33 01 31 TV Inspection of Sewer Pipelines.pdf
PDF 96 KB Posted
- Attached to
- 2027 Sewer System Improvements Project
- Solicitation number
- Not on record
- Issued by
- Dauphin County, Harveys Lake Borough, Pennsylvania
About this file
This is a technical specification document for TV inspection of sewer pipelines, prepared for Capital Region Water's 2027 Sewer System Improvements Project in Pennsylvania. The specification requires post-construction internal sewer audio/video taping performed by contractors for all installed sanitary sewer mains, spot repairs, and rehabilitated pipe throughout the project. All recording equipment must meet professional-grade standards and comply with National Association of Sewer Service Companies (NASSCO) requirements and Pennsylvania Department of Transportation specifications. Video recordings must be delivered in .WMV, .MPG, .AVI, or .MP4 format on external storage devices, accompanied by typed video logs containing inspection date, sewer section and manhole numbers, distance measurements, verbal confirmations of pipe characteristics and defects, and weather conditions. Contractors must provide written 48-hour notice to the Owner and Engineer prior to taping to allow for project representatives to observe the work, and all videos and storage devices become property of the Owner upon completion.
The contractor performing television inspections must employ operators and quality assurance personnel who hold current Pipeline Assessment Certification Program (PACP) certifications from NASSCO. The camera equipment must include pan-and-tilt capability, remote-dimmable lighting systems capable of illuminating the entire pipe periphery, a minimum resolution of 650 lines, and ability to operate in 100% humidity at 400 psi pressure. All video must be in color conforming to NTSC standards with clear audio recorded in English describing field conditions and observations. The contractor is responsible for conducting inspections during periods of low flow, providing flow control measures at no additional cost, and maintaining clear picture quality throughout the taping process. Inspection coding must follow NASSCO PACP conventions, with all continuous defects properly opened and closed with corresponding defect codes, and the contractor must ensure all work meets or exceeds NASSCO standards as a minimum requirement at no additional cost to the Owner.
View the file
Other files
Show 40 more
Latest 50 of 116 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
33 01 31 TV Inspection of Sewer Pipelines
33 01 31 - 1
1.0 General
1.1 Scope
A. Post construction Internal Sewer Audio/Video Taping by the Contractor is required for all installed sanitary sewer mains, spot repairs, and rehabilitated pipe. The Contractor is required to ensure that all recording equipment used must be of professional grade as rated by the manufacturer, and meet the requirements herein.
B. Notwithstanding paragraph 1.1.A above, the requirements and specifics of this section may apply to televised inspection and videotaping of piping of all types and at all times throughout the project and/or completion of the project.
1.2 Qualifications
A. The Contractor is responsible to ensure that all required taping is performed by a firm actively engaged, experienced and knowledgeable in video taping of sewer conditions on utility projects. The Engineer and Owner reserve the right to request sample work and investigate the qualifications of any Contractor or subcontractor proposing to perform this work.
1.3 References
A. National Association of Sewer Service Companies (NASSCO)
1. Recommended Specifications for Sewer Collection System Rehabilitation.
2. Pipeline Assessment Certification Program (PACP) Standards and Requirements.
C. Pennsylvania Department of Transportation (PennDOT)
1. Publication 408 – Specifications.
1.4 Submittals
A. The Contractor shall submit under provisions of Section 01 33 00 – Submittal Procedures.
B. Certifications:
1. PACP Certification Cards – The Contractor shall submit a copy of operator PACP certification cards to the Engineer and Owner. Certification cards shall be provided for on-site operators performing the inspections as well as individuals performing QA/QC review of the videos.
C. Contractor shall provide videos recordings in electronic format acceptable to the Owner on an external storage device and typed video logs of all televised pipe sections.
D. Upon completion of the work, all videos recorded and all external storage devices utilized to store videos and/or video logs during the television inspection shall become the property of the Owner.
