About this file

This document package comprises Task Assignment Change Orders (TACO) issued by the State of Florida Department of Environmental Protection (FDEP) to amend a task assignment contract with Arcadis U.S., Inc. The contract, designated HW680, concerns environmental remediation work at the Dry Cleaning Depot facility (ERIC_4160) located in Fort Lauderdale, Broward County, Florida. The contracting parties include FDEP, represented by Project Manager Theresa Pepe, and Arcadis U.S., Inc., represented by Contract Manager Gus Suarez. Two change orders are detailed: TACO 3, executed on May 30, 2023, and TACO 4, executed on August 16, 2023.

The contract involves environmental assessment and monitoring activities at a contaminated dry cleaning facility, including site access negotiations, monitor well installation, field logging, sampling, and preparation of monitoring reports and waste disposal manifests. The total task assignment value remains fixed at $38,808.65 with no cost modifications in either change order. TACO 3 extended the completion date by 60 days from July 31, 2023 to September 29, 2023, while TACO 4 added an additional 90-day extension, moving the completion date to December 28, 2023. Both extensions were necessary to obtain off-site access and regulatory approvals from the City of Lauderhill for contractor registration and right-of-way permits. The invoicing schedule distributes payments across three deliverables: $4,053.01 for site access negotiations, $30,000.00 for monitor well installation and sampling, and $4,755.64 for monitoring reports and project management, contingent upon FDEP approval of each phase.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001B.pdf PDF
CN-370000-HW680-DC001E.pdf PDF
CN-370000-HW680-DC001F.pdf PDF
CN-370000-HW680-DC005A.pdf PDF
CN-370000-HW680-DC005B.pdf PDF
CN-370000-HW680-DC006C.pdf PDF
CN-370000-HW680-DC007C.pdf PDF
CN-370000-HW680-DC008C.pdf PDF
CN-370000-HW680-DC009A.pdf PDF
CN-370000-HW680-DC009D.pdf PDF
CN-370000-HW680-DC010A.pdf PDF
CN-370000-HW680-DC010B.pdf PDF
CN-370000-HW680-DC011A.pdf PDF
CN-370000-HW680-DC012A.pdf PDF
CN-370000-HW680-DC014D.pdf PDF
CN-370000-HW680-DC015F.pdf PDF
CN-370000-HW680-DC016A.pdf PDF
CN-370000-HW680-DC017A.pdf PDF
CN-370000-HW680-DC017D.pdf PDF
CN-370000-HW680-DC019A.pdf PDF
CN-370000-HW680-DC019B.pdf PDF
CN-370000-HW680-DC020D.pdf PDF
CN-370000-HW680-DC021A.pdf PDF
CN-370000-HW680-DC022A.pdf PDF
CN-370000-HW680-DC026D.pdf PDF
CN-370000-HW680-DC029B.pdf PDF
CN-370000-HW680-DC030A.pdf PDF
CN-370000-HW680-DC033A.pdf PDF
CN-370000-HW680-DC034A.pdf PDF
CN-370000-HW680-DC039B.pdf PDF
CN-370000-HW680-DC03BCO1.pdf PDF
CN-370000-HW680-DC03DCO1.pdf PDF
CN-370000-HW680-DC03DCO2.pdf PDF
CN-370000-HW680-DC040A.pdf PDF
CN-370000-HW680-DC041B.pdf PDF
CN-370000-HW680-DC041C.pdf PDF
CN-370000-HW680-DC046B.pdf PDF
CN-370000-HW680-DC047B.pdf PDF
CN-370000-HW680-DC048B.pdf PDF
CN-370000-HW680-DC049A.pdf PDF
CN-370000-HW680-DC050B.pdf PDF
CN-370000-HW680-DC051B.pdf PDF
CN-370000-HW680-DC07BCO1.pdf PDF
CN-370000-HW680-DC07CCO1.pdf PDF
CN-370000-HW680-DC09ACO1.pdf PDF
CN-370000-HW680-DC10ACO1.pdf PDF
CN-370000-HW680-DC10BCO2.pdf PDF
CN-370000-HW680-DC10BCO3.pdf PDF
CN-370000-HW680-DC11BCO1.pdf PDF
CN-370000-HW680-DC13DC01.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC014B 4 HW680

A time extension of 90 days is added for obtaining off-site access.

Theresa Pepe 850-245-8966 Contractor Contractor

Contractor Contractor

Contractor

Arcadis U.S. Inc.

