Attachment 4 - AF Form 66 Submittal - Lift Station.pdf
Air Force Form PDF 78 KB Posted
- Attached to
- B3456 Water Lift Station
- Solicitation number
- FA303021R0005
View the file
Other versions and copies of AF Form 66
Show all 20
Who attaches AF Form 66
| State | Files |
|---|---|
| Iowa | 1 |
| Massachusetts | 1 |
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FORM66.xls
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT: GAFB DoD Fire Academy B3453
Lift Station
SOLICITATION/CONTRACT NO.
TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
DATE CONTRACTOR
NOTIFIED
APPROVED DISAPPROVED
1 Para. 1.5.1 - Work Schedule 1 14 Days Prior
(e) GA
Para 1.10 Portable toilet locations 1 (e) FIO
Para 1.7.2 Company Safety Policy and Accident Prevention Plan
1 x (c) FIO
Para 1.13 List of Warranties and Certificates 1
Upon Final Acceptance by
Gov
GA
Para 1.14.1 Parking & Storage 1 (e) GA
Para 1.15.1.1 AF Form 103 Base Work Clearance Request
1 (e) GA
Para 1.15.2 Utility Outages 1 14 Days Prior
(e) GA
Para 1.16 Waste Disposal 1 (d) GA
Para 2.2 Hazardous Waste Records 2 x (b) GA
Para 2.3 Haz. Material List with worksheet for each SDS 2 x (c) GA
Para 2.6 Air Emissions Reports 2 x (b) GA
CONTRACT-
TOR RE-
SUBMIT-
TAL
FINAL
APPROVAL REMARKS
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW UP
IN
ST
RU
CT
IO
NS
SE
E
P
AR
A
OT
HE
RS
A
S
SP
EC
IF
IE
D
REQUIRED
SUBMISSION
DATE
RE
CO
MM
EN
DA
TI
ON
S
MA
NU
FA
CT
UR
ER
'S
W
AR
RA
NT
Y
OP
ER
AT
IN
G
SH
OP
D
RA
W
IN
GS
SA
MP
LE
S
CO
LO
R
SE
LE
CT
IO
N
MA
NU
FA
CT
UR
ER
'S
L I N E
N U M B E R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
(Ref spec & para no.)
CE
RT
IF
IC
AT
IO
N
OF
C
OM
PL
IA
NC
E
FORM66.xls
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT: GAFB DoD Fire Academy B3453
Lift Station
SOLICITATION/CONTRACT NO.
TO BE COMPLETED BY THE PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
DATE CONTRACTOR
NOTIFIED
APPROVED DISAPPROVED
CONTRACT-
TOR RE-
SUBMIT-
TAL
FINAL
APPROVAL REMARKS
DATE
RECEIVED
IN CON-
TRACTING
DATE TO
CIVIL
ENGINEER-
ING
RETURN
SUSPENSE
DATE
FOLLOW UP
IN
ST
RU
CT
IO
NS
SE
E
P
AR
A
OT
HE
RS
A
S
SP
EC
IF
IE
D
REQUIRED
SUBMISSION
DATE
RE
CO
MM
EN
DA
TI
ON
S
MA
NU
FA
CT
UR
ER
'S
W
AR
RA
NT
Y
OP
ER
AT
IN
G
SH
OP
D
RA
W
IN
GS
SA
MP
LE
S
CO
LO
R
SE
LE
CT
IO
N
MA
NU
FA
CT
UR
ER
'S
L I N E
N U M B E R
ITEM OR DESCRIPTION
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL
(Ref spec & para no.)
CE
RT
IF
IC
AT
IO
N
OF
C
OM
PL
IA
NC
E
Para 2.7 Construction Waste Management Form 2 (b) GA
Para 3.3 CPM:
Manufacturer's Specifications
(e) FIO
Para 3.3 CPM: As-built drawings 3 (e) FIO
AF Form 66, SEP 86
(a) As soon as possible but in no case later than 45 calendar days after NTP.
(b) Prior to Final Inspection.
(c) Prior to Use.
(d) As Required.
(e) Prior to start of work.
(f) Weekly.