Task Assignment DC037A Summary

This is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S., Inc. for environmental remediation services at the Lori-Al (D140) Dry Cleaner site located at 1316 North University Drive, Coral Springs, Broward County, Florida. The TA is entered into pursuant to Contract Number HW680 and was executed on June 22, 2023, with a completion date of November 30, 2023. Theresa Pepe serves as the FDEP Project Manager, while Gus Suarez represents Arcadis as the Contractor's Project Manager.

The scope of work authorizes Arcadis to install a deep monitor well to delineate the groundwater plume containing vinyl chloride contamination, all activities performed according to Arcadis's June 16, 2023, Work Plan. The total TA value is $19,430.67 on a fixed unit rate basis, allocated as follows: $16,272.41 for fieldwork activities (due 09/29/2023) and $3,158.26 for well installation, sampling report, and project management deliverables (due 10/31/2023). The work comprises four subtasks: Project Management (automatically calculated as a percentage of total labor), Well Installation & Sampling (including sonic drilling by subcontractor PDS at $8,970.00, sampling and laboratory analysis at $183.00, and field equipment at $953.00), IDW disposal services by EnviroServe at $1,188.00, and Reporting. Invoicing is contingent upon FDEP approval of deliverables at each stage.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001A.pdf PDF
CN-370000-HW680-DC001D.pdf PDF
CN-370000-HW680-DC002A.pdf PDF
CN-370000-HW680-DC004D.pdf PDF
CN-370000-HW680-DC006A.pdf PDF
CN-370000-HW680-DC006B.pdf PDF
CN-370000-HW680-DC013C.pdf PDF
CN-370000-HW680-DC014E.pdf PDF
CN-370000-HW680-DC014F.pdf PDF
CN-370000-HW680-DC016B.pdf PDF
CN-370000-HW680-DC017B.pdf PDF
CN-370000-HW680-DC017C.pdf PDF
CN-370000-HW680-DC018B.pdf PDF
CN-370000-HW680-DC018C.pdf PDF
CN-370000-HW680-DC020A.pdf PDF
CN-370000-HW680-DC021D.pdf PDF
CN-370000-HW680-DC022C.pdf PDF
CN-370000-HW680-DC024B.pdf PDF
CN-370000-HW680-DC027A.pdf PDF
CN-370000-HW680-DC028A.pdf PDF
CN-370000-HW680-DC028B.pdf PDF
CN-370000-HW680-DC030B.pdf PDF
CN-370000-HW680-DC031B.pdf PDF
CN-370000-HW680-DC031E.pdf PDF
CN-370000-HW680-DC034B.pdf PDF
CN-370000-HW680-DC035B.pdf PDF
CN-370000-HW680-DC035C.pdf PDF
CN-370000-HW680-DC036B.pdf PDF
CN-370000-HW680-DC039A.pdf PDF
CN-370000-HW680-DC039C.pdf PDF
CN-370000-HW680-DC039D.pdf PDF
CN-370000-HW680-DC03ACO2.pdf PDF
CN-370000-HW680-DC042A.pdf PDF
CN-370000-HW680-DC043A.pdf PDF
CN-370000-HW680-DC044A.pdf PDF
CN-370000-HW680-DC046A.pdf PDF
CN-370000-HW680-DC047A.pdf PDF
CN-370000-HW680-DC06ACO1.pdf PDF
CN-370000-HW680-DC06ACO2.pdf PDF
CN-370000-HW680-DC09BCO1.pdf PDF
CN-370000-HW680-DC10BCO4.pdf PDF
CN-370000-HW680-DC11ACO1.pdf PDF
CN-370000-HW680-DC11CCO2.pdf PDF
CN-370000-HW680-DC14BCO2.pdf PDF
CN-370000-HW680-DC14BCO3.pdf PDF
CN-370000-HW680-DC14BCO4.pdf PDF
CN-370000-HW680-DC14BCO9.pdf PDF
CN-370000-HW680-DC14FCO1.pdf PDF
CN-370000-HW680-DC14FCO2.pdf PDF
CN-370000-HW680-DC14FCO4.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW680

DC037A Completion November 30, 2023

This task assignment authorizes Arcadis to install a deep monitor well to help delineate the groundwater plume. All activities will be performed according to the June 16, 2023, Work Plan submitted by Arcadis.