Gus Suarez 813-205-4703

ERIC_4160

Dry Cleaning Depot

✔ $ 0.00 $ 0.00

$ 0.00 $ 0.00 Completion

Completion✔ 09/29/2023 12/28/2023 90

✔ 1 1 4

Arcadis U.S. Inc.

Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2023.08.16 13:18:10 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2023.08.16 11:35:54 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW680

DC014B

$ 38,808.65

Site Access negotiations and prep work (subtask 2 partial)

Monitor Well Installation Field Logs, and additional sampling (subtask 2 partial & subtask 4)

Monitoring Report/IDW manifest/Project Management (subtasks 1 & 3)

FDEP approval of Site Access negotiations and prep work (subtask 2 partial)

FDEP approval of Annual Monitoring Report/IDW manifest/Project Management (subtasks 1 & 3)

FDEP approval of Monitor Well Installation Field Logs, and additional sampling (subtask 2 partial & subtask 4)

09/15/2023

10/31/2023

11/30/2023

$ 30,000.00

$ 4,053.01

$ 4,755.64

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Negotiation File Dry Cleaning Depot Facility ID No. 06-9502029; ERIC_4160 Fort Lauderdale, Broward County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC014B-4 (HW680) DATE: August 11, 2023

More time is required to negotiate off-site access. Additionally, the deliverable schedule is modified for invoicing purposes. For additional information, see the August 10, 2023, change order request memo from Doug McGlone of Arcadis.

This change order adds ninety days to the completion date. There is no cost change to the task assignment. Arcadis may invoice according to the attached schedule.

From: McGlone, Douglas To: Pepe, Theresa Subject: RE: Dry Cleaning Depot time extension Date: Thursday, August 10, 2023 4:12:43 PM Attachments: image002.png image003.png image004.png image005.png image006.png image007.png

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

I hope 90 days is enough additional time. We are currently waiting for City of Lauderhill to approve us as a registered contractor. One we are registered we can apply for ROW permit. I think the ROW permit will go faster. I’ll put something together to document the efforts and correspondence between church and now Lauderhill for invoicing.

Thanks

Douglas J. McGlone PG Principal Geologist Arcadis U.S., Inc.

1500 Gateway Blvd., Suite 200 | Boynton Beach, Florida | 33426 | USA M. +1 561.662.7978 www.arcadis.com

Professional Geologist / PG-FL 2405

From: Pepe, Theresa <Theresa.Pepe@FloridaDEP.gov> Sent: Thursday, August 10, 2023 11:03 AM To: McGlone, Douglas <Douglas.McGlone@arcadis.com> Subject: Dry Cleaning Depot time extension

Good morning Doug, Regarding DC Depot and the downgradient wells - I am getting ready to write a time extension for the attached TA. Do you think an additional 90 days is adequate or would you prefer a different due date?

Also, if you submit an access deliverable (documentation of applying for ROW permits or something similar), I can allow you to invoice for the first deliverable.

