This is a Task Assignment (TA) document executed between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S., Inc. for environmental remediation services at the Miami Dry Cleaners facility located at 810 West Flagler Street, Miami, Miami-Dade County, Florida. The task assignment is designated as TA Number DC015A under underlying Contract Number HW680. The FDEP Project Manager is Theresa Pepe, and the Contractor's Project Manager is Gus Suarez. The document is dated April 13, 2022, with a completion date of November 30, 2022.

The contract requires Arcadis to conduct six months of Operation and Maintenance (O&M) activities at the site according to the April 12, 2022 Work Plan. Services include four subtasks: Project Management, Year 1 Quarter 4 O&M (April-June 2022) with a semi-annual report and groundwater/vapor sampling, Year 2 Quarter 1 O&M (July-September 2022) with quarterly email updates, and Utilities Management. Compensation consists of a Fixed Unit Rate of $22,321.58 and Cost Reimbursement of $3,900.00 for utilities, totaling $26,221.58. Utility invoices are invoiced on a Cost Plus basis with a $60 handling fee per month, not to exceed $1,950.00 per three-month period. The contract includes four invoice milestones contingent upon FDEP approval: $12,138.27 for the semi-annual O&M report, $2,010.00 for utility invoices (3 months), $10,063.31 for quarterly O&M email update, and $2,010.00 for additional utility invoices. No funding information has been specified in the document.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001A.pdf PDF
CN-370000-HW680-DC001D.pdf PDF
CN-370000-HW680-DC002A.pdf PDF
CN-370000-HW680-DC004D.pdf PDF
CN-370000-HW680-DC006A.pdf PDF
CN-370000-HW680-DC006B.pdf PDF
CN-370000-HW680-DC013C.pdf PDF
CN-370000-HW680-DC014E.pdf PDF
CN-370000-HW680-DC014F.pdf PDF
CN-370000-HW680-DC016B.pdf PDF
CN-370000-HW680-DC017B.pdf PDF
CN-370000-HW680-DC017C.pdf PDF
CN-370000-HW680-DC018B.pdf PDF
CN-370000-HW680-DC018C.pdf PDF
CN-370000-HW680-DC020A.pdf PDF
CN-370000-HW680-DC021D.pdf PDF
CN-370000-HW680-DC022C.pdf PDF
CN-370000-HW680-DC024B.pdf PDF
CN-370000-HW680-DC027A.pdf PDF
CN-370000-HW680-DC028A.pdf PDF
CN-370000-HW680-DC028B.pdf PDF
CN-370000-HW680-DC030B.pdf PDF
CN-370000-HW680-DC031B.pdf PDF
CN-370000-HW680-DC031E.pdf PDF
CN-370000-HW680-DC034B.pdf PDF
CN-370000-HW680-DC035B.pdf PDF
CN-370000-HW680-DC035C.pdf PDF
CN-370000-HW680-DC036B.pdf PDF
CN-370000-HW680-DC039A.pdf PDF
CN-370000-HW680-DC039C.pdf PDF
CN-370000-HW680-DC039D.pdf PDF
CN-370000-HW680-DC03ACO2.pdf PDF
CN-370000-HW680-DC042A.pdf PDF
CN-370000-HW680-DC043A.pdf PDF
CN-370000-HW680-DC044A.pdf PDF
CN-370000-HW680-DC046A.pdf PDF
CN-370000-HW680-DC047A.pdf PDF
CN-370000-HW680-DC06ACO1.pdf PDF
CN-370000-HW680-DC06ACO2.pdf PDF
CN-370000-HW680-DC09BCO1.pdf PDF
CN-370000-HW680-DC10BCO4.pdf PDF
CN-370000-HW680-DC11ACO1.pdf PDF
CN-370000-HW680-DC11CCO2.pdf PDF
CN-370000-HW680-DC14BCO2.pdf PDF
CN-370000-HW680-DC14BCO3.pdf PDF
CN-370000-HW680-DC14BCO4.pdf PDF
CN-370000-HW680-DC14BCO9.pdf PDF
CN-370000-HW680-DC14FCO1.pdf PDF
CN-370000-HW680-DC14FCO2.pdf PDF
CN-370000-HW680-DC14FCO4.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW680

DC015A Completion November 30, 2022

Arcadis will conduct six months of O&M activities at the site. Work will be performed according to the April 12, 2022, Work Plan submitted by Arcadis.

