This is a Task Assignment (TA) document issued under Contract HW680 between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S. Inc. The task assignment pertains to environmental remediation services at the Peerless Dry Cleaners site located at 7379 NW 36th Street, Miami, Miami-Dade County, Florida (FACID No. 13-9501189; ERIC_4379). The State of Florida FDEP, represented by Project Manager Theresa Pepe, contracted with Arcadis U.S. Inc., represented by Contract Manager Gus Suarez, to conduct groundwater monitoring activities in accordance with the February 15, 2024 Work Plan submitted by Arcadis.
The task assignment (TA Number DC017D) is valued at $6,660.98 on a fixed unit rate basis and consists of three subtasks: (1) Project Management, calculated as a percentage of total labor; (2) Groundwater Monitoring, which includes sampling six wells for drycleaning solvents with containerized disposal of investigation-derived waste (IDW) by a licensed waste hauler; and (3) Reporting, with a deliverable due date of April 30, 2024. The deliverable is a Site Rehabilitation Completion Report or, if results are not clean, a Groundwater Monitoring Report recommending either site closure without conditions or return to annual monitoring. The cost estimate details 41 total labor hours distributed across project management, monitoring, and reporting activities, along with expenses for vehicle rental ($120.00), analytical costs ($438.00), sample shipping ($150.00), IDW disposal ($125.00), and field equipment and expendables ($472.00). Invoice payment is contingent upon FDEP approval of the final Site Rehabilitation Completion Report, IDW manifest, and project management documentation, with the task assignment completion date of June 7, 2024.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW680
DC017D Completion June 7, 2024
Arcadis will conduct groundwater monitoring from select wells at the site. All activities will be performed according to the February 15, 2024, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Arcadis U.S. Inc.
Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4379
7379 NW 36th Street, Miami, Miami-Dade County
Peerless Dry Cleaners
✔ $ 6,660.98
$ 6,660.98
Scope of Work
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2024.02.19 16:44:08 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.02.19 16:15:16 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Site Rehabilitation Completion Report/IDW manifest/Project Management 04/30/2024
FDEP approval of Site Rehabilitation Completion Report/IDW manifest/Project Management $ 6,660.98
$ 6,660.98
HW680
DC017D
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Peerless Dry Cleaners
FACID NO. 13-9501189; ERIC_4379
Miami, Miami-Dade County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC017D (HW680) DATE: February 16, 2024
Arcadis U.S. Inc. will perform groundwater monitoring from select wells at the site. A clean event during this sampling period is expected to bring the site to unconditional closure. All activities will be conducted in accordance with the February 15, 2024, Work Plan submitted by Doug McGlone of Arcadis.
The final task assignment total is $6,660.98. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Groundwater Monitoring Arcadis will sample six wells for drycleaning solvents. IDW will be drummed and disposed by a licensed waste hauler.
Subtask 3: Reporting Assuming the sampling event is clean, a Site Rehabilitation Completion Report recommending closure without conditions will be submitted as the final deliverable.
If the sampling event is not clean, a groundwater monitoring report will be submitted as the final deliverable and the site will be returned to an annual monitoring schedule.
Hours and costs are comparable to past task assignments of similar scope.
FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.
