Hydrostatic Testing Specification

This document is a technical specification file related to Capital Region Water's (CRW) 2027 Sewer System Improvements Project in Pennsylvania. The specification outlines hydrostatic testing requirements for sewer system infrastructure improvements, establishing the technical standards and procedures that contractors must follow when performing testing on water and sewer lines as part of the broader capital improvement initiative. The hydrostatic testing specification applies to all pipe installations and rehabilitations completed under the 2027 Sewer System Improvements Project contract, with testing required to verify pipe integrity and system performance prior to acceptance by CRW. Bids for the overall 2027 Sewer System Improvements Project (Contract No. 2026-12) were due October 27, 2026, at 10:00 AM (EST), with bids to be opened online immediately thereafter. The contract is structured on a unit price basis, and the work encompasses sewer system improvements including infrastructure installation, materials, equipment, labor, and all miscellaneous items as identified in the contract documents.

The hydrostatic testing specification establishes the technical requirements and acceptance criteria that bidders must account for in their pricing submissions for the 2027 Sewer System Improvements Project. Capital Region Water has adopted a Minority Women and Disadvantaged Business Enterprise (MWDBE) Plan to ensure equal opportunity for disadvantaged business enterprises in project participation, with contractors required to submit MWDBE documentation in compliance with contract requirements. All bid documents are available at no cost through the PennBid Bonfire Hub website, with no initial or recurring costs for bidders utilizing the platform. The specification serves as a binding technical requirement document that contractors must follow to ensure system integrity and meet CRW's acceptance standards for completed hydrostatic testing work.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 05 05.31 – Hydrostatic Testing

1.0 General

1.1 Summary

A. This Section describes the provisions for acceptance and testing for waterlines.

1.2 References

B. American Water Works Association:

1. AWWA C600, Installation of Ductile Iron Water Mains and Their Appurtenances.

1.3 Submittals

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. The Contractor shall submit following items a minimum of 72 hours prior to start of testing:

1. Testing procedures.

2. List of test equipment.

3. Testing sequence schedule.

4. Provisions for disposal of flushing and test water.

5. Certification of test gage calibration.

C. Test and Evaluation Reports: Indicate results of piping tests.

1.4 Quality Assurance

A. Design Criteria for Testing Water Mains:

1. Required Test Pressures: The Contractor shall be responsible to ensure that all water mains are tested as specified in this Section, and in accordance with all applicable AWWA regulations.

2. The Contractor shall ensure that pressure does not vary more than plus or minus five (5) psi from the required test procedures.

3. The Contractor shall obtain required test pressures shall be obtained upon request from Engineer.

2.0 Products

2.1 Hydrostatic Testing

A. Equipment:

1. Pressure pump.

2. Pressure hose.

3. Water meter.

4. Test connections.

5. Pressure relief valve.

6. Pressure Gage: Calibrated to 0.1 psig.

3.0 Execution

3.1 Preparation

A. General Requirements:

1. The Contractor shall conduct tests specified herein so that each pipeline installed in the Project is tested to the Engineer's satisfaction. The Contractor shall ensure that all piping is properly flushed and tested unless otherwise approved in writing by the Engineer, with the consent of the Owner.

2. The Contractor shall furnish and install all means and apparatus necessary for getting the air or water into the pipeline for flushing and testing including pumps, pipe connection to main, compressors, gauges, and meters, any necessary plugs and caps, and any required blow-off piping and fittings, etc., complete with any necessary reaction blocking to prevent pipe movement during the flushing and testing. The Contractor shall provide water for all flushing and testing of pipelines.

Only potable water shall be used for flushing and testing the potable water system.

The cost of water is incidental to the Project, and no separate or additional payment shall be made by the Owner.

3. Contractor shall thoroughly clean all new pipe by flushing with water, or other means approved by the Engineer, to remove all dirt, stones, pieces of wood, etc., which may have entered the pipe during the construction period. If after this cleaning any obstructions remain, they shall be corrected by the Contractor, at their own expense, to the satisfaction of the Engineer and Owner. Pipelines shall be flushed at the rate of at least 2.5 feet per second for a duration suitable to the

Engineer or shall be flushed by other methods approved in writing by the Engineer and Owner.

