Atch 2 AF Form 66.xlsx
XLSX spreadsheet 38 KB Posted
- Solicitation number
- FA461324Q0030
About this file
This document is an Attachment 2 - AF Form 66 that provides a Schedule of Material Submittals for the federal contract opportunity to "Replace Tile with Non-slip Tile at Pool Bldg. 217" at FE Warren AFB, WY.
The key details are:
- The contract number is FA461324Q0030.
- The required submittals include certification of compliance, shop drawings, samples, color selection, technical data, installation instructions, MSDS sheets, test reports, and manufacturer's warranty.
- Submittal due dates are 15-30 days post-award, with final approval required.
- The contract also requires a hazard safety plan, hazmat authorization sheet, and O&M documents to be submitted post-award.
- This AF Form 66 is intended to be completed by the Contractor and the Contract Administrator to track the submittal review process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Atch 3 Drawings.pdf | ||
| Atch 4 ACM Report.pdf | ||
| Solicitation - FA461324Q0030.pdf | ||
| Atch 5 Hazmat Auth Form.pdf | ||
| Atch 6 Salient Characteristics.xlsx | XLSX spreadsheet | |
| Atch 1 PWS 6 Aug 2024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 01
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT: Replace Tile with Non-slip Tile at Pool Bldg. 217 | SOLICITATION/CONTRACT NO. | ||
| AF FORM 66 | Page 1 of 1 | Tririga # GHLN23-8342 | ||
| TO BE COMPLETED BY ARCHITECT-ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR |
LINE NUMBER ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL CERTIFICATION OF COMPLIANCE SHOP DRAWINGS SAMPLES COLOR SELECTION SCHEDULE OF MATERIALS TECHNICAL DATA INSTALLATION INSTRUCTIONS OPERATING INSTRUCTIONS MSDS SHEETS TEST REPORTS MANUFACTURER'S WARRANTY REQUIRED SUBMISSION DATE fergusog: Enter the due date from the Contractor (DD/MMM/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (DD/MMM/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (DD/MMM/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(DD/MMM/YY)
SUBMITTAL NUMBER
fergusog: Enter the Submittal Number
CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(DD/MMM/YY)
REMARKS
fergusog: Enter any comments pertaining to the sumittal
App'd fergusog: Enter date the Contractor was notified of submittal approval
(DD/MMM/YY)
fergusog: Enter any comments pertaining to the sumittal Disapp'd fergusog: Enter date the Contractor was notified of submittal disapproval
(DD/MMM/YY)
| SCHEDULE (3064) | x | 15 DAYS POST AWARD | ||||||
| HAZARD SAFETY PLAN | x | 15 DAYS POST AWARD | ||||||
| HAZMAT AUTHORIZATION SHEET | x | 15 DAYS POST AWARD | ||||||
| TILE | x | x | x | x | x | 30 DAYS POST AWARD | ||
| RUBBER BASE AND TRANSITION | x | x | x | x | x | x | 30 DAYS POST AWARD | |
| BASE ADHESIVE | x | x | x | 30 DAYS POST AWARD | ||||
| GROUT | x | x | x | x | 30 DAYS POST AWARD | |||
| MORTAR | x | x | x | x | 30 DAYS POST AWARD | |||
| WARRANTY | x | 15 DAYS POST COMPLETION | ||||||
| O&M | x | 15 DAYS POST COMPLETION |
Section 02 SCHEDULE OF MATERIAL SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | SCHEDULES, LISTINGS,REPORTS, PLANS | MANUFACTURER'S RECOMMENDATION | TECHNICAL DATA | OPERATING INSTRUCTIONS | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBER | CONTR NOTI | ACTOR FIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS |
| A | D |
| 12 |
| 13 |
| 14 |
| 15 |
| 16 |
| 17 |
| 18 |
| 19 |
| 20 |
| 21 |
| 22 |
| 23 |
| 24 |
| 25 |
| 26 |
| 27 |
| 28 |
| 29 |
| 30 |
| 31 |
| 32 |
| 33 |
| 34 |
| 35 |
Resubmittals SCHEDULE OF MATERIAL SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | SCHEDULES, LISTINGS,REPORTS, PLANS | MANUFACTURER'S RECOMMENDATION | TECHNICAL DATA | OPERATING INSTRUCTIONS | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBER | CONTR NOTI | ACTOR FIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS |
| A | D |