CN-370000-HW684-DC022A.pdf
PDF 2 MB Posted
- Contract number
- HW684
- Issued by
- Florida
About this file
This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to GHD Services, Inc. for operations and maintenance services at the Sunshine Cleaners site located at 124 W Granada Boulevard, Ormond Beach, Volusia County, Florida. The task assignment is numbered DC022A under Contract HW684 and was executed in June 2022 with a completion date of October 27, 2023. The department project manager is Kevin Kane, and the contractor's project manager is Brian Moore.
The contract encompasses 12 months of soil vapor extraction (SVE) system operations and maintenance divided into five subtasks: Project Management (13% of direct labor costs); Semi-Annual O&M for six months including monthly site visits, groundwater sampling at 12 monitor wells, OVA readings, and a semi-annual summary report; Utilities for six months at $700 per month plus $20 handling fee per month; Semi-Annual O&M for the second six months with similar activities and a final Remedial Action Status Report; and second six-month Utilities at identical rates. The total task assignment value is $30,601.04, comprised of $22,201.04 in fixed unit rate costs and $8,400.00 in cost reimbursement for utilities. Deliverables include a Semi-Annual O&M Summary due January 5, 2023; Paid Utility Invoices due January 13, 2023 and July 24, 2023; and a Remedial Action Status Report due July 13, 2023. The payment structure is broken into five invoiceable subtasks ranging from $4,320.00 to $11,814.92, with invoicing contingent upon completion and FDEP approval of deliverables.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC022A Completion October 27, 2023
GHD Services, Inc. will conduct 12 months of operations & maintenance of the soil vapor extraction system staged at the Sunshine Cleaners site located in Ormond Beach, FL. All work will be conducted in accordance with the scope of work and cost proposal submitted on June 2, 2022.
The payment of utility invoices associated with O&M activities under this Task Assignment is the only portion of this Task Assignment which is Cost Reimbursement.
Kevin Kane (850) 245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore (813) 257-0658
ERIC_5524
124 W Granada Blvd, Ormond Beach, Volusia County
Sunshine Cleaners
✔ $ 22,201.04 ✔ $ 8,400.00
$ 30,601.04
Scope of Work
Brian Moore
Project Manager
Brian Moore Digitally signed by Brian Moore Date: 2022.06.28 16:48:27 -04'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.06.28 16:18:46 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Semi-Annual O&M Summary 01/05/2023
Paid Utility Invoices (first two quarters) 01/13/2023
Remedial Action Status Report 07/13/2023
Paid Utility Invoices (second two quarters) 07/24/2023
Subtask 2: Upon completion of 6 months O&M activities and FDEP approval of Semi-Annual O&M Summary $ 11,814.92
Subtask 3: Upon submittal of Paid Utility Invoices (first two quarters):
Utilities (Cost Plus Fixed Fee) not to exceed $4,200.00 Utilities Handling Fee: $120.00
$ 4,320.00
Subtasks 1 & 4: Upon completion of 6 months O&M activities and FDEP approval of Remedial Action Status Report + Project Management $ 10,146.12
Subtask 5: Upon submittal of Paid Utility Invoices (second two quarters):
Utilities (Cost Plus Fixed Fee) not to exceed $4,200.00 Utilities Handling Fee: $120.00
$ 4,320.00
$ 30,601.04
HW684
DC022A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
TO: HW684 Contract File Michael the Cleaner Ormond Beach, Volusia County
ERIC_5524
FROM: Kevin Kane, Contract Manager
DATE: June 27, 2022
SUBJECT: Task Assignment Summary
HW684 DC022A
Operations & Maintenance
GHD Services, Inc. (GHD) will conduct 12 months of operations & maintenance (O&M) of the soil vapor extraction system present on site. Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: O&M (6 months) As part of Subtask 2, monthly site visits will be conducted to verify system operation and record operational data including vacuum, flows, and water levels. During monthly site visits, operation flow patterns in the subsurface will be adjusted to maximize mass recovery. OVA readings and vapor influent sampling will be conducted quarterly.
