This document is an AF Form 66 schedule of material submittals for the Installation of Electrical Drops Bldg 940, Joint Base Elmendorf-Richardson (JBER), AK project. The form outlines submittal requirements for the contractor, including a construction schedule due at NTP+15, health and safety plan due at NTP+15, QA/QC plan due at NTP+15, 100% design drawings including floor plans, elevations, sections, schedules and details due at NTP+90, foundation structural plans and details due at NTP+90, concrete and reinforcing steel drawings due at NTP+90, concrete mix design due at NTP+90, electrical cables, transformers, disconnects, receptacles, panels, breakers, conduits, garage controls, new building one line diagram, garage motors, DD1354 form before acceptance, and as-built drawings in AutoCAD due at final+7. The solicitation number is FA500021R0033 and is being conducted by the Department of the Air Force Pacific Air Forces for the Installation of Electrical Drops Bldg 940 at Joint Base Elmendorf-Richardson in Alaska.

View the file

Other versions and copies of AF Form 66

File Revision Posted Attached to
Attachment 2 AF Form 66.pdf Revision not stated REPAIR AC PAVING
AF form 66 Blank.pdf Revision not stated Demo Mini mute sites
Attach 9_AF Form 66 Submittal Register.pdf Revision not stated PKAA Dorm Water Damage Repair (Construction)
AF Form 66-EEPZ260842 Renovate Convert Comm to SAPR B730.xlsx Revision not stated B730 Renovate Convert Comm to SAPR
AF Form 66_EEPZ254664-B972 UOQ.xlsx Revision not stated B972 Renovate UOQ Community Commons
AF Form 66 B268.xlsx Revision not stated B268 Replace STUS Backup Generator
AF Form 66 B730.xlsx Revision not stated B730 - Renovate RM106 for Emergency Operations Center
AF Form 66.xlsx Revision not stated B836 Replace Electrical in Airfield Lighting Vault
AF Form 66 OSI Flooring.xlsx Revision not stated OSI B926 Flooring
EEPZ254660 Repair Control Tower HVAC B1806 - AF Form 66.xlsx Revision not stated B1806 Repair Control Tower HVAC
AF Form 66 Template.xlsx Revision not stated Replace AAS BAK-15 Controls, B2001, B2003
AF Form 66 EEPZ216808 Replace Security Forces Elevator B926.xlsx Revision not stated B926 Replace Security Forces Elevator
WT 17518487 AF Form 66.xlsx Revision not stated Repair Structural Fire Trainer B17903, 17904
AF Form 66.xlsx Revision not stated RENOVATE/CONVERT 50th 49th SQ OPS, B230
AF Form 66.xlsx Revision not stated T-6 Flightline Shacks
AF Form 66 Template.xlsx Revision not stated Replace Fire Alarms, Multi Facility
EEPZ248229 -- AF Form 66.xlsx Revision not stated Repair Kiddie Pool
Atch 2 AF Form 66.pdf Revision not stated Removal of Underground Storage Tank at Launch Facility E-10 (Laramie County, WY)
Attachment 4 - AF Form 66 Submittal Register.pdf Revision not stated Bldg 65 - Renovation of Telephone Office Area, FE Warren AFB, WY AMENDMENT 03
Attachment 7 - AF Form 66.xlsx Revision not stated Replace Chapel Windows B912
Show all 20

Who attaches AF Form 66

State Files
Iowa 1
Massachusetts 1

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LI

N

E N

U M

B ER Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.

C

ER

TI

F.

