitting 6 wks Tue 3/22/22 Mon 5/2/22

5 Field Work Preparation 2 wks Mon 5/2/22 Fri 5/13/22

6 Well Installation 1.5 days Mon 5/16/22Tue 5/17/22

7 Groundwater Sampling 2 days Wed 5/18/22Thu 5/19/22

8 Groundwater Monitoring Report

6 wks Fri 5/27/22 Thu 7/7/22 arry rek Barry,Skylar Albritton

5/22 5/29 6/5 6/12 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009A a the Sargents One Hour Cleaners (formerly) site located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/8/22 Mon 3/21/22

2 Subtask 1: Project Management

78 days Tue 3/22/22 Thu 7/7/22

3 Subtask 2: Groundwater Monitoring

78 days Tue 3/22/22 Thu 7/7/22

4 Right of Way Permitting 6 wks Tue 3/22/22 Mon 5/2/22

5 Field Work Preparation 2 wks Mon 5/2/22 Fri 5/13/22

6 Well Installation 1.5 days Mon 5/16/22Tue 5/17/22

7 Groundwater Sampling 2 days Wed 5/18/22Thu 5/19/22

8 Groundwater Monitoring Report

6 wks Fri 5/27/22 Thu 7/7/22 Jeremy Hess,Ed Sierse

6/19 6/26 7/3 7/10 July

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009A a the Sargents One Hour Cleaners (formerly) site located in Orlando, Orange County

File details come from the government source that posted it. Updated .