The payment of utility invoices is the only portion of this Task Assignment that is Cost Plus.

Theresa Pepe 850-245-8966 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Arcadis U.S. Inc.

Arcadis U.S. Inc.

Gus Suarez 813-205-4703

ERIC_4372

810 West Flagler Street, Miami, Miami-Dade County

Miami Dry Cleaners

✔ $ 22,321.58 ✔ $ 3,900.00

$ 26,221.58

Scope of Work

Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2022.04.13 15:49:52 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.04.13 14:27:26 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Year 1, Quarter 4 - Semi-Annual O&M report 07/22/2022

3 months Utility Invoices 08/12/2022

Year 2, Quarter 1 - Quarterly O&M email update/IDW manifest/Project Management 10/21/2022

3 months utility invoices 11/10/2022

FDEP approval of Year 1, Quarter 4 - Semi-Annual O&M report $ 12,138.27

FDEP approval of 3 months utility invoices Utilities (Cost Plus Fixed Fee) = not to exceed $1,950.00 Utilities Handling Fee = $60

$ 2,010.00

FDEP approval of Year 2, Quarter 1 - Quarterly O&M email update/IDW Manifest/Project Management $ 10,063.31

FDEP approval of 3 months utility invoices Utilities (Cost Plus Fixed Fee)= not to exceed $1,950.00 Utilities Handling Fee = $60

$ 2,010.00

$ 26,221.58

HW680

DC015A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Negotiation File Miami Dry Cleaners Facility ID No. 13-9501077; ERIC_4372 Miami, Miami-Dade County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment DC015A (HW680) DATE: April 13, 2022

Task Assignment DC015A is for six months of O&M activities at Miami Dry Cleaners.

Additional information is described in the April 12,2022, Work Plan from Doug McGlone of Arcadis.

The final task assignment equals $26,221.58. Arcadis may invoice according to the attached schedule.

Specific negotiated subtasks are as follows:

Subtask 1: Project Management This subtask is calculated automatically based on a percentage of total labor.

Subtask 2: Quarterly O&M & Reporting This subtask provides costs for one quarter (April - June 2022) of monthly O&M site visits including groundwater and vapor sampling per the approved ISR Work Plan.

Costs for telemetry and IDW are included in this subtask. One Semi-annual report will be submitted to FDEP summarizing the above data.

Subtask 3: Quarterly O&M & Reporting This subtask provides costs for one quarter (July - September 2022) of monthly O&M site visits including vapor sampling. One brief email update will be submitted to FDEP summarizing the above data.

Subtask 4: Utilities This subtask provides costs for six months of utilities and associated handling fees.

Arcadis will only invoice for actual charges and any remainder will be adjusted by change order.

FDEP COST ESTIMATE

Contractor: Arcadis, U.S., Inc.

Date: 4/12/2022

Task #: SubTask 1 Project Management

Site: Miami Dry Cleaner SubTask 2 Yr1 Qtr 4 O&M

Activity/Phase: O&M SubTask 3 Yr 2 Qtr 1 O&M

Project Manager: Doug McGlone SubTask 4 Utilities

SubTask 5

Totals 1 2 3 4 5

Labor Rate Category

$79.12 Project Manager Suarez, Gus (GS) 9 9.1

$61.38 Principal Scientist McGlone, Douglas (DMc) 9 6 3 0 0$61.32 Principal Scientist Dellay, Leah (LD) 0 0 0 0 0

$43.88 Project Engineer Hays, Timothy (TH) 28 15 13 0 0

$39.34 Staff Scientist Riley, Joel (JR) 81 45 36 0 0

$39.67 Drafter/Designer Oliva, Brian (BO) 10 6 4 0 0$30.99 Drafter/Designer Richards, Jim (JR) 0 0 0 0 0