Theresa Pepe 850-245-8966 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Arcadis U.S. Inc.

Arcadis U.S. Inc.

Gus Suarez 813-205-4703

ERIC_4234

1316 North University Drive, Coral Springs, Broward County

Lori-Al (D140) Dry Cleaner

✔ $ 19,430.67

$ 19,430.67

Scope of Work

Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2023.06.22 10:55:42 -04'00'

Kelly Crain

Kelly Crain Digitally signed by Kelly Crain Date: 2023.06.22 08:29:10 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Fieldwork Activities 09/29/2023

Well Installation & Sampling Report/IDW manifest/Project Management 10/31/2023

FDEP approval of Fieldwork Activities $ 16,272.41

FDEP approval of Well Installation & Sampling Report/IDW manifest/Project Management $ 3,158.26

$ 19,430.67

HW680

DC037A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Negotiation File Lori-Al (D140) Dry Cleaner

FACID NO. 06-9701245; ERIC_4234

Coral Springs, Broward County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC037A (HW680) DATE: June 21, 2023

Arcadis U.S. Inc. will install and sample a deep monitor well to delineate the groundwater plume. All activities will be conducted in accordance with the June 16, 2023, Work Plan submitted by Doug McGlone of Arcadis.

The final task assignment total is $19,430.67. Arcadis may invoice according to the attached schedule.

Specific negotiated subtasks are as follows:

Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.

Subtask 2: Well Installation & Sampling Arcadis will coordinate access for the off-site property before work commences. A site access form for the source property was obtained in June 2021. No changes in property ownership have occurred since that date.

Arcadis will install a deep off-site monitor well via sonic drilling to delineate the downgradient vinyl chloride plume. The location/depth of the well was approved by the Waste Site Cleanup Section geologist.

PDS was chosen as the drilling subcontractor based on their low bid of three bids solicited. IDW will be drummed and disposed by a licensed waste hauler.

Subtask 4: Reporting Arcadis will submit a well installation and sampling report as the Final Deliverable.

FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.

Date: 6/15/2023

Task #: SubTask 1 Project Management Site: Lori AL D-140 SubTask 2 Site Access, Well Installation/Sampling

Activity/Phase: Well Installation SubTask 3 Reporting Project Manager: Doug McGlone SubTask 4

SubTask 5

Totals 1 2 3 4 5 Labor Rate Category

$67.07 Project Manager McGlone, Douglas (DMc) 4 4.3$100.00 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0 $85.87 Principal Engineer Suarez, Gus (GS) 0 0 0 0 0$81.66 Principal Scientist McManus, Andrew (ATM) 0 0 0 0 0$67.07 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0 $67.07 Principal Scientist McGlone, Douglas (DMc) 10 6 4 0 0 $39.34 Staff Scientist Riley, Joel (JR) 30 22 8 0 0 $39.67 Drafter/Designer Oliva, Brian (BO) 4 0 4 0 0 $34.40 Drafter/Designer Berndgen, Wendy (WDB) 0 0 0 0 0 $35.00 Document Technician Ballheim, Debra (DJB) 0 0 0 0 0 $30.00 Document Technician Embras, Susan (SRE) 0 0 0 0 0 $37.25 Project Assistant Cruz, Michele (MC) 5 2 3 0 0

