Task Assignment Summary
This Task Assignment (TA) BIL02A is executed between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. under the broader Contract Number HW684. The task is funded through federal State & Tribal Response Program Bipartisan Infrastructure Law (BIL) cooperative agreement funds administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA). The work is focused on the Former Polk County Fertilizer site located at 0 Citrus Ave, Haines City, Polk County, identified as ERIC_13343.
GHD Services, Inc. shall conduct a file review and generate a path forward recommendation letter for environmental assessment and remediation planning at the specified site. The task comprises two subtasks: Subtask 1 provides project management at a cost of $763.00, and Subtask 2 includes detailed file review, site visit, and preparation of path forward recommendations at a cost of $5,989.24, for a total TA value of $6,752.24. The primary deliverable is the Path Forward Recommendation Letter, due July 14, 2023. Work commenced June 12, 2023, with completion targeted for September 20, 2023. Invoice payment is contingent upon FDEP approval of the project management and path forward recommendation letter deliverables.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
BIL02A Completion September 20, 2023
GHD Services, Inc. will conduct a file review and generate a path forward recommendation letter in accordance with the June 2023 scope or work and cost proposal.
Allison Hankins 850.245.8990 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore 813.971.3882
ERIC_13343
0 Citrus Ave, Haines City, Polk County
Former Polk County Fertilizer
✔ $ 6,752.24
$ 6,752.24
Scope of Work
Brian Moore
Vice President
Brian Moore Digitally signed by Brian Moore Date: 2023.06.04 15:56:57 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2023.06.02 15:29:14 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Path Forward Recommendation Letter; Project Management 07/14/2023
DEP approval of Project Management and Path Forward Recommendation Letter (Subtasks 1 & 2) $ 6,752.24
$ 6,752.24
HW684
BIL02A
www.FloridaDEP.gov
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO:
FROM:
DATE:
SUBJECT:
GHD Services, Inc. HW684 Contract File
Allison Hankins, Contract Manager
June 2, 2023
Negotiation Summary – BIL22, Task Assignment (TA) BIL02A Former Polk County Fertilizer - Site ID # ERIC_13343 File Review, Site Visit, and Path Forward Recommendation Letter
This TA is intended for conducting File Review, a Site Visit, and a Path Forward Recommendation Letter for activities at the Former Polk County Fertilizer site, located at 0 Citrus Ave, Haines City, Polk County. The services under this task are being conducted using federal funds from the State & Tribal Response Program Bipartisan Infrastructure Law (BIL) funding cooperative agreement that is administered by the Department on behalf of the U.S. Environmental Protection Agency
(EPA).
Subtask 1: Project Management This subtask is a percentage of the overall project and has been negotiated as a contract rate. It includes project management, overhead, general, administrative, and fringe. The agreed upon cost of this subtask is $763.
Subtask 2: File Review, Site Visit, and Path Forward Recommendation Letter This subtask includes a detailed file review and a site visit to evaluate site conditions and any site logistics or constraints regarding future testing and/or cleanup. The purpose of this subtask will be to define a path forward to appropriately use Brownfield-eligible funding for environmental remediation activities at the site, prior to preparing an Interim Source Removal Workplan or a Remediation Workplan. The deliverable will be the Path Forward Recommendation letter. The agreed upon cost of this subtask is $5,989.24.
Summary The Department’s BIL Contract Manager and GHD Services, Inc.’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $6,752.24. Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) Form and CP/LOE narrative provided by GHD Services, Inc. on June 2, 2023, and the TA Form for BIL01A prepared by the Department. The final deliverable for this TA must be received by the Department no later than July 14, 2023.