$26.52 Document Technician Embras, Susan (SRE) 0 0 0 0 0

$30.96 Project Assistant McLemore, Michele (MMc) 6 3 3 0 0

Total Hours 143 9 75 59 0 0

Direct Labor $6,271.57 $721.51 $3,127.68 $2,422.38 $0.00 $0.00

Overhead 79.00% $4,954.54 $569.99 $2,470.87 $1,913.68 $0.00 $0.00

Gen & Admin 36.00% $2,257.76 $259.74 $1,125.96 $872.06 $0.00 $0.00

Fringe 37.10% $2,326.75 $267.68 $1,160.37 $898.70 $0.00 $0.00

Total Labor $15,810.62 $1,818.92 $7,884.88 $6,106.82 $0.00 $0.00

Travel

Vehicle Rental $840.00 $480.00 $360.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $840.00 $480.00 $360.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $150.00 $150.00 $0.00 $0.00 $0.00

Utilities $3,900.00 $0.00 $0.00 $3,900.00 $0.00 telemetry $299.00 $299.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $4,349.00 $449.00 $0.00 $3,900.00 $0.00

Handling Fee $164.90 $44.90 $0.00 $120.00 $0.00

Total Subcontractor Cost $4,513.90 $493.90 $0.00 $4,020.00 $0.00

Laboratory

Analytical Costs $911.00 $711.00 $200.00 $0.00 $0.00

Sample Shipping $370.00 $260.00 $110.00 $0.00 $0.00

Total Laboratory $1,281.00 $971.00 $310.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $280.00 $160.00 $120.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $1,365.00 $1,035.00 $330.00 $0.00 $0.00

Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00

Equipment (Other) - MAGS; recon $450.00 $225.00 $225.00 $0.00 $0.00

Total Field Expenses $2,195.00 $1,520.00 $675.00 $0.00 $0.00

Subtotal $24,640.52 $1,818.92 $11,349.78 $7,451.82 $4,020.00 $0.00

Completion Fee $1,581.06 $181.89 $788.49 $610.68 $0.00 $0.00

Total Estimated Cost $26,221.58 $2,000.81 $12,138.27 $8,062.50 $4,020.00 $0.00

REV: 02/03 CEF ARCADIS Page 1

SITE : Miami Dry Cleaner SUBTASK 2: Yr1 Qtr 4 O&M

DATE: 4/12/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Yr1 Qtr 4 O&M Principal / DMc PG review of data, review report, owner/operator discussions/coordination, utilities 6 Staff Scientist / JR Mob (2 hrs x 3), Month 10-12 O&M visits (30 hrs), sample influent 36 Staff Scientist / JR Mob (2 hrs), sample seven monitor wells (7 hrs), pack ship (1 hr) 9 Project Engineer / TH System performance / data review, report prep/submittal 15 Drafter/Designer / BO Figures production for O&M report 6 Project Assistant / MMc Process field notes, sample tracking, data entry, report assembly, submittal 3

TOTAL LABOR 75

VEHICLE TYPE RATE UNIT USEAGE

Van/Truck $120.00 Per Day 4 $480.00 $480.00

TOTAL VEHICLE $480.00

SUBCONTRACTOR COSTS

Services Procurement

Name Purpose Rate Units Usage Totals NAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00

$0.00 Lump Sum 0 $0.00 Clark Environmental IDW Disposal $150.00 Drum 1 $150.00 Sensaphone Telemetry $299.00 Lump Sum 1 $299.00

Total Services: $449.00

TOTAL $449.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260 Aqueous $73.00 1.00 7 $511.00 VOC Soil Vapor TO-15 Vapor $200.00 1.00 1 $200.00 Priority Pollutant Organics Full Suite Aqueous $735.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $711.00

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00

Total Shipping: $260.00

TOTAL LAB $971.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals Total PPE: $0.00

Expendables Miscellaneous Expendables $40.00 Per Day 4 $160.00

Total Expendables: $160.00 Equipment ItemsTubing, Poly/HDPE $0.30 Per Foot 0 $0.00 55-gallon Drum $100.00 Each 1 $100.00 PID (ppbRae) $110.00 Per Day 3 $330.00

Total Equipment Items: $430.00 Equipment Kits Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00 Deep Groundwater Sampling Kit $415.00 Day 1 $415.00 Construction/O&M Supplies $75.00 Day 3 $225.00