Total Hours 53 4 30 19 0 0

Direct Labor $2,481.29 $285.46 $1,342.40 $853.43 $0.00 $0.00

Overhead 79.00% $1,960.22 $225.51 $1,060.50 $674.21 $0.00 $0.00 Gen & Admin 36.00% $893.26 $102.77 $483.26 $307.23 $0.00 $0.00 Fringe 37.10% $920.56 $105.91 $498.03 $316.62 $0.00 $0.00 Total Labor $6,255.33 $719.65 $3,384.19 $2,151.49 $0.00 $0.00

Travel Vehicle Rental $240.00 $240.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $240.00 $240.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $8,970.00 $8,970.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 IDW EnviroServe $1,188.00 $1,188.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $10,158.00 $10,158.00 $0.00 $0.00 $0.00 Handling Fee $1,015.80 $1,015.80 $0.00 $0.00 $0.00 Total Subcontractor Cost $11,173.80 $11,173.80 $0.00 $0.00 $0.00

Laboratory Analytical Costs $73.00 $73.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 $110.00 $0.00 $0.00 $0.00 Total Laboratory $183.00 $183.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $80.00 $80.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $33.00 $33.00 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 Equipment (Other) $740.00 $740.00 $0.00 $0.00 $0.00 Total Field Expenses $953.00 $953.00 $0.00 $0.00 $0.00

Subtotal $18,805.13 $719.65 $15,933.99 $2,151.49 $0.00 $0.00 Completion Fee $625.54 $71.97 $338.42 $215.15 $0.00 $0.00

Total Estimated Cost $19,430.67 $791.62 $16,272.41 $2,366.64 $0.00 $0.00

REV: 02/03 CEF ARCADIS Page 1

SITE : Lori AL D-140 SUBTASK 2: Site Access, Well Installation/Sampling

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

(Subtask Title) Principal (DMc) Event oversight, site owner/tenant access, IDW management 6 Staff Scientist (JR) Mob/demob (3 hrs), Well installation (10 hrs) 13 Staff Scientist (JR) Mob/demob (3 hrs), survey TOC (1 hr) sampling, pack/ship (5 hrs) 9 Project Asst (MMc) Process field notes, data entry 2 Drafter/Designer(BO) 0

TOTAL LABOR 30

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 2 $240.00 $240.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

Meals Category/Staff Rate Unit Usage Totals

$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00

Hotel Category/Staff Rate Unit Usage Totals

$150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals NAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00 PDS Drilling services $8,970.00 Lump Sum 1 $8,970.00 EnviroServe IDW $198.00 6 $1,188.00NAME OF COMPANY On-site Mobile Laboratory analysis $0.00 Lump Sum 0 $0.00

Handling Fee $0.00 Per Month 0 $0.00

Total Services: $10,158.00

TOTAL $10,158.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC 8260 Aqueous $73.00 1.00 1 $73.00Dissolved Solids, Total SM2540 C Aqueous $16.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $73.00

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00

Total Shipping: $110.00

TOTAL LAB $183.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals

Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 2 $80.00

Total Expendables: $80.00 Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 100 $30.00 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 1 $3.00 55-gallon Drum $100.00 Each 1 $100.00

Total Equipment Items: $133.00 Equipment Kits Monitor Well Installation Kit $325.00 Day 1 $325.00 Deep Groundwater Sampling Kit $415.00 Day 1 $415.00

Total Equipment Kits: $740.00

TOTAL EQUIPMENT $953.00

SITE : Lori AL D-140

SUBTASK 3: Reporting

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

(Subtask Title) Principal (DMc) Prepare and submit field notes, lab report, sample forms and deliverable to FDEP; technical analysis 4

Project Engineer (TH) 0

Staff Scientist (JR) Data evaluation and preparation of deliverable 8

Project Asst (MMc) Assemble report, ADaPT upload 3

Drafter/Designer(BO) Figures production for report 4

TOTAL LABOR 19

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

Meals Category/Staff Rate Unit Usage Totals

$36.00 Per Day 0 $0.00

$36.00 Per Day 0 $0.00

Hotel Category/Staff Rate Unit Usage Totals

$150.00 Per Day 0 $0.00

$150.00 Per Day 0 $0.00

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage TotalsNAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00 Handling Fee $20.00 Per Month 0 $0.00

