This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S., Inc. for remedial system maintenance services at the Dry Cleaning Depot facility located at 3470 W. Broward Boulevard in Fort Lauderdale, Broward County, Florida. The task assignment is designated as DC014C under Contract Number HW680 and was executed in June 2023. The FDEP project manager is Theresa Pepe, while Arcadis's project manager is Gus Suarez.
The scope of work consists of four quarters of System Shutdown Preventative Maintenance (SSPM) for the soil vapor extraction remedial system, performed in accordance with FDEP guidelines and a June 4, 2023 work plan submitted by Arcadis. The work is structured across three subtasks: project management (automatically calculated as a percentage of total labor), four quarterly SSPM events with email updates documenting site conditions, and utility account maintenance including electricity costs and handling fees. The task assignment is valued at $7,380.00, comprised of $6,780.00 in fixed unit rates and $600.00 in cost reimbursement for utility invoices not to exceed $150.00 per month with a $60.00 handling fee. Invoicing occurs upon FDEP approval of completed quarterly maintenance activities and utility documentation, with a completion date of June 28, 2024.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW680
DC014C Completion June 28, 2024
Arcadis will complete four quarters of remedial system shutdown preventive maintenance consistent with FDEP guidance. Activities will be performed according to the June 4, 2023, Work Plan submitted by Arcadis.
The payment of utility invoices is the only portion of this Task Assignment that is Cost Plus.
Theresa Pepe 850-245-8966 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Arcadis U.S. Inc.
Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4160
3470 W Broward Blvd, Fort Lauderdale, Broward County
Dry Cleaning Depot
✔ $ 6,780.00 ✔ $ 600.00
$ 7,380.00
Scope of Work
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2023.06.22 08:41:01 -04'00'
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.06.20 13:32:20 -04'00'
N/A
Task Assignment Notification/Change Order
Deliverables and Invoice Schedule Attachment
Contract Number: HW680
Task Assignment #: DC014C
Deliverables:
Deliverable Deliverable Due Date
One quarter System Shutdown Maintenance & email update 31-Jul-23
3 months utility invoices 31-Aug-23 One quarter System Shutdown Maintenance & email update 31-Oct-23 3 months utility invoices 30-Nov-23 One quarter System Shutdown Maintenance & email update 31-Jan-24 3 months utility invoices 29-Feb-24
One quarter System Shutdown Maintenance & email update/Project Management 30-Apr-24 3 months utility invoices 31-May-24
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
FDEP approval of One quarter System Shutdown Maintenance & email update $1,473.94
FDEP approval of utility invoices
Utilities (Cost Plus Fixed Fee) = not to exceed $150.00
Utilities Handling Fee = $60.00
$210.00
One quarter System Shutdown Maintenance & email update $1,473.94
FDEP approval of utility invoices
Utilities (Cost Plus Fixed Fee) = not to exceed $150.00
Utilities Handling Fee = $60.00
$210.00
One quarter System Shutdown Maintenance & email update $1,473.94
FDEP approval of utility invoices
Utilities (Cost Plus Fixed Fee) = not to exceed $150.00
Utilities Handling Fee = $60.00
$210.00
One quarter System Shutdown Maintenance & email update/Project Management $2,118.18
FDEP approval of utility invoices
Utilities (Cost Plus Fixed Fee) = not to exceed $150.00
Utilities Handling Fee = $60.00
$210.00
TOTAL COST $7,380.00
BWC TAFORM 01/18
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Dry Cleaning Depot
FACID NO. 06-9502029; ERIC_4160
Fort Lauderdale, Broward County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment DC014C (HW680) DATE: June 14, 2023
Arcadis U.S., Inc. will conduct four quarters of System Shutdown Preventative Maintenance (SSPM) for the remedial system on site. This work will be performed in accordance with FDEP guidelines and the June 4, 2023, Work Plan submitted by Arcadis.