Groundwater depth to water measurements will also be gathered at monitor wells MW001 and MW006 on a monthly basis. In accordance with the approved ISRP, annual groundwater sampling will be conducted under this subtask. Prior to sampling, depth to water measurements will be gathered at all site monitor wells (30 total). Following depth to water measurements, groundwater sampling will be completed at monitor wells
MW001, MW002, MW018, MW020, MW025, MW032, MW034, MW036, MW037,
MW042, MW043, and MW044. Groundwater sampling will be conducted in accordance with FDEP Standard Operating Procedures and all groundwater samples will be analyzed for the presence of volatile organic halocarbons (VOHs). At the end of 6 months of operations and upon receipt of groundwater data, GHD will prepare a brief Semi-Annual O&M Summary that includes a discussion of operational performance and recommendations.
Subtask 3: Utilities (6 months) Subtask 3 includes utility reimbursement charges ($700.00/month) for electrical service for 6 months, as well as associated utility handling fees ($20.00/month)
Subtask 4: O&M (6 months) As part of Subtask 4, monthly site visits will be conducted to verify system operation and record operational data including vacuum, flows, and water levels. In addition, during monthly site visits, operation flow patterns in the subsurface will be adjusted to maximize mass recovery. OVA readings and vapor influent sampling will be conducted quarterly.
Groundwater depth to water measurements will also be gathered at monitor wells MW001 and MW006 on a monthly basis.
Subtask 5: Utilities (6 months) Subtask 5 includes utility reimbursement charges ($700.00/month) for electrical service for 6 months, as well as associated utility handling fees ($20.00/month)
GHD and the FDEP confirmed on June 28, 2022, that an Access Agreement with the current real property owner of the aforementioned site has been executed.
Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is July 24, 2023, and the completion date for the task assignment is October 27, 2023.
The final cost total for Task Assignment DC022A is $30,601.04.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 06/28/22
Task #: DC022A SubTask 1 Project Management SubTask 6
Site: Sunshine Cleaners SubTask 2 O&M (semi-annual) SubTask 7
Activity/Phase: O&M SubTask 3 Utilities SubTask 8
Project Manager: Brian Moore, PE SubTask 4 O&M (semi-annual) SubTask 9
SubTask 5 Utilities SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.12 Project Manager JM 14.80 14.8 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$46.33 Sr Professional Engineer JH 38.50 17.50 0.00 21.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$43.28 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 2.00 1.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 17.00 17.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 100.00 58.00 0.00 42.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 4.00 0.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 13.00 7.00 0.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 189.30 14.80 100.50 0.00 74.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $5,170.15 $594.80 $2,483.60 $0.00 $2,091.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $6,710.85 $772.05 $3,223.71 $0.00 $2,715.09 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $1,954.31 $224.83 $938.80 $0.00 $790.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $13,835.31 $1,591.68 $6,646.11 $0.00 $5,597.52 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $1,680.00 $960.00 $0.00 $720.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 1
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 06/28/22
Task #: DC022A SubTask 1 Project Management SubTask 6
Site: Sunshine Cleaners SubTask 2 O&M (semi-annual) SubTask 7
Activity/Phase: O&M SubTask 3 Utilities SubTask 8
Project Manager: Brian Moore, PE SubTask 4 O&M (semi-annual) SubTask 9