Total Equipment Kits: $930.00

TOTAL EQUIPMENT $1,520.00

SITE : Miami Dry Cleaner SUBTASK 3: Yr 2 Qtr 1 O&M

DATE: 4/12/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Reporting Principal / DMc PG review of data, review report and email update 3 Staff Scientist / JR Mob (2 hrs x 3), month 13-15 O&M visits (30 hrs), sample influent 36 Project Engineer / TH E-results, system performance, data review, prep submittal 13 Drafter/Designer / BO Figure propduction for O&M update 4 Project Assistant / MMc Process field notes, data entry, sample tracking 3

TOTAL LABOR 59

VEHICLE TYPE RATE UNIT USEAGE

Van/Truck $120.00 Per Day 3 $360.00 $360.00

TOTAL VEHICLE $360.00

SUBCONTRACTOR COSTS

Services Procurement

Name Purpose Rate Units Usage Totals NAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00 NAME OF COMPANY Drilling services (DPT, MAG wells, SBs, VPs) $0.00 Lump Sum 0 $0.00

IDW $150.00 Drum 0 $0.00 NAME OF COMPANY On-site Mobile Laboratory analysis $0.00 Lump Sum 0 $0.00 NAME OF COMPANY Utility Locate / GPR Survey $0.00 Lump Sum 0 $0.00 FPL Utilities -Power $50.00 Per Month 0 $0.00

Handling Fee $20.00 Per Month 0 $0.00

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260 Aqueous $73.00 1.00 0 $0.00 VOC Soil Vapor TO-15 Vapor $200.00 1.00 1 $200.00 Priority Pollutant Organics Full Suite Aqueous $735.00 1.00 0 $0.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $200.00 Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00

Total Shipping: $110.00

TOTAL LAB $310.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals Total PPE: $0.00

Expendables Miscellaneous Expendables $40.00 Per Day 3 $120.00

Total Expendables: $120.00 Equipment Items PID (ppbRae) $110.00 Per Day 3 $330.00

Total Equipment Items: $330.00 Equipment KitsSite Reconnaissance Kit $150.00 Day 0 $0.00 Construction/O&M Supplies $75.00 Day 3 $225.00

Total Equipment Kits: $225.00

TOTAL EQUIPMENT $675.00

SITE :

SUBTASK 4:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

(Subtask Title)

Principal 0

Senior Sci 0

Staff Sci 0

Technician 0

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

Meals

Category/Staff Rate Unit Usage Totals

$36.00 Per Day 0 $0.00

$36.00 Per Day 0 $0.00

Hotel

Category/Staff Rate Unit Usage Totals

$150.00 Per Day 0 $0.00

$150.00 Per Day 0 $0.00

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals $0.00 Per Day 1 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals FPL Utilities $650.00 Per Month 6 $3,900.00

Handling Fee $20.00 Per Month 6 $120.00

Total Services: $4,020.00

TOTAL $4,020.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples TotalsVOC 8260 Aqueous $150.00 1.00 0 $0.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage TotalsPPE Level D $35.00 Per Man Day 0 $0.00

Total PPE: $0.00

Expendables

Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00

Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00

Total Equipment Items: $0.00

Equipment Kits

Total Equipment Kits: $0.00

TOTAL EQUIPMENT $0.00

This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.

arcadis.com C:\Users\Pepe_T\Desktop\Miami DC SVE 2022 OMM Proposal_041222.docx

Page:

1/3

Ms. Theresa Pepe, Contract Manager Hazardous Waste Cleanup Section Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Subject:

Proposal for Six Months of Operation and Maintenance Miami Dry Cleaner (ERIC_4370), 8410 West Flagler Street, Miami, Florida

Dear Ms. Pepe:

Arcadis U.S., Inc. (Arcadis) is pleased to submit this proposal/cost estimate for the Miami Dry Cleaner Site, located in Miami, Miami-Dade County, Florida. This proposal includes operation, maintenance and monitoring (OM&M) of the soil vapor extraction (SVE) system for six months (April – September 2022), vapor and groundwater sampling, one semi-annual remedial action status report and one e-mail update. This proposal includes a description of the proposed scope of services, and an estimated cost and schedule for their completion.