4. All work involving chlorinated water discharges to the surface, such as but not limited to: flushing of water mains and hydrants, water system disinfection, and hydrostatic testing shall be dechlorinated in accordance with PADEP regulations pertaining to the Planned and Unplanned Discharges of Chlorinated Waters to

Surface Waters. Refer to Section 01 41 26. The Contractor shall be solely responsible to ensure that all such requirements are complied with.

3.2 Field Quality Control

A. Inspection:

1. The Contractor shall inspect each section of pipe, joint alignment, and each pipe fitting prior to backfilling to assure the maximum deflection present in each joint does not exceed the manufacturer's recommendations.

2. Any and all defects shall be corrected by Contractor at no additional cost to Owner and to the satisfaction of Engineer prior to backfilling. This shall be completed before the work is to proceed and before acceptance of and/or payment shall be made. Remove rejected pipe and/or fittings from project.

3. The Contractor shall inspect pipelines to assure the lines are installed at a constant or increasing grade so as to eliminate the possibility for air accumulation at an intermediate high point. Where high points cannot be avoided, the Contractor shall ensure that high points within a potable water main are located at fixtures such as fire hydrants or service line connections, such that air may either not become trapped or can be released.

4. The Engineer reserves the unqualified right to oversee and inspect the testing procedures; determine the acceptability of all tests performed; and to totally control the progress or continuation of pipe laying operations in view of testing not in compliance with the herein stated criteria. With input from the Owner, the decision of the Engineer in regard to all matters related to testing shall be considered as final.

B. Hydrostatic Testing:

1. General:

a. The Contractor shall provide test pump, pipe connection to main and all necessary tools, materials and equipment, including the test gauge, required for the main testing.

b. The Contractor shall conduct pressure and leakage tests specified herein so that each water main installed in the Project is tested to the Engineer’s and

Owner’s satisfaction.

c. The Contractor shall ensure that all hydrostatic tests are in accordance with the following requirements:

i. Ductile Iron Pipe Water Mains: AWWA C600.

d. The Contractor’s hydrostatic testing equipment and installation shall be satisfactory to the Engineer prior to testing.

e. The Contractor shall conduct the hydrostatic pressure and leakage tests in the presence of and to the satisfaction of the Engineer.

f. When the length of a water main exceeds 1,200 feet, the Engineer reserves the right to require that the water main be tested in sections, the length of each section to be determined by the Engineer. This shall be at no additional cost to the Owner.

g. Water for testing shall be furnished by the Contractor. The Contractor shall utilize the existing water system via a metered hydrant connection for the quantities required. The Contractor must coordinate all arrangements and conform to Capital Region Water’s standards for use and connection. The

Contractor shall obtain a “Fire Hydrant Use Request” form from the Owner’s website (https://capitalregionwater.com/wp-content/uploads/2024/01/2022-

01-00-Fire-Hydrant-Use-Request.pdf) and shall complete the same and shall return to the Owner. The Owner reserves the right to charge the Contractor for the water used. However, the Owner’s intent is to bill the Contractor for the water used, for accounting purposes, and then reimburse the Contractor in-kind, such that there is no cost to the Contractor for water from the Owner’s system which was properly used in the course of construction. The Contractor may also elect to truck in potable water, as long as it is properly tested and documentation is provided to the Owner and Engineer demonstrating that all water brought in to the project meets the Owner’s requirements. The Owner also has a bulk water point at 100 Pine Drive, Harrisburg, PA, which the

Contractor may be able to use, with proper prior coordination with and approval by the Owner.

i. The Contractor shall use separate meters for work associated with filling, flushing, testing, etc. of main pipelines and those used in conjunction with any temporary (distribution) services.

h. The Contractor will be required to perform hydrostatic pressure testing concurrent with installation of the pipe system.