SubTask 5 Utilities SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,680.00 $960.00 $0.00 $720.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $8,400.00 $0.00 $4,200.00 $0.00 $4,200.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $8,510.00 $110.00 $4,200.00 $0.00 $4,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $251.00 $11.00 $120.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $8,761.00 $121.00 $4,320.00 $0.00 $4,320.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,749.00 $1,349.00 $0.00 $400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $220.00 $0.00 $0.00 $220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $296.50 $296.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,265.50 $1,645.50 $0.00 $620.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $520.00 $280.00 $0.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $2,155.70 $1,497.70 $0.00 $658.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $2,675.70 $1,777.70 $0.00 $898.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $29,217.51 $1,591.68 $11,150.31 $4,320.00 $7,835.52 $4,320.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,383.53 $159.17 $664.61 $0.00 $559.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $30,601.04 $1,750.85 $11,814.92 $4,320.00 $8,395.27 $4,320.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Sunshine Cleaners SUBTASK 2: O&M (semi-annual)
DATE: 06/28/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager JM Conclusions/Recommendations 1
Professional Engineer JH Prepare field scope of work (0.5 hr / month) 3 Professional Engineer JH Field sampling SOW (groundwater) 1 Professional Engineer JH QA/QC field and laboratory data (3 data sets) 1.5 Professional Engineer JH Determine flow rates and operating conditons based on field data sheets (0.25 hr / month) 3 Professional Engineer JH Prepare semi-annual summary (brief letter report with recommendations) 8 Professional Engineer JH Characterization and waste profile for transportation and dispolsal of IDW Drums(s) 1
17.5
Senior Technician SC mob/demob from Jax (7 days) 21 Senior Technician SC Monthly O&M (4 hours per visit) 24 Senior Technician SC Water Levels (all wells - 32) 4 Senior Technician SC Groundwater Sampling (6 wells) 9
Senior Technician SA mob/demob from Tampa (1 day) 4 Senior Technician SA Water Levels (all wells - 32) 4 Senior Technician SA Groundwater Sampling (6 wells) 9
Administrative Assistant DA Data Entry (2 SVE samples, field data, wl, and 12 gw samples) (0.25/month) 4 Administrative Assistant DA Remedial Summary Tables (update with O&M and gw data) 2 Administrative Assistant DA Publish semi-annual update 1
TOTAL LABOR 100.5
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 8 $960.00
TOTAL VEHICLE $960.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Disposal 1 drum $110 $110.00
TOTAL $110.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs EPA 8260 $73.00 13 $949.00 TO-15 (influent quarterly) $200.00 2 $400.00
Shipping (Next Day - small Cooler) $110.00 2 $220.00 Shipping Large cooler (2 day) $70.00 1 $70.00
Ice $6.50 1 $6.50
TOTAL LAB $1,645.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 7 $280.00
Equipment (Analytical Related) air sampling pump $27.00 day 2 $54.00 vacuum gauges $19.00 day 6 $114.00 tedlar bags $20.00 each 2 $40.00 anemometer $33.00 day 6 $198.00
OVA $125.00 day 2 $250.00 Groundwater Sampling Kit $290.00 day 2 $580.00 Poly Tubing (HDPE) $0.30 ft 419 $125.70 Drum $100.00 drum 1 $100.00 Silicon Tubing $3.00 ft 12 $36.00
Equipment (Other) $0.00
TOTAL EQUIPMENT $1,777.70
FINAL --7/24/96
SUBTASK 3: Utilities
DATE: 06/28/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
FPL Electricity $700.00 month 6 $4,200.00 Handling Fee $20.00 month 6 $120.00
TOTAL $4,320.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$0.00 $0.00 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Equipment (Analytical Related)
Equipment (Other) $0.00
TOTAL EQUIPMENT $0.00
SUBTASK 4: O&M (semi-annual)
DATE: 06/28/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager JM Conclusions/Recommendations for RASR 1
Professional Engineer JH Prepare field scope of work (0.5 hr / month) 3 Professional Engineer JH Determine flow rates and operating conditons based on field data sheets (0.25 hr / month) 1.5 Professional Geologist JH Project Background (RASR) 1 Professional Geologist JH Groundwater Sampling Methods (RASR) 1 Professional Geologist JH Groundwater flow evaluation (shallow/deep) - (RASR) 2 Professional Geologist JH Water Quality Parameter Summary - (RASR) 1 Professional Geologist JH Groundwater Analtycial Results (shallow/deep) - (RASR) 2 Professional Geologist JH QA/QC Laboratory Data (RASR) 1.5 Professional Engineer JH Prepare annual RASR including summary of operating conditions and conclusions and recommen 8