http://www.floridadep.gov/
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 6/2/2023
Task #: BF002 SubTask 1 Project Management SubTask 6
Site: Foirmer Polk County Fert SubTask 2 File Review and Path Forward Letter SubTask 7
Activity/Phase: Assessment SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$44.81 Project Manager JM 5.79 5.79 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$63.94 Sr Professional Engineer GK 2.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$53.40 Professional Engineer/Sc KC 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.11 Project Engineer/Scientis TC 18.00 18.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $44.81 Project Manager/ Engine JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $30.05 Staff Engineer/Scientist JW 18.00 18.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.53 Senior Technician SA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.35 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.89 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.25 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.00 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 10.00 10.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.16 Administrative Assistant DA 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 61.79 5.79 56.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $2,253.11 $259.21 $1,993.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $2,924.53 $336.45 $2,588.08 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $851.67 $97.98 $753.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,029.31 $693.64 $5,335.67 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 6/2/2023
Task #: BF002 SubTask 1 Project Management SubTask 6
Site: Foirmer Polk County Fert SubTask 2 File Review and Path Forward Letter SubTask 7
Activity/Phase: Assessment SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $6,149.31 $693.64 $5,455.67 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $602.93 $69.36 $533.57 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $6,752.24 $763.00 $5,989.24 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $6,752.24 Auto-Calculated
Final Total Cost: $6,752.24 Auto-Calculated
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Polk County Fertilizer Plant SUBTASK 2: File Review and Path Forward Letter
DATE: 6/2/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer GK 2
Project Manager JM Path Forward Letter and Recommendations 12 Project Manager JM Site Visit 6
Professional Engineer/Scientist KC Path Forward Letter and Recommendations 4
Staff Engineer/Scientist JW File Review and Summary Preparation 12 Staff Engineer/Scientist JW Site Visit 6
Drafting Technician PM Generate Site Plan Base Map 8 Drafting Technician PM Sampling Plan 2
Administrative Assistant DA Data Tables 2 Administrative Assistant DA Finalize Path Forward Letter 2
TOTAL LABOR 56
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
Path Forward Letter and Recommendations
FINAL --7/24/96
COST PROPOSAL FOR TASK BF002
<Former Polk County Fertilizer Site/FDEP ERIC_13343>
< File Review and Path Forward >
1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >
GHD Services Inc. (GHD) is pleased to submit this proposal to complete a file review, site reconnaissance, and prepare path forward recommendations for the referenced site located in Haines City, Polk County. Our proposed scope of work is included below.
Subtask 1: Project Management Subtask 1 includes all tasks associated with project management of the file review and path forward recommendations for the former Polk County Fertilizer Site.
Subtask 2: Site Reconnaissance and Path Forward Recommendations As requested, GHD will conducted a detailed file review to evaluate previous assessment work that was completed at the site. In addition, GHD will conduct a site visit in order to evaluate current site logistics and any constraints regarding future testing and/or cleanup.
Following completion of the file review and site reconnaissance, GHD will prepare path forward recommendations for the Site. The path forward recommendations letter will include a detail of the findings of the file review and the site reconnaissance. Recommendations will be provided regarding additional assessment activities and possible source removal planning.
Deliverables:
Deliverable Deliverable Due Date
Path Forward Recommendation Letter 7/14/23
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approval 1 wk Fri 6/2/23 Thu 6/8/23
2 Subtask 1: Project Management
25 days Mon 6/12/23 Fri 7/14/23
3 Subtask 2: Path Forward Recommendations
25 days Mon 6/12/23 Fri 7/14/23
4 File Review 2 wks Mon 6/12/23 Fri 6/23/23
5 Site Reconnaissance 1 day Mon 6/26/23 Mon 6/26/23
6 Path Forward Recommendations
3 wks Mon 6/26/23 Fri 7/14/23
5/21 5/28 6/4 June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task BF002 at the former Polk County Fertilizer site located in Haines City, Polk County
Project: TA_002 Date: Fri 6/2/23
Task Name Duration Start Finish
1 LOE Submittal/Approval 1 wk Fri 6/2/23 Thu 6/8/23
2 Subtask 1: Project Management
25 days Mon 6/12/23 Fri 7/14/23
3 Subtask 2: Path Forward Recommendations
25 days Mon 6/12/23 Fri 7/14/23
4 File Review 2 wks Mon 6/12/23 Fri 6/23/23
5 Site Reconnaissance 1 day Mon 6/26/23 Mon 6/26/23
6 Path Forward Recommendations
3 wks Mon 6/26/23 Fri 7/14/23
Jessica Walsh
Jenna Martin,J
6/11 6/18 6/25 July
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task BF002 at the former Polk County Fertilizer site located in Haines City, Polk County
Task Name Duration Start Finish
1 LOE Submittal/Approval 1 wk Fri 6/2/23 Thu 6/8/23
2 Subtask 1: Project Management
25 days Mon 6/12/23 Fri 7/14/23
3 Subtask 2: Path Forward Recommendations
25 days Mon 6/12/23 Fri 7/14/23
4 File Review 2 wks Mon 6/12/23 Fri 6/23/23
5 Site Reconnaissance 1 day Mon 6/26/23 Mon 6/26/23
6 Path Forward Recommendations
3 wks Mon 6/26/23 Fri 7/14/23
Jessica Walsh
Guy Kaminski,Jenna Ma
7/2 7/9 7/16 y
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task BF002 at the former Polk County Fertilizer site located in Haines City, Polk County
| Task Assignment Form |
| Negotiation Summary |
| TA_002 |
| Cost Estimate |
| Subtask 2 |
| TA_002_scope |
| Schedule - TA_002 |
File details come from the government source that posted it. Updated .