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples TotalsVOC TO-15 Vapor $200.00 1.00 0 $0.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals Total PPE: $0.00

Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00 Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00

Total Equipment Items: $0.00 Equipment KitsSite Reconnaissance Kit $150.00 Day 0 $0.00

Total Equipment Kits: $0.00

TOTAL EQUIPMENT $0.00

Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.

Arcadis U.S., Inc.

1500 Gateway Boulevard

Suite 200

Boynton Beach

Florida 33426

Tel 561 697 7000

Fax 561 369 4731 www.arcadis.com

Page:

1/2

Ms. Theresa Pepe, Project Manager Hazardous Waste Cleanup Section Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, FL 32399-2400

Subject:

Proposal for Additional Assessment Lori-Al D140 1316 North University Drive, Coral Springs, FL FDEP Facility ID No. ERIC_4234

Dear Theresa:

As requested, Arcadis U.S., Inc. (Arcadis) is pleased to provide the Florida Department of Environmental Protection (FDEP) this proposal for monitor well installation and sampling and preparation of report of findings with recommendations as to whether the monitor well network is adequate.

PROPOSED SCOPE OF WORK

Task 1: Project Management

This task includes project management activities associated with completion of Tasks 2 through 3.

Task 2: Offsite Access, Well Installations and Sampling/Analysis

Arcadis will verify ownership of the University Maplewood Townhomes bordering the site to the west for the installation of one additional monitor well (MW025) for vertical delineation of vinyl chloride. The new well will be constructed with 2-inch diameter pvc and screened 100-110 ft bg. The top of casing elevation of the newly installed well will be surveyed and referenced to the existing well network.

The newly installed well will be sampled for the presence of VOHs by EPA 8260.

ENVIRONMENTAL

Date:

June 16, 2023

Contact:

Douglas J. McGlone

Phone:

561-662-7978

Email:

douglas.mcglone@arcadis.com

Our ref:

D-140

Florida License Numbers

Engineering

Geology

GB564

Surveying

LB7062

This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.

arcadis.com C:\Users\Pepe_T\Desktop\Lori Al D140 Proposal 6-16-23.docx

Theresa Pepe June 13, 2023

Page:

2/2

Task 3: Supplemental Groundwater Assessment Report

A brief letter report summarizing well installation and survey elevations, and groundwater monitoring methods and results including a table summarizing the groundwater analytical results and figures illustrating the extent and magnitude of the groundwater impacts and copies of sample lab reports will be provided to the FDEP, along with recommendations for future site activities. The report will be signed and sealed by a Florida registered professional geologist.

SCHEDULE

Arcadis will begin implementing the proposed tasks upon receipt of a Task Assignment (TA) from FDEP.

We anticipate performing the well installations and groundwater sampling within 30 days of receiving Task Assignment. We anticipate submittal of the letter report within 45 days of completion of field work activities.

Cost Estimate

Cost Estimate and Level of Effort Forms (CEF-LOE) that present estimated project costs are enclosed in Attachment 1.

CLOSING REMARKS

Arcadis appreciates the opportunity to assist the FDEP with this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.

Sincerely, Arcadis U.S., Inc.

Douglas J. McGlone, P.G.

Principal Hydrogeologist

Preferred Drilling Solutions, Inc.

8820 66th St, Pinellas Park, FL 33782

Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com

SONIC DRILLING TECHNOLOGY QUOTE FORM

Date: 6/21/23 FAC ID#:

*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner

Unit Unit Rate Number of Units Extended Price per day $4,000.00 1 4,000.00$ per day $3,000.00 -$ per foot $18.00 -$ per foot $25.00 110 2,750.00$ per foot $35.00 -$ each $125.00 -$ per well $125.00 1 125.00$ roundtrip $1,575.00 1 1,575.00$ per crew / per night $450.00 -$ each $70.00 6 420.00$ each $100.00 1 100.00$

TOTAL QUOTE PRICE $8,970.00

Notes: 1. Includes caps, plugs, tubing, saw cuts, development, standby time, and decon.