Senior Technician SC mob/demob from Jax (6 days) 18 Senior Technician SC Monthly O&M (4 hours per visit) 24
CADD Design PM Groundwater Flow Figures (shallow/deep) 2 CADD Design PM Groundwater Analytical Figure 2
Administrative Assistant DA Data Entry (2 SVE samples and field data) (0.25/month) 3 Administrative Assistant DA Remedial Summary Tables 1 Administrative Assistant DA Publish RASR 2
TOTAL LABOR 74
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 6 $720.00
TOTAL VEHICLE $720.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 (influent quarterly) $200.00 2 $400.00 Shipping (Next Day - small Cooler) $110.00 2 $220.00
TOTAL LAB $620.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 6 $240.00
Equipment (Analytical Related) $2.00 air sampling pump $27.00 day 2 $54.00 vacuum gauges $19.00 day 6 $114.00 tedlar bags $20.00 each 2 $40.00 anemometer $33.00 day 6 $198.00
OVA $125.00 day 2 $250.00
Equipment (Other) $0.00
TOTAL EQUIPMENT $898.00
SUBTASK 5: Utilities
DATE: 06/28/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
FPL Electricity $700.00 month 6 $4,200.00 Handling Fee $20.00 month 6 $120.00
TOTAL $4,320.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$0.00 $0.00 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Equipment (Analytical Related)
Equipment (Other) $0.00
TOTAL EQUIPMENT $0.00
COST PROPOSAL FOR TASK DC022A
< Sunshine Cleaners, ERIC_5524>
SVE System Operations and Maintenance (12 months)
1. INTRODUCTION:
Following soil assessment, GHD installed 7 SVE wells and completed underground piping for the SVE system installation at the Sunshine Cleaners site located in Ormond Beach, Volusia County. The system was activated following ISRP approval and it is currently operational.
Task DC022A includes 12 additional months of operations and maintenance of the SVE system
Subtask 1 Project Management Sub Task 1 includes all tasks associated with managing the operations and maintenance of an SVE system at the Sunshine Cleaners facility.
Subtask 2 O&M (6 months) As part of subtask 2, monthly site visits will be conducted to verify system operation and record operational data including vacuum, flows, and water levels. In addition, during monthly site visits, operation flow patterns in the subsurface will be adjusted to maximize mass recovery. OVA readings and vapor influent sampling will be conducted quarterly.
Groundwater depth to water measurements will also be gathered at monitor wells MW001 and MW006 on a monthly basis.
As part of Subtask 2, groundwater sampling will be conducted. In accordance with the approved ISRP, annual groundwater sampling will be conducted. Prior to sampling, depth to water measurements will be gathered at all site monitor wells (30 total). Following depth to water measurements, groundwater sampling will be completed at monitor wells MW001, MW002, MW018, MW020, MW025, MW032, MW034, MW036, MW037, MW042, MW043, and MW044. Groundwater sampling will be conducted in accordance with FDEP Standard Operating Procedures and all groundwater samples will be analyzed for the presence of volatile organic halocarbons (VOHs).
At the end of 6 months of operations and upon receipt of groundwater data, GHD will prepare a brief email summary that includes a discussion of operational performance and recommendations.
Subtask 3: Utilities (6 months) Subtask 3 includes utility reimbursement charges ($700/month) for electrical service for 6 months.
UTILITIES INCLUDED IN SCOPE OF WORK: Yes No List (Electric, Phone, Sewer): _Electric, Phone, sewer___________________________ Number of months: _6_________ Estimated per month cost: $____$700_________ Handling fee: $____20__________
Hook up fees: $______________
Subtask 4 O&M (6 months) As part of subtask 2, monthly site visits will be conducted to verify system operation and record operational data including vacuum, flows, and water levels. In addition, during monthly site visits, operation flow patterns in the subsurface will be adjusted to maximize mass recovery. OVA readings and vapor influent sampling will be conducted quarterly.
Groundwater depth to water measurements will also be gathered at monitor wells MW001 and MW006 on a monthly basis.