Date: 2/15/2024
Task #: SubTask 1 Project Management Site: Peerless Cleaners SubTask 2 Groundwater Monitoring
Activity/Phase: Annual NAM 2024 SubTask 3 Reporting Project Manager: Gus Suarez SubTask 4
SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$67.07 Project Manager McGlone, Douglas (DMc) 3 3.3 $85.87 Principal Engineer Suarez, Gus (GS) 0 0 0 0 0 $67.07 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0 $67.07 Principal Scientist McGlone, Douglas (DMc) 8 4 4 0 0 $39.34 Staff Scientist Riley, Joel (JR) 21 11 10 0 0 $39.67 Drafter/Designer Oliva, Brian (BO) 3 0 3 0 0 $34.40 Drafter/Designer Berndgen, Wendy (WDB) 0 0 0 0 0 $35.00 Document Technician Ballheim, Debra (DJB) 0 0 0 0 0 $30.00 Document Technician Embras, Susan (SRE) 0 0 0 0 0 $37.25 Project Assistant Cruz, Michele (MC) 6 3 3 0 0
Total Hours 41 3 18 20 0 0
Direct Labor $1,926.89 $221.68 $812.77 $892.44 $0.00 $0.00
Overhead 79.00% $1,522.25 $175.13 $642.09 $705.03 $0.00 $0.00 Gen & Admin 36.00% $693.68 $79.80 $292.60 $321.28 $0.00 $0.00 Fringe 37.10% $714.88 $82.24 $301.54 $331.10 $0.00 $0.00 Total Labor $4,857.70 $558.85 $2,049.00 $2,249.85 $0.00 $0.00
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 IDW Erwin $125.00 $125.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $125.00 $125.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $12.50 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $137.50 $0.00 $0.00 $0.00
Laboratory Analytical Costs $438.00 $438.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $150.00 $150.00 $0.00 $0.00 $0.00 Total Laboratory $588.00 $588.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $142.00 $142.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $290.00 $290.00 $0.00 $0.00 $0.00 Total Field Expenses $472.00 $472.00 $0.00 $0.00 $0.00
Subtotal $6,175.20 $558.85 $3,366.50 $2,249.85 $0.00 $0.00 Completion Fee $485.78 $55.89 $204.90 $224.99 $0.00 $0.00
Total Estimated Cost $6,660.98 $614.74 $3,571.40 $2,474.84 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Peerless Cleaners SUBTASK 2: Groundwater Monitoring
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
GW sampling
Principal (DMc) Access; technical analysis; oversight with field crew 4
Staff Scientist (JR) Prp for field work (1 hr), mob/demob (2 hr); round of WLs, purge & sample 6 wells (6 hrs) , pack/ship, IDW stage (2 hrs) 11
Project Assistant (MC) Process field notes, sample tracking, data entry 3
TOTAL LABOR 18
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 1 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals NAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00 NAME OF COMPANY Drilling services (DPT, MAG wells, SBs, VPs) $0.00 Lump Sum 0 $0.00 Erwin IDW $125.00 Drum 1 $125.00
Handling Fee $0.00 Per Month 0 $0.00
Total Services: $125.00
TOTAL $125.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons only) 8260 Aqueous $73.00 1.00 6 $438.00Dissolved Solids, Total SM2540 C Aqueous $16.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $438.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $150.00
TOTAL LAB $588.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals
Total PPE: $0.00 Expendables
Miscellaneous Expendables $40.00 Per Day 1 $40.00 Total Expendables: $40.00
Equipment Items
Tubing, Poly/HDPE $0.30 Per Foot 90 $27.00 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 5 $15.00 55-gallon Drum $100.00 Each 1 $100.00
Total Equipment Items: $142.00 Equipment KitsSite Reconnaissance Kit $150.00 Day 0 $0.00
Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00 Deep Groundwater Sampling Kit $415.00 Day $0.00Shallow Groundwater / Soil Vapor Screening Kit $290.00 Day 0 $0.00
Total Equipment Kits: $290.00
TOTAL EQUIPMENT $472.00
SITE : Peerless Cleaners
SUBTASK 3: Reporting
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)
Principal (DMc) Technical analysis; sign and seal report 4
Staff Scientist (JR) Data evaluation and preparation of report 10
Project Assistant (MC) Process field notes, data entry, report assembly, ADaPT processing/upload 3
Drafter/Designer (BO) Figures production for report 3
TOTAL LABOR 20
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 1 $0.00
Total Equip.: $0.00
Services Procurement Name Purpose Rate Units Usage Totals
Handling Fee $0.00 Per Month 1 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons only) 8260 Aqueous $73.00 1.00 0 $0.00
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00 Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00
Total Equipment Items: $0.00 Equipment KitsSite Reconnaissance Kit $150.00 Day 0 $0.00
Total Equipment Kits: $0.00
TOTAL EQUIPMENT $0.00
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
Arcadis U.S., Inc.