The final task assignment equals $7,380.00. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated based on a percentage of total labor.
Subtask 2: Four Quarters SSPM/Email updates Per FDEP’s engineer, the remedial system is presently inactive but may be operated again for vapor control if bioremediation injections are performed. This subtask provides costs for four quarters of System Shutdown Preventative Maintenance. A brief email update regarding site/system conditions will be submitted as the deliverable after each event.
Subtask 3: Utilities Subtask three includes hours for utility invoices as well as the appropriate handling fees. Arcadis will only invoice for actual charges and any remainder will be adjusted via change order. Hours and costs are comparable to past task assignment of similar work.
FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.
Date: 6/4/2023
Task #: SubTask 1 Project Management Site: Dry Cleaning Depot SubTask 2 SSPM
Activity/Phase: SSPM SubTask 3 Utilities Project Manager: Doug McGlone SubTask 4
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category
$67.07 Project Manager McGlone, Douglas (DMc) 4 3.5
$85.87 Principal Engineer Suarez, Gus (GS) 0 0 0 0 0
$67.07 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0
$67.07 Principal Scientist McGlone, Douglas (DMc) 8 8 0 0 0$66.87 Principal Scientist Dellay, Leah (LD) 0 0 0 0 0
$39.34 Staff Scientist Riley, Joel (JR) 28 28 0 0 0
$39.67 Drafter/Designer Oliva, Brian (BO) 0 0 0 0 0
$34.40 Drafter/Designer Berndgen, Wendy (WDB) 0 0 0 0 0
$35.00 Document Technician Ballheim, Debra (DJB) 0 0 0 0 0
$30.00 Document Technician Embras, Susan (SRE) 0 0 0 0 0
$37.25 Project Assistant Cruz, Michele (MC) 4 4 0 0 0
Total Hours 44 4 40 0 0 0
Direct Labor $2,019.40 $232.32 $1,787.08 $0.00 $0.00 $0.00
Overhead 79.00% $1,595.32 $183.53 $1,411.79 $0.00 $0.00 $0.00
Gen & Admin 36.00% $726.99 $83.64 $643.35 $0.00 $0.00 $0.00
Fringe 37.10% $749.20 $86.19 $663.01 $0.00 $0.00 $0.00
Total Labor $5,090.91 $585.68 $4,505.23 $0.00 $0.00 $0.00
Travel
Vehicle Rental $480.00 $480.00 $0.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00
Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $480.00 $480.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
EESI $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW EnviroServe $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $600.00 $0.00 $600.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $600.00 $0.00 $600.00 $0.00 $0.00
Handling Fee $240.00 $0.00 $240.00 $0.00 $0.00
Total Subcontractor Cost $840.00 $0.00 $840.00 $0.00 $0.00
Laboratory
Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00
Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $160.00 $160.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other) $300.00 $300.00 $0.00 $0.00 $0.00
Total Field Expenses $460.00 $460.00 $0.00 $0.00 $0.00
Subtotal $6,870.91 $585.68 $5,445.23 $840.00 $0.00 $0.00
Completion Fee $509.09 $58.57 $450.52 $0.00 $0.00 $0.00
Total Estimated Cost $7,380.00 $644.25 $5,895.75 $840.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Dry Cleaning Depot
SUBTASK 2: SSPM
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)
Principal (DMc) Field Support, site owner/tenant access, reporting on quarterly basis 8
Project Engineer (TH) 0
Staff Scientist (JR) 4 events: field prep (1 hr), mob/demob (2 hrs), SSPM activities (4 hrs) 28
Project Asst (MMc) Process field notes, data entry 4
Drafter/Designer(BO) 0
TOTAL LABOR 40
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 4 $480.00 $480.00
TOTAL VEHICLE $480.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel
Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals
EESI AWS $2,000.00 Per Day 0 $0.00
Total Equip.: $0.00
Services Procurement
Name Purpose Rate Units Usage Totals
NAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00NAME OF COMPANY Drilling services (DPT, MAG wells, SBs, VPs) $0.00 Lump Sum 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs
Parameter Method Media Rate Turn Around Total Samples Totals
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals
Total PPE: $0.00
Expendables
Miscellaneous Expendables $40.00 Per Day 4 $160.00
Total Expendables: $160.00
Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00
Total Equipment Items: $0.00
Equipment Kits
Construction/O&M Supplies $75.00 Day 4 $300.00
Total Equipment Kits: $300.00
TOTAL EQUIPMENT $460.00
SITE : Dry Cleaning Depot
SUBTASK 3: Utilities
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
(Subtask Title)
Principal (DMc) 0
Project Engineer (TH) 0
Staff Scientist (JR) 0
Project Asst (MMc) 0
Drafter/Designer(BO) 0
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00
Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
Meals
Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel
Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00
$150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals
$0.00 Per Day 0 $0.00
Total Equip.: $0.00
Services Procurement
Name Purpose Rate Units Usage TotalsNAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00
NAME OF COMPANY Utilities -Power $50.00 Per Month 12 $600.00
Handling Fee $20.00 Per Month 12 $240.00
Total Services: $840.00
TOTAL $840.00
LABORATORY COSTS
Analytical Costs
Parameter Method Media Rate Turn Around Total Samples TotalsVOC TO-15 Vapor $200.00 1.00 0 $0.00
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage TotalsPPE Level D $35.00 Per Man Day 0 $0.00
Total PPE: $0.00
Expendables
Miscellaneous Expendables $40.00 Per Day 0 $0.00
Total Expendables: $0.00
Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00
Total Equipment Items: $0.00
Equipment Kits
Total Equipment Kits: $0.00
TOTAL EQUIPMENT $0.00
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
Arcadis U.S., Inc.
3109 West Dr. Martin Luther King
Jr. Boulevard
Suite 350
Tampa
Florida 33607
Tel 813 903 3100
Fax 813 903 9115 www.arcadis.com
Page:
1/2
Theresa Pepe, Contract Manager Hazardous Waste Cleanup Section Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Subject:
Proposal for Soil Vapor Extraction System Shutdown Preventative Maintenance Dry Cleaning Depot, 3470 W. Broward Blvd, Ft. Lauderdale, Broward County, Florida
ERIC_4160
Dear Ms. Pepe:
Arcadis U.S., Inc. (Arcadis) is pleased to provide the Florida Department of Environmental Protection (FDEP) this proposal and cost estimate to perform four quarters of Soil Vapor Extraction (SVE) System Shutdown Preventative Maintenance (SSPM) events for the subject facility.
This proposal includes completion of quarterly SSPM events (July 2023, October 2023, January 2024, and April 2024). Per FDEP guidelines, the SVE system will be operated for approximately 2 hours during each SSPM visit to verify operational status. Additionally, the equipment compound will be cleaned and maintained during this period. An e-update notification of maintenance completion will be submitted within 30 days of completion of the field event.
Cost Estimate
A Cost Estimate Form and Level of Effort (CEF-LOE) to complete the proposed work is presented as Attachment 1. The CEF-LOE includes nominal costs to
ENVIRONMENT
Date:
June 4, 2023
Contact:
Doug McGlone
Phone:
561-662-7978
Email:
Douglas.mcglone@arcadis.com
Our ref:
WF900203.0009
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
arcadis.com C:\Users\Pepe_T\Desktop\DC Depot SSMP Proposal_6-4-23.docx
Ms. Theresa Pepe June 4, 2023
Page:
2/2 maintain the utility account for a period of 12 months (July 2023 through June 2024). The invoices will be submitted on a quarterly basis.
Closing Remarks
Arcadis appreciates the opportunity to assist the FDEP on this project. Please call if you have any questions or wish to discuss this proposal further.
Sincerely, Arcadis U.S., Inc.
Douglas J. McGlone, P.G.
Project Manager