At the end of 12 months of operations GHD will prepare a Remedial Action Status Report (RASR). The RASR will include a summary of operational data and groundwater sampling and results. The RASR will include a discussion of operational performance and recommendations for additional monitoring/remediation.
Subtask 5: Utilities (6 months) Subtask 3 includes utility reimbursement charges ($700/month) for electrical service for 6 months.
UTILITIES INCLUDED IN SCOPE OF WORK: Yes No List (Electric, Phone, Sewer): _Electric, Phone, sewer___________________________ Number of months: _6_________ Estimated per month cost: $____$700_________ Handling fee: $____20__________ Hook up fees: $______________
REPORTING INCLUDED IN SCOPE OF WORK: Yes No Indicate number of each (i.e. Startup-1, Quarterly-2, Annual-1) Baseline/Startup: ________ Quarterly: ____________ Monthly: ___________ Semi-Annually: Semi-Annual Summary Annual: _____RASR_______ Completion Report: ________________
Deliverables:
Deliverable Deliverable Due Date
Semi-Annual Email Summary 1/5/23
Paid Utilities (6 Months) includes cost reimbursement of $700 per month and handling fee of $120 (6 months) 1/13/23
Remedial Action Status Report 7/13/23
Paid Utilities (6 Months) includes cost reimbursement of $700 per month and handling fee of $120 (6 months) 7/24/23
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway – Suite F
Tampa, FL 33610
May 23, 2022
Re: Transportation and Disposal of Non-Hazardous Soil and Water – Florida
Mr. Moore:
The price for disposal of drums of non-hazardous soil or groundwater located in the State of Florida will be $110.00 per drum, for both transportation and disposal.
This pricing is valid for all regions in the State of Florida except for the Florida Keys.
Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
This quote is valid for 180 days.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png
$95.00 per drum plus $150.00 stop charge Have a great day
Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.
P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com
From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami
Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks
Brian Moore, PE
GHD
Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect
WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION
mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
This e-mail has been scanned for viruses
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Thu 6/2/22 Wed 6/15/22 2 Subtask 1: Project Managemen Thu 6/16/22 3 Subtask 2: Semi‐Annual O&M 146 days Thu 6/16/22 Thu 1/5/23 4 Field Work Preparation 2 wks Thu 6/16/22 Wed 6/29/22 5 O&M Site Visit 1 day Thu 6/30/22 Thu 6/30/22 6 O&M Site Visit (vapor sampli 1 day Fri 7/29/22 Fri 7/29/22 7 O&M Site Visit 1 day Mon 8/29/22 Mon 8/29/22 8 O&M Site Visit 1 day Thu 9/29/22 Thu 9/29/22 9 Groundwater Sampling 1 day Fri 10/21/22 Fri 