O F

C O

M

PL

IA

N

C E

SH

O

P D

R

AW

IN

G

S

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

TU

R

U R

'S R

EC

O

M M

EN

D

AT

IO

C

AT

AL

O

G D

AT

A

O &M

R

EC

O M

M

EN

D

AT

IO

N

S

C

AL

C U

LA

TI

O N

S

W

AR

R

AN

TY

D R

AW

IN

G S

R

EP

O R

T

TE

ST

R

ES

U

LT

S

R

EQ

U

IR

ED

S

U

BM

IS

SI

O N

D

AT

E

D

AT

E

TO

C O

N

TR

AC

TI

N G

D

AT

E

TO

C

IV

IL

E

N G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D

AT

E

SU

BM

IT

TA

L N

U M

BE

R

S

AP

PR

O

VE

D

D

IS

AP

PR

O

VE

D

C O

N

TR

AC

TO

R S

U

BM

IT

TA

L

FI

N

AL

A

PP

R

O

VA

L

NOTES

GENERAL

1 Project Specific Form 66 X NTP + 15 2 Construction Schedule X NTP + 15 3 Contractor's Health, Safety, and Environment Plan X NTP + 15 4 Contractor's QA/QC Plan X NTP + 15

5 Copy of Engineering License(s) of person or consultancy responsible for design X Design

DESIGN

All submissions to be provided electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) and 100% Design Drawings to include:

X NTP + 90

(100%)

7 Floor Plan, Elevations, Sections, Schedules, and Details X NTP + 90

8 Foundation Structural Plans and Details X X NTP + 90

9 STRUCTURAL

10 Concrete/Reinforcing Steel Drawings X NTP + 90 Design 11 Concrete Mix Design X NTP + 90

12 Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints X NTP + 90

13 Concrete Field Test Results X WITHIN 7

DAYS OF TEST

Anchor Bolt ICC Report X X NTP + 90

14 Slump Test Results & Concrete Truck Tickets (per truck) X WITHIN 7

DAYS OF TEST

15 28-Day Concrete Compressive Strength Test X WITHIN 7

DAYS OF TEST

16 ELECTRICAL

17 Cables (Electrical conductors, Controls) X NTP + 45 18 Transformer X X X X X X NTP + 45 19 Disconnect / Receptacles X X NTP + 45 20 Panels, Breakers X X

Grounding, Rods X X NTP + 45 Conduits X X X NTP + 45 Garage controls X X NTP + 45

21 New Building One line Diagram X X X NTP + 45 22 Garage Motors X X X NTP + 45

23 CLOSEOUT

24 O&M and Training Class For Disconnects X X X X X X X X X X X

SOLICITATION /CONTRACT NUMBERPROJECT NAME

INSTALL ELECTRICAL

DROPS BLDG 940

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

PROJECT NUMBER

HJZH 17-1426

AF FORM 66, OCT 99 Previous Edition Will Be Used

FA500021R0033

HJZH 17-1426 Install Electrical Drops

Attachment 7 - AF Form 66

LI

N

E N

U M

B ER Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.

C

ER

TI

F.

O F

C O

M

PL

IA

N

C E

SH

O

P D

R

AW

IN

G

S

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

TU

R

U R

'S R

EC

O

M M

EN

D

AT

IO

C

AT

AL

O

G D

AT

A

O &M

R

EC

O M

M

EN

D

AT

IO

N

S

C

AL

C U

LA

TI

O N

S

W

AR

R

AN

TY

D R

AW

IN

G S

R

EP

O R

T

TE

ST

R

ES

U

LT

S

R

EQ

U

IR

ED

S

U

BM

IS

SI

O N

D

AT

E

D

AT

E

TO

C O

N

TR

AC

TI

N G

D

AT

E

TO

C

IV

IL

E

N G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D

AT

E

SU

BM

IT

TA

L N

U M

BE

R

S

AP

PR

O

VE

D

D

IS

AP

PR

O

VE

D

C O

N

TR

AC

TO

R S

U

BM

IT

TA

L

FI

N

AL

A

PP

R

O

VA

L

NOTES

SOLICITATION /CONTRACT NUMBERPROJECT NAME

INSTALL ELECTRICAL

DROPS BLDG 940

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

PROJECT NUMBER

HJZH 17-1426

25 DD1354 X Before Acceptance

26 As Builts (electronic in AutoCAD ) X Final + 7

AF FORM 66, OCT 99 Previous Edition Will Be Used

FA500021R0033

HJZH 17-1426 Install Electrical Drops

Attachment 7 - AF Form 66