TASK 1: PROJECT MANAGEMENT

As specified by FDEP, project management is calculated automatically in the CEF as the first subtask.

TASK 2 THROUGH TASK 3: GENERAL OM&M ACTIVITIES

In accordance with the approved ISRWP, the SVE system’s performance will be monitored monthly for six months (April – September 2022). The following will be performed during each monthly event:

• The ROI of the SVE system will be measured by sequentially isolating the

SVE wells and measuring the vacuum influence of the nearby SVE or monitor wells.

• Vapor extraction flow rate and vacuums will be recorded using meters and gauges located within the system. Adjustments will be made as necessary to optimize system performance.

ENVIRONMENTAL

Date:

April 12, 2022

Contact:

Doug McGlone

Phone:

561.662.7978

Email:

Douglas.mcglone@arcadis.com

Our ref:

30041815

Florida License Numbers

Engineering

Geology

GB564

Surveying

LB7062

The extraction blower will be inspected and adjusted for proper operation, including periodic oil changes, grease, and filter replacement.

• The SVE system will be operated to minimize the capture and entrainment of groundwater.

• The system interlocking controls and fail-safe mechanisms will be inspected for proper operation

Recovered vapors from the SVE system will be monitored quarterly. The SVE vapor sample will be collected from system influent to calculate mass removal.

TASK 2: SVE SYSTEM OM&M YEAR 1 QUARTER 4 (APRIL THROUGH JUNE

2022)

Task 2 consists of system monthly OM&M visits for one quarter (Month 10 through Month 12) and semi-annual reporting. The SVE vapor sample will be collected from system influent to calculate mass removal. Groundwater samples will be collected from seven monitor wells (MW001 through MW005, MW002I and MW-1D) for analysis of VOHs by EPA Test Method 8260. Purge water will be containerized for offsite disposal.

A Semi-Annual OM&M Report will be submitted at the completion of the quarter and include six months of system operational data (i.e., January through June 2022). The semi-annual report will include results and data analysis of the vapor and groundwater monitoring events and recommendations to optimize system operation.

TASK 3: SVE SYSTEM OM&M YEAR 2 QUARTERS 1 (JULY THROUGH

SEPTEMBER 2022)

Task 3 consists of system monthly OM&M visits for one quarter (Month 13 through Month 15) and quarterly reporting. A vapor sample will be collected from the influent sample port in a Summa™ canister and analyzed for VOHs using EPA Method TO-15 to calculate mass removal.

A Quarterly email update consisting of tables and figures will be submitted to the FDEP following the September 2022 OM&M event.

TASK 4: UTILITIES MANAGEMENT

This task will be used to manage and process FPL invoices for six months of system operation included in this proposal. Based upon prior FPL invoices, it is anticipated that the utility budget be estimated at $650 per month. A monthly handing fee of $20 per month is also included. Actual utility costs will be invoiced, and any differences will be adjusted through Task Assignment Change Orders.

SCHEDULE

Arcadis will begin implementing the OM&M activities in October 2021 upon receipt of a Task Assignment (TA) from the FDEP. The following deliverables and estimated timeframe for completion are included below:

Deliverable Anticipated Submittal

Date

Year 1 Quarter 3 & 4 Semi-Annual Remedial Action System Status Report July 2022

Year 2 Quarter 1 Email Update October 2022

CLOSING REMARKS

Arcadis appreciates the opportunity to assist the FDEP at this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.

Sincerely, Arcadis U.S., Inc.

Doug McGlone, P.G.

Principal Scientist.

Enclosures:

CEF-LOE

HW680_DC015A negsum.pdf
Subtask 1: Project Management
Subtask 2: Quarterly O&M & Reporting
Subtask 3: Quarterly O&M & Reporting
Subtask 4: Utilities
Miami DC SVE 2022 OMM Proposal_041222.pdf
task 1: Project Management
task 2 through task 3: General OM&M Activities
task 2: SVE System OM&M Year 1 Quarter 4 (April through June 2022)
task 3: SVE System OM&M Year 2 Quarters 1 (July through September 2022)
task 4: Utilities Management
Schedule
Closing Remarks

File details come from the government source that posted it. Updated .