10/21/22 10 O&M Site Visit (vapor sampli 1 day Fri 10/28/22 Fri 10/28/22 11 O&M Site Visit 1 day Mon 11/28/22 Mon 11/28/2 12 Semi‐Annual Update 5 wks Fri 12/2/22 Thu 1/5/23 13 Subtask 3: Utilities 6.6 mons Wed 6/1/22 Thu 12/1/22 14 Subtask 4: Semi‐Annual O&M 161 days Thu 12/1/22 Thu 7/13/23 15 Field Work Preparation 2 wks Thu 12/1/22 Wed 12/14/2 16 O&M Site Visit 1 day Wed 12/28/22 Wed 12/28/2 17 O&M Site Visit (vapor sampli 1 day Fri 1/27/23 Fri 1/27/23 18 O&M Site Visit 1 day Mon 2/27/23 Mon 2/27/23 19 O&M Site Visit 1 day Mon 3/27/23 Mon 3/27/23 20 O&M Site Visit (vapor sampli 1 day Thu 4/27/23 Thu 4/27/23 21 O&M Site Visit 1 day Fri 5/26/23 Fri 5/26/23 22 Remedial Action Status Repo 6 wks Fri 6/2/23 Thu 7/13/23 23 Subtask 5: Utilities 6.6 mons Thu 12/1/22 Fri 6/2/23
Jeremy Hess
Steven Custer Steven
5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 June July August
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC022A at the Sunshine Cleaners facility located in Ormond Beach, Volusia County
Project: TA_022A Date: Thu 6/2/22
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Thu 6/2/22 Wed 6/15/22 2 Subtask 1: Project Managemen Thu 6/16/22 3 Subtask 2: Semi‐Annual O&M 146 days Thu 6/16/22 Thu 1/5/23 4 Field Work Preparation 2 wks Thu 6/16/22 Wed 6/29/22 5 O&M Site Visit 1 day Thu 6/30/22 Thu 6/30/22 6 O&M Site Visit (vapor sampli 1 day Fri 7/29/22 Fri 7/29/22 7 O&M Site Visit 1 day Mon 8/29/22 Mon 8/29/22 8 O&M Site Visit 1 day Thu 9/29/22 Thu 9/29/22 9 Groundwater Sampling 1 day Fri 10/21/22 Fri 10/21/22 10 O&M Site Visit (vapor sampli 1 day Fri 10/28/22 Fri 10/28/22 11 O&M Site Visit 1 day Mon 11/28/22 Mon 11/28/2 12 Semi‐Annual Update 5 wks Fri 12/2/22 Thu 1/5/23 13 Subtask 3: Utilities 6.6 mons Wed 6/1/22 Thu 12/1/22 14 Subtask 4: Semi‐Annual O&M 161 days Thu 12/1/22 Thu 7/13/23 15 Field Work Preparation 2 wks Thu 12/1/22 Wed 12/14/2 16 O&M Site Visit 1 day Wed 12/28/22 Wed 12/28/2 17 O&M Site Visit (vapor sampli 1 day Fri 1/27/23 Fri 1/27/23 18 O&M Site Visit 1 day Mon 2/27/23 Mon 2/27/23 19 O&M Site Visit 1 day Mon 3/27/23 Mon 3/27/23 20 O&M Site Visit (vapor sampli 1 day Thu 4/27/23 Thu 4/27/23 21 O&M Site Visit 1 day Fri 5/26/23 Fri 5/26/23 22 Remedial Action Status Repo 6 wks Fri 6/2/23 Thu 7/13/23 23 Subtask 5: Utilities 6.6 mons Thu 12/1/22 Fri 6/2/23 n Custer
Steven Custer Steven Custer
8/7 8/14 8/21 8/28 9/4 9/11 9/18 9/25 10/2 10/9 10/16 September October
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC022A at the Sunshine Cleaners facility located in Ormond Beach, Volusia County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Thu 6/2/22 Wed 6/15/22 2 Subtask 1: Project Managemen Thu 6/16/22 3 Subtask 2: Semi‐Annual O&M 146 days Thu 6/16/22 Thu 1/5/23 4 Field Work Preparation 2 wks Thu 6/16/22 Wed 6/29/22 5 O&M Site Visit 1 day Thu 6/30/22 Thu 6/30/22 6 O&M Site Visit (vapor sampli 1 day Fri 7/29/22 Fri 7/29/22 7 O&M Site