1500 Gateway Boulevard
Suite 200
Boynton Beach
Florida 33426
Tel 561 697 7000
Fax 561 369 4731 www.arcadis.com
Page:
1/2
Theresa Pepe, Contract Manager Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Subject:
Annual Groundwater Monitoring Proposal Peerless Cleaners #3416, ERIC_4379 7379 NW 36th Street, Miami, Florida
Dear Ms. Pepe:
Arcadis U.S., Inc. (Arcadis) is pleased to provide the Florida Department of Environmental Protection (FDEP) this proposal for the Peerless Cleaners #3416 site, located in Miami, Miami-Dade County, Florida. This proposal includes annual groundwater monitoring and reporting.
ANNUAL GROUNDWATER MONITORING
Arcadis will perform the following groundwater monitoring activities:
• Measure depth to water in all site wells;
• Field water quality (pH, temperature, conductivity, dissolved oxygen and ORP) in six monitor wells (MW-1, MW-2, MW-6, MW-7, MW-9, and MW-10);
and
• Purging and sampling six shallow-depth monitor wells (MW-1, MW-2, MW-6, MW-7, MW-9, and MW-10). Purge water will be containerized for offsite disposal. A site figure of well locations is presented herein.
ENVIRONMENTAL
Date:
February 15, 2024
Contact:
Douglas J. McGlone
Phone:
561-663-7978
Email:
douglas.mcglone@arcadis.com
Our ref:
Peerless
Florida License Numbers
Engineering
Geology
GB564
Surveying
LB7062
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
arcadis.com C:\Users\Pepe_T\Desktop\Peerless Cleaners Annual Monitoring Proposal 2-15-24.docx
Theresa Pepe
FDEP
February 15, 2024
Page:
2/2
ANNUAL GROUNDWATER MONITORING REPORT
• Following completion of the monitoring event, an Annual Groundwater Monitoring Report will be prepared and submitted to the FDEP. The report will summarize the data collected and present appropriate recommendations for additional actions and/or closure.
SCHEDULE
Arcadis will schedule field activities immediately upon receipt of the Task Assignment. The deliverable will be submitted within 45 days of completion of field work.
COST ESTIMATE
A Cost Estimate Form and Level of Effort (CEF-LOE) Form are attached for the above scope of work (Attachment 1).
CLOSING REMARKS
Arcadis appreciates the opportunity to assist the FDEP at this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.
Sincerely, Arcadis U.S., Inc.
Douglas J. McGlone, P.G.
Principal Geologist
Attachments:
CEF-LOE
Invoice
Date
12/18/2023
Invoice #
AUS088
Arcadis U.S., Inc.
Attn: Miranda Silano 1705 Metropolitan Boulevard Tallahassee, FL 32308 invoices_us@arcadis.com
P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511 ErwinRemediation@gmail.com
Site City
Pembroke Pines
Site Name
Aristocrat Cleaners
Total
Quantity Rate AmountDate Item
1 125.00 125.0012/11/2023 Drum Disp - Non-Haz Groundwater
$125.00
| Peerless Cleaners #3416 Annual Monitoring Proposal 4-18-2022.pdf |
| Annual Groundwater Monitoring |
| Annual Groundwater Monitoring Report |
| Schedule |
| Cost Estimate |
| Closing Remarks |
| HW680_DC017D ns.pdf |
| Subtask 1: Project Management |
| Peerless Cleaners Annual Monitoring Proposal 2-15-24.pdf |
| Annual Groundwater Monitoring |
| Annual Groundwater Monitoring Report |
| Schedule |
| Cost Estimate |
| Closing Remarks |