This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (DEP) to GHD Services, Inc. for operations and maintenance activities at the Sunshine Cleaners site located at 124 W Granada Boulevard, Ormond Beach, Volusia County, Florida. The task assignment is identified as DC022C under master Contract HW684, with a completion date of August 27, 2025. Nicole Knutson serves as the Department Project Manager, while Brian Moore represents GHD Services, Inc. as the contractor's project manager.
The task encompasses twelve months of Soil Vapor Extraction (SVE) system operations and maintenance, divided into five subtasks. Subtask 1 covers overall project management; Subtask 2 includes six months of O&M activities with monthly site visits, operational data recording, quarterly vapor sampling, and a Remedial Action Status Report due November 22, 2024; Subtask 3 provides utilities reimbursement of $800 per month plus a $120 handling fee for six months, invoiced by December 20, 2024; Subtask 4 includes an additional six months of O&M with groundwater sampling at twelve monitoring wells and a final RASR due May 22, 2025; and Subtask 5 provides six months of utilities reimbursement due June 27, 2025. The total task value is $39,588.77, consisting of $29,988.77 in fixed unit rate costs and $9,600.00 in cost reimbursement. Subcontractor Erwin Remediation is responsible for IDW (Investigation Derived Waste) transportation and disposal at a cost of $125 per drum.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW684
DC022C August 27, 2025
GHD Services, Inc. will complete O&M activities at Sunshine Cleaners.
Nicole Knutson 850-245-8763 GHD Services, Inc.
Brian Moore 813-257-0658
ERIC_5524
124 W Granada Blvd, Ormond Beach, Volusia County
Sunshine Cleaners
$ 29,988.77
$ 9,600.00
$ 39,588.77
Scope of Work
GHD Services, Inc.
Brian Moore Digitally signed by Brian Moore Date: 2024.02.29 13:42:03 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.02.29 11:35:17 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: ERIC_5524
Sunshine Cleaners
FROM: Nicole Knutson, Project Manager
SUBJECT: Negotiation Summary
HW684 DC022C
DATE: February 28, 2024
GHD will perform O&M activities at Sunshine Cleaners, as detailed in the February 28, 2024 proposal. Erwin Remediation will complete IDW transportation and disposal.
Total task amount is $39,588.77. GHD’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is June 27, 2025.
Task completion date is August 27, 2025.
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Sunshine Cleaners SUBTASK 2: O&M (6 months)
DATE: 2/28/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer JH Conclusions/Recommendations for RASR 1
Project Manager JM Prepare field scope of work (0.5 hr / month) 3
Project Manager JM Determine flow rates and operating conditons based on field data sheets (0.5 hr / month) 3
Project Manager JM Project Background (RASR) 1
Project Manager JM Run time and troubleshooting details - RASR 2
Project Manager JM Operating conditions (flow rates, vacuums, roi, etc.) - RASR 2
Project Manager JM Soil gas analytical results/influent - RASR 2
Project Manager JM Laboratory data validation - RASR 1.5 Project Manager JM Conclusions/recommendations 1.5
Professional Scientist DB mob/demob from Orlando (6 days) 12 Professional Scientist DB Monthly O&M (4 hours per visit) 24
CADD Design PM Groundwater Flow Figures (shallow/deep) 2 CADD Design PM Groundwater Analytical Figure 2
Administrative Assistant JJ Data Entry (2 SVE samples and field data) (0.25/month) 3
Administrative Assistant JJ Remedial Summary Tables 1 Administrative Assistant JJ Publish RASR 2
TOTAL LABOR 63
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 6 $720.00
TOTAL VEHICLE $720.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 (influent quarterly) $200.00 2 $400.00
Shipping (Next Day - small Cooler) $110.00 2 $220.00
TOTAL LAB $620.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 6 $240.00 air sampling pump $27.00 day 2 $54.00 vacuum gauges $19.00 day 6 $114.00 summa canister $33.00 each 2 $66.00 anemometer $33.00 day 6 $198.00
