4. AF Form 66 Schedule of Material Submittals.xls

Air Force Form XLS spreadsheet 91 KB Posted

Attached to
Runway and Taxiway Markings
Solicitation number
FA5702-21-R-0003
Issued by

View the file

Other versions and copies of AF Form 66

File Revision Posted Attached to
Attachment 2 AF Form 66.pdf Revision not stated REPAIR AC PAVING
AF form 66 Blank.pdf Revision not stated Demo Mini mute sites
Attach 9_AF Form 66 Submittal Register.pdf Revision not stated PKAA Dorm Water Damage Repair (Construction)
AF Form 66-EEPZ260842 Renovate Convert Comm to SAPR B730.xlsx Revision not stated B730 Renovate Convert Comm to SAPR
AF Form 66_EEPZ254664-B972 UOQ.xlsx Revision not stated B972 Renovate UOQ Community Commons
AF Form 66 B268.xlsx Revision not stated B268 Replace STUS Backup Generator
AF Form 66 B730.xlsx Revision not stated B730 - Renovate RM106 for Emergency Operations Center
AF Form 66.xlsx Revision not stated B836 Replace Electrical in Airfield Lighting Vault
AF Form 66 OSI Flooring.xlsx Revision not stated OSI B926 Flooring
EEPZ254660 Repair Control Tower HVAC B1806 - AF Form 66.xlsx Revision not stated B1806 Repair Control Tower HVAC
AF Form 66 Template.xlsx Revision not stated Replace AAS BAK-15 Controls, B2001, B2003
AF Form 66 EEPZ216808 Replace Security Forces Elevator B926.xlsx Revision not stated B926 Replace Security Forces Elevator
WT 17518487 AF Form 66.xlsx Revision not stated Repair Structural Fire Trainer B17903, 17904
AF Form 66.xlsx Revision not stated RENOVATE/CONVERT 50th 49th SQ OPS, B230
AF Form 66.xlsx Revision not stated T-6 Flightline Shacks
AF Form 66 Template.xlsx Revision not stated Replace Fire Alarms, Multi Facility
EEPZ248229 -- AF Form 66.xlsx Revision not stated Repair Kiddie Pool
Atch 2 AF Form 66.pdf Revision not stated Removal of Underground Storage Tank at Launch Facility E-10 (Laramie County, WY)
Attachment 4 - AF Form 66 Submittal Register.pdf Revision not stated Bldg 65 - Renovation of Telephone Office Area, FE Warren AFB, WY AMENDMENT 03
Attachment 7 - AF Form 66.xlsx Revision not stated Replace Chapel Windows B912
Show all 20

Who attaches AF Form 66

State Files
Iowa 1
Massachusetts 1

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION / CONTRACT NO.
20-0052 & 21-0037Repair Runway and Taxiway MarkingsFA570221R0006
(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTSTEST RESULTSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDISAPPROVED
GENERALThis document shall be a "live document"
1Project Specific Form 66XANTP + 5
2Construction ScheduleXANTP + 5
3Contractor's Health, Safety, and Environment PlanXANTP + 5
4Contractor's QA/QC PlanXANTP + 5
5Copy of Engineering License(s) of person or consultancy responsible for designXANTP + 5Provide certified translation if not in English.
DESIGN
6All submissions to be provided electronically.XXXXXXXXXXX
765% Design & Form 66XX
895% Design, Form 66, & Draft 1354XX
9Construction ScheduleXCNTP + 5
Material Submittals-Contractor to complete this section with all materials to be used in construction (Ex. Below)
TEST RESULTS
10All submissions to be provided electronically.X
11Hydrostatic Test
12Leakage Test
13Bacteriolocgical TestingXX
14Backflow Preventer Tests
15Electrical Inspections/Testing
CLOSEOUT
16Warranty DocumentsXFinal + 7
17O&M ManualsFinal + 7
18DD 1354Final + 7
19As-Builts (electronic in AutoCAD & PDF)XFinal + 7
Schedule of Material Submittals Template, Apr 18 (SAF/AQCP)

Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)

Enter any comments pertaining to the submittal

File details come from the government source that posted it. Updated .