Project No.:

Subcontract Company Name: Preferred Drilling Solutions, Inc. (727) 561-7477

Subcontract Mailing Address: 8820 66th St, Pinellas Park, FL 33782

Signature and Title of Person Submitting Quote: ___________________________________Kevin Bonacum, Estimator

MISCELLANEOUS

(1) 2" x 110' MW with 5' .010 screen, 8" x 80' temp override casing, no soil sampling, drum soil & water, pad and 8" manhole

Sonic Daily Rate & Crew (up to 10 hours on site)

Sonic Half Day Rate & Crew (up to 5 hours on site)

1" PVC Well Installation (includes all materials)

2" PVC Well Installation (includes all materials) 4" PVC Well Installation (includes all materials)

Pre-Packed Well Screen (includes all materials) ID 2" 5' Length

Well Completion (includes MH w/ cover, concrete pad, and locking well cap)

Consultant Name: Arcadis

Site Name and Location: Lori-AL Cleaners 1316 N University Dr, Coral Springs, Broward County, FL

PROPOSED SCOPE OF WORK:

Equipment Type: Geoprobe 8150LS, Terrasonic 150CC

SONIC DRILLING TECHNOLOGY

Other (specify)

Other (specify)

Days to Complete Scope of Work: 1

Mobilization Per Diem

DOT Approved 55-gal Drum

Permits

Other (specify)

Pepe_T Highlight

2703 NW 19th Street, Pompano Beach, FL 33069

Monitoring Wells Sparge Wells Direct Push

Geotechnical Drilling SONIC Drilling

DATE

CLIENT: PHONE

SITE:

PROPOSED SCOPE OF WORK:

Unit Number

Rate of Units

Sonic Daily Rate per day $3,900.00 1

Sonic Daily Rate

8" Sonic Over Ride Casing per foot $20.00 80

Compact Tooling Loader / Water Support per day $550.00 1

1" PVC Well Material (includes all annular backfill) per foot

2" PVC Well Material (includes all annular backfill) per foot $16.00 110

4" PVC Well Material (includes all annular backfill) per foot

8" Bolt-down completion per well $225.00 1

12" Bolt-down completion per well

Above Grade Protector (Aluminum) per well

Mobilization (Sonic Drill with all associated equipment) roundtrip $1,000.00 1

Daily Mobilization (to and from site per day) per day

Per Diem per night

Permits each $85.00 1

Decontamination Pad (incl. setup & breakdown) lump sum

Water Meter and usage (If Needed) lump sum $1,000.00 0

DOT Approved 55-gal Drum each $80.00 3

Onsite Pre-Drill Meeting each

Standby / Difficult Moving Time per hour $550.00

Days to Complete Scope of Work 1 Submitted By: Charles Bucher TOTAL QUOTE PRICE

$0.00

$0.00

$0.00

$0.00

$0.00

Well Completion (includes 30 min. development, bolt-down manhole, concrete pad(2'x2' or 10" circle) & lockable well cap

$225.00

6/21/2023

Lori AL D-140 - 1316 N University Dr - Coral Springs, FL

(Hand Clear to 5' or Refusal at all locations)

(1) MW 2" x 110' w/ 10' .010" Screen (20/30 Sand) & 8" BD Completion - 8" x 80' Temp Override Casing

(561) 662-7978Arcadis Doug McGlone

Sonic Daily Rate (Compact Track) Price Includes a ten hour work day ( 7 to 5 ) Unless otherwise stated in this quote.

