00 61 19 - Warranty Bond.pdf

PDF 126 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

This is a Warranty Bond document for the 2027 Sewer System Improvements Project (Contract No. 2026-12) issued by Capital Region Water, City of Harrisburg, Pennsylvania. The warranty bond secures the contractor's obligation to correct defective work during a correction period that commences 364 days after substantial completion of work and continues for two years thereafter. The bond covers all work encompassed by City of Harrisburg Street Cut and PennDOT Highway Occupancy Permits, including restoration and maintenance of pavement within city and state right-of-way, as well as the contractor's broader correction period obligations under the construction contract as defined in EJCDC C-700, Standard General Conditions of the Construction Contract, Paragraph 15.08.

The surety and contractor are jointly and severally bound to the owner for performance of correction period obligations. If the contractor fails to perform required corrections after written notice from the owner during the bond period, the surety must either fulfill the correction obligations itself or reimburse the owner for all costs incurred in performing the contractor's correction obligations, including correction, removal, replacement, and repair costs. The surety's liability is limited to the bond amount, and no liability extends to obligations unrelated to the construction contract. Any legal proceeding under the bond must be instituted within two years after the surety refuses or fails to perform its obligations and may be brought in any court of competent jurisdiction in the location where the work is performed.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 61 19 WARRANTY BOND

WARRANTY BOND

Contractor Surety

Name: Name:

Address (principal place of business): Address (principal place of business):

Owner Construction Contract

Name: Capital Region Water Description (name and location):

Address (principal place of business): 2027 Sewer System Improvements Project

Contract No. 2026-12

City of Harrisburg, PA 3003 North Front Street

Harrisburg, PA 17110

Contract Price:

Effective Date of

Contract:

Contract’s Date of

Substantial Completion:

Bond

Bond

Amount:

Bond Period: Commencing 364 days after

Substantial Completion of the Work under the

Construction Contract and continuing until two (2) years after such Substantial Completion.

Date of

Bond:

Modifications to this Bond form:

☐ None ☒ See Paragraph 9

Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth herein, do each cause this Warranty Bond to be duly executed by an authorized officer, agent, or representative.

Contractor as Principal Surety

(Full formal name of Contractor) (Full formal name of Surety) (corporate seal)

By: By:

(Signature) (Signature) (Attach Power of Attorney)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Attest: Attest:

(Signature) (Signature)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to Contractor, Surety, Owner, or other party is considered plural where applicable.

1. The Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to the Owner for the performance of the Construction

Contract’s Correction Period Obligations. The Construction Contract is incorporated herein by reference.

2. If the Contractor performs the Correction Period Obligations, the Surety and the Contractor shall have no obligation under this Warranty Bond.

3. If Owner gives written notice to Contractor and Surety during the Bond Period of Contractor’s obligation under the Correction Period Obligations, and Contractor does not fulfill such obligation, then Surety shall be responsible for fulfillment of such Correction Period Obligations. Surety shall either fulfill the Correction Period Obligations itself, through its agents or contractors, or, in the alternative, Surety may waive the right to fulfill the Correction Period Obligations itself and reimburse the Owner for all resulting costs incurred by Owner in performing Contractor’s

Correction Period Obligations, including but not limited to correction, removal, replacement, and repair costs.

4. The Surety’s liability is limited to the amount of this Warranty Bond. Renewal or continuation of the Warranty Bond will not modify such amount, unless expressly agreed to by Surety in writing.

5. The Surety shall have no liability under this Warranty Bond for obligations of the Contractor that are unrelated to the Construction Contract. No right of action will accrue on this Warranty Bond to any person or entity other than the Owner or its heirs, executors, administrators, successors, and assigns.

6. Any proceeding, legal or equitable, under this Warranty Bond may be instituted in any court of competent jurisdiction in the location in which the Work or part of the Work is located and must be instituted within two years after the Surety refuses or fails to perform its obligations under this Warranty Bond.

7. Written notice to the Surety, the Owner, or the Contractor must be mailed or delivered to the address shown in this Warranty Bond.

8. Definitions

8.1. Construction Contract—The agreement between the Owner and Contractor identified on the cover page of this Warranty Bond, including all Contract Documents and changes made to the agreement and the Contract Documents.

8.2. Contract Documents—All the documents that comprise the agreement between the Owner and Contractor.

8.3. Correction Period Obligations—The duties, responsibilities, commitments, and obligations of the Contractor with respect to correction or replacement of defective Work, as set forth in the Construction Contract’s Correction Period clause, EJCDC® C-700, Standard General

Conditions of the Construction Contract, Paragraph 15.08, as duly modified.

8.4. Substantial Completion—As defined in the Construction Contract.

8.5. Work—As defined in the Construction Contract.

9. This Bond specifically includes all Work covered by the City of Harrisburg Street Cut and

PennDOT Highway Occupancy Permits, including restoration and maintenance of pavement within the City and PennDOT right-of-way, but does not limit Contractor’s broader Correction

Period Obligations under the Construction Contract unless expressly stated herein.

File details come from the government source that posted it. Updated .