OVA $125.00 day 2 $250.00
TOTAL EQUIPMENT $922.00
FINAL --7/24/96
SUBTASK 3: Utilities (6 months)
DATE: 2/28/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
FPL Electricity $800.00 month 6 $4,800.00
Handling Fee $20.00 month 6 $120.00
TOTAL $4,920.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
SUBTASK 5: O&M (6 months)
DATE: 2/28/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer JH Conclusions/Recommendations for RASR 1
Project Manager JM Prepare field scope of work (0.5 hr / month) 3 Project Manager JM Determine flow rates and operating conditons based on field data sheets (0.5 hr / month) 3 Project Manager JM Project Background (RASR) 1 Project Manager JM Run time and troubleshooting details - RASR 2 Project Manager JM Operating conditions (flow rates, vacuums, roi, etc.) - RASR 2 Project Manager JM Soil gas analytical results/influent - RASR 2 Project Manager JM Groundwater Sampling Procedures (RASR) 2 Project Manager JM Groundwater Flow shallow/deep (RASR) 2 Project Manager JM Groundwater field parameters shallow/deep (RASR) 2 Project Manager JM Groundwater analytical shallow/deep (RASR) 2 Project Manager JM Laboratory data validation - RASR 1.5 Project Manager JM Conclusions/recommendations 1.5
Professional Scientist DB mob/demob from Orlando (7 days) 14 Professional Scientist DB Monthly O&M (4 hours per visit) 24 Professional Scientist DB Depth to water measurements (all wells - 30 total)) 4 Professional Scientist DB Groundwater Sampling (2 wells) 3
Sr Technician SA mob/demob from Tampa 4.5 Sr Technician SA Depth to water measurements (all wells) 4 Sr Technician SA Groundwater Sampling (10 wells) 15
23.5
CADD Design PM Groundwater Flow Figures (shallow/deep) 2 CADD Design PM Groundwater Analytical Figure 2
Administrative Assistant JJ Data Entry (2 SVE samples, 12 gw samples, wls, field data) (0.25/month) 3 Administrative Assistant JJ Remedial Summary Tables 2 Administrative Assistant JJ Publish RASR 2
TOTAL LABOR 104.5
VEHICLE TYPE RATE UNIT USEAGE
Professional Scientist (DB) Company Truck $120.00 day 7 $840.00 Sr Technician (SA) Company Truck $120.00 day 2 $240.00
TOTAL VEHICLE $1,080.00
PER DIEM STAFF RATE UNIT USEAGE
Sr tech (SA) Hotel $150.00 night 1 $150.00 Sr tech (SA) Per Diem $36.00 day 2 $72.00
TOTAL PER DIEM $222.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Disposal $125.00 drum 1 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 (influent quarterly) $200.00 9 $1,800.00 VOHs EPA Method 8260 $73.00 12 $876.00
Shipping (Next Day - small Cooler) $110.00 2 $220.00 MW001, MW002, MW018R, MW020, MW025, MW032, MW034, MW036, MW037, MW042, MW043, and MW044 Shipping Large Cooler (2 day) $70.00 1 $70.00
Ice $6.50 1 $6.50
TOTAL LAB $2,972.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 7 $280.00 air sampling pump $27.00 day 2 $54.00 vacuum gauges $19.00 day 6 $114.00 summa canister $33.00 each 9 $297.00 anemometer $33.00 day 6 $198.00 OVA $125.00 day 2 $250.00
Professional Scientist Groundwater Sampling Kit $290.00 day 1 $290.00 Sr Technician Groundwater Sampling Kit $290.00 day 2 $580.00
Poly Tubing $0.30 ft 447 $134.10 Silicon Tubing $3.00 ft 12 $36.00
Drum $100.00 each 1 $100.00
TOTAL EQUIPMENT $2,333.10
SUBTASK 5: Utilities (6 months)
DATE: 2/28/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
FPL Electricity $800.00 month 6 $4,800.00
Handling Fee $20.00 month 6 $120.00
TOTAL $4,920.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
COST PROPOSAL FOR TASK DC022C
< Sunshine Cleaners, ERIC_5524>
SVE System Operations and Maintenance (12 months)
1. INTRODUCTION:
A Soil Vapor Extraction (SVE) system was installed and is currently operational at the Sunshine Cleaners site located in Ormond Beach, Volusia County. Task DC022C includes 12 additional months of operations and maintenance of the SVE system. It is anticipated that system shutdown procedures will be recommended at some point during the next 12 months of O&M.
