01 32 26 - Construction Progress Reporting.pdf

PDF 89 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

This is a technical specification document for Construction Progress Reporting (Section 01 32 26) applicable to the 2027 Sewer System Improvements Project being procured by Capital Region Water (CRW) in Pennsylvania. The specification establishes mandatory reporting requirements for contractors throughout the construction phase, including daily construction reports submitted weekly upon request by the Engineer and/or Owner, material location reports submitted monthly, field condition reports submitted upon discovery of differing site conditions, and special coordination memoranda as needed. Daily reports must document comprehensive project site information including subcontractor and separate contractor rosters, personnel classifications, equipment inventory, material deliveries, weather conditions, accidents, meetings, work stoppages, delays, shortages, equipment tests, service connections, and change orders. Material location reports must provide cumulative listings of all delivered and stored materials along with delivery schedules for off-site fabricated items. Field condition reports require detailed descriptions of discrepancies between actual field conditions and contract documents, accompanied by recommendations for contract modifications.

The specification does not establish pricing terms, set-asides, or incumbent vendor requirements, as it functions as an internal operational and quality control standard rather than a procurement specification. No budget allocation, funding sources, or bond requirements are addressed in this document. The reporting requirements ensure comprehensive documentation and coordination among all contractors involved in the project, with all reports directed through the Engineer to facilitate transparent communication and change management throughout the construction period. This specification is foundational to the project's contract administration and quality assurance framework, enabling CRW to maintain detailed records of all construction activities and decisions for the duration of the sewer system improvements project.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 32 26 - Construction Progress Reporting

1.0 General

1.1 Summary

A. Section Includes:

1. Daily construction reports.

2. Material location reports.

3. Field condition reports.

4. Special reports.

B. Related Sections:

1. Section 01 10 00 – Summary.

2. Section 01 40 00 – Quality Requirements.

1.2 Submittals

A. Daily Construction Reports: Submit at weekly intervals, if requested by Engineer and/or Owner.

B. Material Location Reports: Submit at monthly intervals, if requested by Engineer and/or Owner.

C. Field Condition Reports: Submit at time of discovery of differing conditions.

D. Special Reports: Submit at time of occurrence.

1.3 Coordination

A. Coordinate preparation and processing of reports with performance of construction activities and with reporting of separate contractors.

1.4 Reports

A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:

1. List of subcontractors at Project site.

2. List of separate contractors at Project site.

3. Personnel at Project site by classification.

4. Equipment at Project site.

5. Material deliveries.

6. High and low temperatures and general weather conditions.

01 32 26 - Construction Progress Reporting

7. Accidents.

8. Meetings and significant decisions.

9. Stoppages, delays, shortages, and losses.

10. Meter readings and similar recordings.

11. Emergency procedures.

12. Orders and requests of authorities having jurisdiction.

13. Change Orders received and implemented.

14. Clarifications requested, received, and implemented.

15. Services connected and disconnected.

16. Equipment or system tests and startups.

17. Partial Completions and occupancies.

18. Substantial Completions authorized.

B. Material Location Reports: At monthly intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, showing materials previously reported plus items recently delivered. Include with list a statement of progress on and delivery dates for materials or items of equipment fabricated or stored away from Project site.

C. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

1.5 Special Reports

A. Prepare Coordination Memoranda for distribution to each Contractor involved outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings. Provide copy to the Engineer.

B. Prepare similar memoranda for the Owner and separate contractors where coordination of their work is required. All such memoranda must be directed through the Engineer.

2.0 Products – Not Used.

3.0 Execution – Not Used.

END OF SECTION