Visit 1 day Mon 8/29/22 Mon 8/29/22 8 O&M Site Visit 1 day Thu 9/29/22 Thu 9/29/22 9 Groundwater Sampling 1 day Fri 10/21/22 Fri 10/21/22 10 O&M Site Visit (vapor sampli 1 day Fri 10/28/22 Fri 10/28/22 11 O&M Site Visit 1 day Mon 11/28/22 Mon 11/28/2 12 Semi‐Annual Update 5 wks Fri 12/2/22 Thu 1/5/23 13 Subtask 3: Utilities 6.6 mons Wed 6/1/22 Thu 12/1/22 14 Subtask 4: Semi‐Annual O&M 161 days Thu 12/1/22 Thu 7/13/23 15 Field Work Preparation 2 wks Thu 12/1/22 Wed 12/14/2 16 O&M Site Visit 1 day Wed 12/28/22 Wed 12/28/2 17 O&M Site Visit (vapor sampli 1 day Fri 1/27/23 Fri 1/27/23 18 O&M Site Visit 1 day Mon 2/27/23 Mon 2/27/23 19 O&M Site Visit 1 day Mon 3/27/23 Mon 3/27/23 20 O&M Site Visit (vapor sampli 1 day Thu 4/27/23 Thu 4/27/23 21 O&M Site Visit 1 day Fri 5/26/23 Fri 5/26/23 22 Remedial Action Status Repo 6 wks Fri 6/2/23 Thu 7/13/23 23 Subtask 5: Utilities 6.6 mons Thu 12/1/22 Fri 6/2/23
Steven Custer,Skylar Albritton Steven Custer
Steven Custer J
Jeremy Hess Steven C
10/23 10/30 11/6 11/13 11/20 11/27 12/4 12/11 12/18 12/25 1/1 November December January
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC022A at the Sunshine Cleaners facility located in Ormond Beach, Volusia County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Thu 6/2/22 Wed 6/15/22 2 Subtask 1: Project Managemen Thu 6/16/22 3 Subtask 2: Semi‐Annual O&M 146 days Thu 6/16/22 Thu 1/5/23 4 Field Work Preparation 2 wks Thu 6/16/22 Wed 6/29/22 5 O&M Site Visit 1 day Thu 6/30/22 Thu 6/30/22 6 O&M Site Visit (vapor sampli 1 day Fri 7/29/22 Fri 7/29/22 7 O&M Site Visit 1 day Mon 8/29/22 Mon 8/29/22 8 O&M Site Visit 1 day Thu 9/29/22 Thu 9/29/22 9 Groundwater Sampling 1 day Fri 10/21/22 Fri 10/21/22 10 O&M Site Visit (vapor sampli 1 day Fri 10/28/22 Fri 10/28/22 11 O&M Site Visit 1 day Mon 11/28/22 Mon 11/28/2 12 Semi‐Annual Update 5 wks Fri 12/2/22 Thu 1/5/23 13 Subtask 3: Utilities 6.6 mons Wed 6/1/22 Thu 12/1/22 14 Subtask 4: Semi‐Annual O&M 161 days Thu 12/1/22 Thu 7/13/23 15 Field Work Preparation 2 wks Thu 12/1/22 Wed 12/14/2 16 O&M Site Visit 1 day Wed 12/28/22 Wed 12/28/2 17 O&M Site Visit (vapor sampli 1 day Fri 1/27/23 Fri 1/27/23 18 O&M Site Visit 1 day Mon 2/27/23 Mon 2/27/23 19 O&M Site Visit 1 day Mon 3/27/23 Mon 3/27/23 20 O&M Site Visit (vapor sampli 1 day Thu 4/27/23 Thu 4/27/23 21 O&M Site Visit 1 day Fri 5/26/23 Fri 5/26/23 22 Remedial Action Status Repo 6 wks Fri 6/2/23 Thu 7/13/23 23 Subtask 5: Utilities 6.6 mons Thu 12/1/22 Fri 6/2/23
Jenna Martin,Jeremy Hess,Debra Andrews
Custer
Steven Custer Steven Custer