$0.00

$0.00

$0.00

$0.00

Drum Soil & Development Water.

$0.00

SONIC DRILL Unit Extended Price

$3,900.00

MISCELLANEOUS

$550.00

$0.00

WELL MATERIALS

$0.00

$1,760.00

$9,360.00

$1,000.00

$0.00

$85.00

$240.00

$1,600.00

$0.00

$0.00

$0.00

$0.00

Arcadis 6/15/2023 1500 Gateway Boulevard PN230615-125694rev Suite 200 6/21/2023 Boynton Beach, Florida 33426 Coral Springs, FL

Douglas McGlone 1316 N University Drive douglas.mcglone@arcadis.com Coral Springs

561.662.7978 Florida

Cascade Rep Contact Information

Scope of Work

Quantity Unit Sales Price Subtotal Mobilization 1 Each 3,500.00$ 3,500.00$ Demobilization 1 Each 3,500.00$ 3,500.00$ Per Diem and Lodging (per worker) 6 Man/Day 225.00$ 1,350.00$ 6" Sonic Casing Advance (overburden) 110 Feet 45.00$ 4,950.00$ 7" Temporary Override Casing 80 Feet 30.00$ 2,400.00$ 2" PVC Well Installation 110 Feet 30.00$ 3,300.00$ Flush Mount Completion w/ 2'x2' pad 1 Each 400.00$ 400.00$ 55-Gallon DOT Drums 8 Each 95.00$ 760.00$ Hydrant Meter if needed Lump Sum 1,600.00$ Skidsteer/Bobcat 1 Week 1,600.00$ 1,600.00$ Jackhammer 1 Day 125.00$ 125.00$ Concrete Saw and Blades 1 Day 125.00$ 125.00$ Standby Delays/Hydration or Curing Delays/Travel Between Jobsites Hours 525.00$ Permits as needed 1 Each 100.00$ 100.00$

Pre-Tax Total

Tax Percentage

Taxes

Quote Total

Contact Name Project Address Email Project City Phone Project State

Drill one boring to 110' with temporary 7" casing to 80'. Install 2" Sch40 PVC well with 10' of regular .010-slot screen. Complete with a 2'x2' concrete pad and 8" flushmount manhole cut into an asphalt-paved area. Drum all cuttings and development water. Drums will be staged on site for disposal by others.

No union/prevailing wages or additional training is expected.

Work schedule will be 10/4 rotations with daily work hours of 7am - 5pm including lunch and safety meetings.

Level D PPE is expected.

Cascade estimates 2 days to complete this project. All quantities are estimates. Actual accrued totals will be invoiced. Cascade expects 1 permit will be needed for this project. If additional permits are required, they will be invoiced at cost to Arcadis.

Description

$22,110.00

Account Name Bid Date Address Quote Number

Quote Revision Date

Bill To Account Project Zip

Project Name

Number

Prepared By Email wburdette@cascade-env.comWill Burdette, Southeast Region Estimator

This quote is based on information provided by you and is valid for 45 days from the bid date. Unless previously agreed, Cascade requires a 2-week notice prior to mobilization. Your firm is responsible for 1) Obtaining any site specific permits, 2) Locating and clearly marking underground installations or utilities, 3) Furnishing dig

Alert numbers at least three working days prior to scheduled start date and proof of private locating services, 4) Obtaining access to site with no overhead wires within 20' of the holes. Cascade Drilling shall not be responsible for damages to underground improvements not clearly and accurately marked. If bedrock, cobbles, flowing sands or other adverse or unsafe drilling conditions are encountered, drilling may continue on a time and materials basis or be terminated at the discretion of Cascade.

Additional costs may apply if scope is significantly changed. Well development by others may void some or all of Cascade warranties of workmanship and materials.