mailto:Douglas.McGlone@arcadis.com mailto:Theresa.Pepe@FloridaDEP.gov http://secure-web.cisco.com/1soXv434wMrualHuGz-1fnl-_pUzieUSGn7Ks_O6KDsKeByQa45SleKNJZgobDiCWe1r_LLtt8XUjn9pjjJ_WAuy33UGxlhRm4paw6SgKflsrsXDDnB1M8GL8xNMpWBfkNCgaBi7AxBtHM6-p0b6__E79jI3RpMzncAOcFdbpJYrIRFTYue2FiPpsipVz5hXzp5KB6mcOlVI2hgvgkLeH4ovux3oSNO1hZB21hNNS90xlm_DRiRyr4QZIWd1uKLbycKOaf7Xp4E-xTVkqD6K0Dy8tMlE2Ib2t2OVMl1x-nSJ8aXi86eBusjeQPO4Wtu4f/http%3A%2F%2Fwww.arcadis.com%2F https://secure-web.cisco.com/1sNZ9adJoF4Gh1gw0WwadNY2Y7n2UIoX_E3cvwZGjKvaNP__QzwVrmayRdNbWFWp4181yaMGun0GjSgNuMcqHw8Au_RaLzBaw2SWygFSpRiISh2GAxihkkMRdP2QeXElCyUuoQyZTRMnKq_H52aIRo6idMQQ4wQXPgQWN9X3lVE9atFQRzgsJh3qXa35sOYdxXZ4WNlF_TBZIMaFEFMJptCrWQ2s4xFpc2RtSD_3ocORph-ii4DdzTpIOXipp9mp1p3zwOZkxEvSrk8Yh9rmX8izWLQbqTA2NT7MB7dsAXiEtICqpy6Jt5umbPZruK-MZ/https%3A%2F%2Fwww.linkedin.com%2Fshowcase%2Farcadis-north-america%2F https://secure-web.cisco.com/11pwaZXAOvAWBOuHHAvDEKVJo4mbqxNvvjuJkN_oa_Ix3A0uZKYSPZm9sE_F2ZSd59Z4xsVo4S-r8SvDGniD8w0h2cDwMttHqD0QI5UETwsGlbYC00_byuhK6KaWBTVejIXPqIJWmbzo3NSal7cXKK2-o30j99Hh9MCE7lZ2-iqjXY208fK_8DK4G02aOh17-CCVu_AgmFsiH2XddlU91esBFuigMtZ1ISTGr2Byu0_2zUO_56k52bjclLrLJAB_Xy5DI3DFFuUk1wniFtO6fvRfsREZQvr6ojBAu-pi8Hx121YmwhAaVOUnpB_IPj8ZK/https%3A%2F%2Ftwitter.com%2FArcadis_NA%3Fref_src%3Dtwsrc%255Egoogle%257Ctwcamp%255Eserp%257Ctwgr%255Eauthor https://secure-web.cisco.com/1KqFsAzp4_bezxrmqOnd8ud8uthq53zosGYdX-oF6wt0KgxkO9gHkfLMuaeFr7C5o_483xvZmuOs-RiWvBsg85zz1wz6Kpr0tS-cVoa3w9Jtfnf1j40DOOiYNxCukqJkrez0Prdv7k55TYC_5OLem5zleRJn9gA_gZ_If1yLB138ki8GXhb6MJsYbTIm6x6ELxZpkd-oE46os9bpRl783--e_2Ai9mzsK4hehtJLy99TqMa80JCuE7xFjz6cAAMxkmcKnGpXzF1oShfuxXVUpHDqQ8N8oHYBuJzQM2Uve8hmRLUFRZhVERp_jMPjr-SiV/https%3A%2F%2Fwww.facebook.com%2FArcadisNorthAmerica%2F https://secure-web.cisco.com/1elrJuQaQEhKBBnSNT4spGYWqykpK-c84mqlEpxiXxv75OtTsDmZHUu4qEFoLqdjGZWgsNHin8BW2klmBR-2fcAjyXA9hPJHLMs-JiWEWlsrlK5AS3-_qro9NeO3bR5fLBiacU03ouGbqRdZowfFATkuhCTOrAg3KCkwqeAlLarepCZIWKPuZTZtz-Gdqqy9jmLH_o-lpdPMCP0I9tn9pgJXN6E9JwQBGb92YQHk4WlkHIgT00jayGIeVsLu979Clbm8SSHq0u3DOmDkRWG0f4zH5l9wC7yZ-Sxh5AKsc6xLQqObUSq4d5MyPMyEBVQY_/https%3A%2F%2Fwww.instagram.com%2Farcadisglobal%2F%3Fhl%3Den

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

DC014B 3 HW680

A time extension of 60 days is added for obtaining off-site access.

Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor

Contractor Gus Suarez Contractor 813-205-4703

ERIC_4160

Dry Cleaning Depot

✔ $ 0.00 $ 0.00

$ 0.00 $ 0.00 Completion

✔ Completion 07/31/2023 09/29/2023 60

✔ 1 1 3

Arcadis U.S. Inc.

Contractor Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2023.05.30 16:05:06 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2023.05.30 15:32:07 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW680

DC014B

$ 38,808.65

Site Access negotiations and prep work (subtask 2 partial)

Monitor Well Installation Field Logs, and additional sampling (subtask 2 partial & subtask 4)

Monitoring Report/IDW manifest/Project Management (subtasks 1 & 3)

FDEP approval of Site Access negotiations and prep work (subtask 2 partial)

FDEP approval of Annual Monitoring Report/IDW manifest/Project Management (subtasks 1 & 3)

FDEP approval of Monitor Well Installation Field Logs, and additional sampling (subtask 2 partial & subtask 4)

06/16/2023

07/31/2023

08/31/2023

$ 30,000.00

$ 4,053.01

$ 4,755.64