Subtask 1 Project Management Subtask 1 includes all tasks associated with managing the operations and maintenance of an SVE system at the Sunshine Cleaners facility.
Subtask 2 O&M (6 months) As part of subtask 2, monthly site visits will be conducted to verify system operation and record operational data including vacuum, flows, and water levels. In addition, during monthly site visits, operation flow patterns in the subsurface will be adjusted to maximize mass recovery. OVA readings and vapor influent sampling will be conducted quarterly.
Groundwater depth to water measurements will also be gathered at monitor wells MW001 and MW006 on a monthly basis.
At the end of 6 months of operations and upon receipt of laboratory analytical data, GHD will prepare a Remedial Action Status Report (RASR). The RASR will include a discussion of operational performance conditions as well as laboratory analytical results for soil vapor sampling. The RASR will also include conclusions and recommendations.
Subtask 3: Utilities (6 months) Subtask 3 includes utility reimbursement charges ($800/month) for electrical service for 6 months.
Subtask 4 O&M (6 months) As part of subtask 4, monthly site visits will be conducted to verify system operation and record operational data including vacuum, flows, and water levels. In addition, during monthly site visits, operation flow patterns in the subsurface will be adjusted to maximize mass recovery. OVA readings and vapor influent sampling will be conducted quarterly.
Groundwater depth to water measurements will also be gathered at monitor wells MW001 and MW006 on a monthly basis.
In addition, GHD also recommends groundwater sampling during the 5th month of operations to evaluate groundwater quality conditions. Groundwater sampling will be conducted in accordance with the approved ISR Plan at monitoring wells MW001, MW002, MW018, MW020, MW025, MW032, MW034, MW036, MW037, MW042, MW043, and MW044. Prior to groundwater sampling, depth to water measurements will be gathered from all available monitoring wells. Groundwater sampling will be conducted in general accordance with FDEP SOPs and groundwater samples will be submitted to a State certified laboratory for volatile organic halocarbon analysis by EPA Method 8260.
At the end of 6 months of operations and upon receipt of laboratory analytical data, GHD will prepare a Remedial Action Status Report (RASR). The RASR will include a discussion of operational performance conditions as well as laboratory analytical results for soil vapor sampling. The RASR will also include a summary of groundwater sampling methodology and results. The RASR will also include conclusions and recommendations.
Subtask 5: Utilities (6 months) Subtask 3 includes utility reimbursement charges ($800/month) for electrical service for 6 months.
UTILITIES INCLUDED IN SCOPE OF WORK: Yes No List (Electric, Phone, Sewer): _Electric, Phone, sewer___________________________ Number of months: _6_________ Estimated per month cost: $____$800_________ Handling fee: $____20__________ Hook up fees: $______________
Deliverables:
Deliverable Deliverable Due Date
Remedial Action Status Report 11/22/24
Paid Utilities (6 Months) includes cost reimbursement of $800 per month and handling fee of $120 (6 months)
12/20/24
Remedial Action Status Report 5/22/25
Paid Utilities (6 Months) includes cost reimbursement of $800 per month and handling fee of $120 (6 months)
6/27/25
From: Craig Burns To: Brian Moore Subject: GHD_IDW Drum Rates FL Date: Tuesday, June 28, 2022 10:26:46 AM Attachments: image001.png image002.png image003.png image004.png image005.png GHD Drum Rates FL 2022.pdf
Here you go Brian. I do this for a lot of engineering/consulting firms.
Be aware of the low stop less than 6 drums at $50/flat Be aware of the 10% to the total cost for FSC (implemented April 15).
Pass around the GHD Florida offices
From: Brian Moore <Brian.Moore@ghd.com> Sent: Tuesday, June 28, 2022 10:05 AM To: Craig Burns <cburns@clarkenvironmental.com> Subject: IDW Drums
Craig, Is it possible to provide a generic quote for IDW water disposal.
Assumption is non-haz with necessary analytical Maybe provide a range of locations
South florida or central florida, or both?
Thanks in advance
We have many sites that we generate 1 gw drum of IDW and would like to streamline the vendor coordination
BRIAN MOORE PE
GHD
Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA
O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com
The Power of Commitment
Connect
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
File details come from the government source that posted it. Updated .