Florida: 5785 SW 6TH PL STE 101, OCALA FL 34474 ♦ (352) 237-1995

$22,110.00

Arcadis 6/15/2023 1500 Gateway Boulevard PN230615-125694rev Suite 200 6/21/2023 Boynton Beach, Florida 33426 Coral Springs, FL

Douglas McGlone 1316 N University Drive douglas.mcglone@arcadis.com Coral Springs

561.662.7978 Florida

Cascade Rep Contact Information

Contact Name Project Address Email Project City Phone Project State

Account Name Bid Date Address Quote Number

Quote Revision Date

Bill To Account Project Zip

Project Name

Number

Prepared By Email wburdette@cascade-env.comWill Burdette, Southeast Region Estimator

Signature of Authorized Cascade Representative

Name & Title of Authorized Cascade Representative

Date Date

Signature of Client/Owner Authorized Representative

Cascade will perform the Work as described in this proposal subject to the terms and conditions posted at https://cascade-env.com/resources/other/terms-and-conditions/ unless MSA is already established between Cascade and Client in which case MSA takes precedence over the aforementioned terms and conditions. By signing this proposal, Client agrees that this proposal together with the terms and conditions referenced above constitute a Subcontract. Client acknowledges that

Client has received and agrees with all such documents in the form provided by Cascade. Terms and Conditions are posted and accessible at the website location set forth above.

Name & Title of Authorized Representative and Company

09/07/2022 03:24 PM PAGE 1 OF 7

Scope of Work

Blanket Quote based on one drum T&D , for service site specific quote - disposal approval required

TCLP Benzene and 4 Metals with Completed Profile required for each site

Drum Pickup /Transportation/Disposal

Drums south of Miami not included (Keys) additional costs apply

755 PRARIE INDUSTRIAL PKWY,

MULBERRY, FLORIDA, 33860

QUOTE #: 0030388

DATE: 09/07/2022 PROJECT PROPOSAL

CLIENT

DOUGLAS MALONE

ARCADIS

1500 GATEWAY BLVD, SUITE 200, BOYTON BEACH, FLORIDA,

33426

P: (561) 662-7978

PROJECT DESCRIPTION

DRUM PICKUP

VARIOUS SITES SOUTH FLORIDA

THE FOLLOWING DESCRIBES OUR UNDERSTANDING OF THE SCOPE OF SERVICES TO BE PERFORMED BY ENVIROSERVE, FOR THE

CLIENT, AT THE ABOVE REFERENCED LOCATION KNOWN AS THE JOB SITE.

FEE STRUCTURE

TRANSPORTATION

ITEM EST.QTY. UNIT PRICE UNIT TOTAL

TRANSPORTATION 55 GAL DRUMS

NOTES:SUBJECT TO FUEL SURCHARGE,

1.00 $50.00 DRUM $50.00

STOP FEE 6 DRUMS OR LESS PICKUP 1.00 $50.00 EACH $50.00

TRANSPORTATION SUBTOTAL: $100.00

DISPOSAL

ITEM EST.QTY. UNIT PRICE UNIT TOTAL

55 GALLON NON HAZ DRUM

NOTES: Drum DOT Shippable Drum accessible on hard Surface

1.00 $80.00 EACH $80.00

ENERGY SURCHARGE 10% INVOICE TOTAL 1.00 $18.00 EACH $18.00

DISPOSAL SUBTOTAL: $98.00

TOTAL JOB ESTIMATE: $198.00

HW680_DC037A ns.pdf
Subtask 1: Project Management
Subtask 2: Well Installation & Sampling
Subtask 4: Reporting
Lori Al D140 Proposal 6-16-23.pdf
Proposed Scope of Work
Task 1: Project Management
Task 2: Offsite Access, Well Installations and Sampling/Analysis
Task 3: Supplemental Groundwater Assessment Report
Schedule
Cost Estimate

Closing Remarks

Arcadis Lori-AL Cleaners Coral Springs FL (Sonic revised).pdf
Direct Push

File details come from the government source that posted it. Updated .