E. Video recordings and typed video logs shall include the following information:
1. Date of television inspection.
33 01 31 - 2
2. Sewer section and manhole number.
3. Distance along reach (tape counter footage).
4. Label.
5. Verbal confirmation of sewer section and television direction in relation to direction of flow.
6. Verbal description of pipe size, type, and pipe joint length.
7. Verbal description and location of each service connection and pipe defect.
8. Type of weather during inspection.
1.5 Quality Assurance
A. Regulatory Compliance:
1. The Contractor shall comply with applicable portions of PENNDOT Publication 408.
B. The quality of all work specified in this Section shall meet or exceed the requirements of the
National Association of Sewer Service Companies (NASSCO) Recommended Specifications for Sewer Collection System Rehabilitation (latest edition). For any applicable portions of this Section that inadvertently fall below those standards the Contractor shall correct the same and shall ensure that they are maintained at the NASSCO standards as a minimum requirement, at no additional cost to the OWNER.
C. All CCTV inspection operators, or any person who add, modify or delete inspection information, shall be PACP certified by NASSCO at the time of said work. The standards and requirements of the PACP shall be in effect for these inspections unless modified by the
Owner. This is a requirement of the Contractor.
2.0 PRODUCTS
2.1 Equipment Requirements
A. Video Recordings: Videos will be delivered entirely in electronic format, encoded in .WMV, .MPG, .AVI or .MP4 format. Each video recording shall be a separate file.
B. All video shall be in color and conform to NTSC standards. It shall contain no electrical breaks with color correctly balanced to white.
C. The camera used for the inspection shall be one specifically designed and constructed for this type of inspection. The camera should have a pan and tilt head for inspection of the top, bottom, and sides of pipe and for looking up lateral connections. The camera shall be mounted on adjustable skids or be self-propelled to keep it in the center of the pipe. The camera shall be supplied with a lamp capable of being dimmed or brightened remotely. The lighting system shall be capable of lighting the entire periphery of the pipe. The camera shall operate in 100% humidity and have a minimum of 650 lines of resolution and tested at 400 psi.
D. Audio will be recorded during field production and shall contain verbal information relevant to the conditions and items appearing on the video (i.e., identifications of place, conditions, etc.). Language used shall be English.
E. When non-remote powered winches are used to pull the camera through the line, the
Contractor is responsible to ensure that a clear picture of the sewer is maintained.
33 01 31 - 3
F. The Contractor shall use a meter to accurately record the location of the television camera with respect to the referenced manhole.
3.0 EXECUTION
3.1 Procedure
A. All taping to be done by the Contractor following successful installation of sanitary sewer mains and service lateral reconnections, or at other times as may be required.
B. The Contractor shall conduct taping during periods of low flow to insure unobstructed views of the completed work. As necessary, the Contractor shall provide flow control measures at no additional cost to the Owner.
C. The Contractor shall give the Owner and Engineer the opportunity to accompany the
Contractor during taping. The Contractor shall give a written 48 hour notice (minimum) to both the Owner and Engineer prior to video taping. Failure to provide such written notice within said time may result in rejection of the Contractor’s work, requiring the Contractor to re-tape the work, at no additional cost to the Owner.
D. The Contractor shall control direction of travel, panning rates, and zoom in-out rates in a manner that produces clarity of subject during playback. Determination of adequate clarity of subject during playback shall be as determined by the Owner or Engineer.
E. The Contractor shall properly identify all video recordings by video number date, locations and project name. The Contractor shall begin each video recording with current date, project name, and location.
F. CCTV Inspection Coding – All CCTV inspections shall be coded and conform to NASSCO PACP standards. The following NASSCO PACP conventions shall be followed for all inspections.
1. The inspection coding shall include AMH and MWL defects to open the inspection.
2. The inspection shall include a MSA or AMH defect to close the inspection.
3. All continuous defects shall be closed with the same defect code as when opened. Each start code number must have a corresponding finish code number.
END OF SECTION