1/8 1/15 1/22 1/29 2/5 2/12 2/19 2/26 3/5 3/12 3/19 February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC022A at the Sunshine Cleaners facility located in Ormond Beach, Volusia County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Thu 6/2/22 Wed 6/15/22 2 Subtask 1: Project Managemen Thu 6/16/22 3 Subtask 2: Semi‐Annual O&M 146 days Thu 6/16/22 Thu 1/5/23 4 Field Work Preparation 2 wks Thu 6/16/22 Wed 6/29/22 5 O&M Site Visit 1 day Thu 6/30/22 Thu 6/30/22 6 O&M Site Visit (vapor sampli 1 day Fri 7/29/22 Fri 7/29/22 7 O&M Site Visit 1 day Mon 8/29/22 Mon 8/29/22 8 O&M Site Visit 1 day Thu 9/29/22 Thu 9/29/22 9 Groundwater Sampling 1 day Fri 10/21/22 Fri 10/21/22 10 O&M Site Visit (vapor sampli 1 day Fri 10/28/22 Fri 10/28/22 11 O&M Site Visit 1 day Mon 11/28/22 Mon 11/28/2 12 Semi‐Annual Update 5 wks Fri 12/2/22 Thu 1/5/23 13 Subtask 3: Utilities 6.6 mons Wed 6/1/22 Thu 12/1/22 14 Subtask 4: Semi‐Annual O&M 161 days Thu 12/1/22 Thu 7/13/23 15 Field Work Preparation 2 wks Thu 12/1/22 Wed 12/14/2 16 O&M Site Visit 1 day Wed 12/28/22 Wed 12/28/2 17 O&M Site Visit (vapor sampli 1 day Fri 1/27/23 Fri 1/27/23 18 O&M Site Visit 1 day Mon 2/27/23 Mon 2/27/23 19 O&M Site Visit 1 day Mon 3/27/23 Mon 3/27/23 20 O&M Site Visit (vapor sampli 1 day Thu 4/27/23 Thu 4/27/23 21 O&M Site Visit 1 day Fri 5/26/23 Fri 5/26/23 22 Remedial Action Status Repo 6 wks Fri 6/2/23 Thu 7/13/23 23 Subtask 5: Utilities 6.6 mons Thu 12/1/22 Fri 6/2/23
Steven Custer Steven Custer
Steven Custer
3/26 4/2 4/9 4/16 4/23 4/30 5/7 5/14 5/21 5/28 6/4 April May June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC022A at the Sunshine Cleaners facility located in Ormond Beach, Volusia County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Thu 6/2/22 Wed 6/15/22 2 Subtask 1: Project Managemen Thu 6/16/22 3 Subtask 2: Semi‐Annual O&M 146 days Thu 6/16/22 Thu 1/5/23 4 Field Work Preparation 2 wks Thu 6/16/22 Wed 6/29/22 5 O&M Site Visit 1 day Thu 6/30/22 Thu 6/30/22 6 O&M Site Visit (vapor sampli 1 day Fri 7/29/22 Fri 7/29/22 7 O&M Site Visit 1 day Mon 8/29/22 Mon 8/29/22 8 O&M Site Visit 1 day Thu 9/29/22 Thu 9/29/22 9 Groundwater Sampling 1 day Fri 10/21/22 Fri 10/21/22 10 O&M Site Visit (vapor sampli 1 day Fri 10/28/22 Fri 10/28/22 11 O&M Site Visit 1 day Mon 11/28/22 Mon 11/28/2 12 Semi‐Annual Update 5 wks Fri 12/2/22 Thu 1/5/23 13 Subtask 3: Utilities 6.6 mons Wed 6/1/22 Thu 12/1/22 14 Subtask 4: Semi‐Annual O&M 161 days Thu 12/1/22 Thu 7/13/23 15 Field Work Preparation 2 wks Thu 12/1/22 Wed 12/14/2 16 O&M Site Visit 1 day Wed 12/28/22 Wed 12/28/2 17 O&M Site Visit (vapor sampli 1 day Fri 1/27/23 Fri 1/27/23 18 O&M Site Visit 1 day Mon 2/27/23 Mon 2/27/23 19 O&M Site Visit 1 day Mon 3/27/23 Mon 3/27/23 20 O&M Site Visit (vapor sampli 1 day Thu 4/27/23 Thu 4/27/23 21 O&M Site Visit 1 day Fri 5/26/23 Fri 5/26/23 22 Remedial Action Status Repo 6 wks Fri 6/2/23 Thu 7/13/23 23 Subtask 5: Utilities 6.6 mons Thu 12/1/22 Fri 6/2/23 r Jenna Martin,Jeremy Hess,Peter McLean,D
6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 July August
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC022A at the Sunshine Cleaners facility located in Ormond Beach, Volusia County
File details come from the government source that posted it. Updated .