i. No testing will be authorized unless ambient air temperature is 35°F or higher.

j. Any leaks or defective pipe disclosed by the hydrostatic test shall be immediately repaired or replaced by the Contractor, at their expense, and the test repeated until all such piping passes the specified test.

k. The Contractor shall not make any new water service connections to the water distribution main and tested concurrently with the entire water distribution system. The extent of water service connection testing shall be to the curb stop. Upon completion of satisfactory testing and disinfection, the water service connection shall be connected to the existing service line in accordance with the details shown on the Drawings.

l. Under no circumstances shall the new water main pipeline be directly connected to the existing water distribution system – even if separated by an isolation valve (or valves). The new water main pipeline shall not be joined to the existing distribution system until the Owner confirms in writing that they are satisfied that all required testing has been satisfactorily completed.

2. Preparation:

a. At their own option, the Contractor may completely backfill the trench or partially backfill the trench over the center section of each pipe length prior to carrying out the pressure test. The Engineer reserves the right, however, to direct that the entire trench be backfilled, if traffic or other local conditions require such action.

b. The section of water main being tested must be filled with water by the

Contractor for the following minimum time periods before the main is tested:

ii. Ductile Iron Pipe Water Mains: 24 hours.

https://capitalregionwater.com/wp-content/uploads/2024/01/2022-01-00-Fire-Hydrant-Use-Request.pdf https://capitalregionwater.com/wp-content/uploads/2024/01/2022-01-00-Fire-Hydrant-Use-Request.pdf

c. The Contractor shall make the test by closing valves, when available, or by placing temporary bulkheads in the pipe and filling the line slowly with water.

The Contractor shall be responsible for ascertaining that all test bulkheads are suitably restrained to resist the thrust of the test pressure without damage to, or movement of, the adjacent pipe. Care shall be taken to see that all air vents are open during filling.

d. Where any section of a main is provided with concrete reaction backing, the hydrostatic pressure test shall not be made until at least five (5) days have elapsed after the concrete reaction backing was installed. If high early strength cement is used in the concrete reaction backing, the hydrostatic pressure test shall not be made until at least two (2) days have elapsed.

e. The Contractor shall ensure that the pipelines are filled at a rate that will not cause any surges or exceed the rate at which the air can be released through the air valves at a reasonable velocity; all the air within the pipelines shall be properly purged. After the pipeline or section thereof has been filled, it shall be allowed to stand under a slight pressure for a sufficient length of time to allow the escape of air from any air pockets. During this period, bulkheads, valves, and connections shall be examined for leaks. If leaks are found, corrective measures satisfactory to the Engineer shall be taken.

3. Pressure Test:

a. After the pipeline has been filled with water for the minimum time periods required, the Contractor shall conduct a pressure test. Test pressure and duration for each section of water main to be tested shall be as follows:

i. Ductile Iron Pipe Water Mains: 150 psig for at least two (2) hours.

b. The Contractor shall apply the specified test pressure by means of a pump connected to the pipe in a manner satisfactory to the Engineer. Before applying the specified test pressure, all air shall be expelled from the pipe. If hydrants or blow-offs are not available at high places, Contractor shall make the necessary taps at points of highest elevation before the test is made and insert the plugs after the test has been completed, at no additional cost to Owner.

Extreme care must be exercised to ensure that all air is expelled from the pipeline during the filling of the pipe with water.

c. The Contractor shall carefully examine all exposed pipes, joints, fittings, and valves during the test, and tighten all joints showing visible leakage. Remove all defective pipe, fittings, and valves from the line and replace by the

Contractor at his expense.

d. The section under test shall be brought back to test pressure at one-half hour intervals during the testing should repressurization be needed. Resident Project

Representative or Engineer will record both the makeup water amount and pressure at each one-half hour repressurization.

4. Leakage Test:

a. The Contractor shall conduct concurrently with the pressure test.

b. The Contractor shall provide suitable means to measure the leakage during the pressure test, and a record of water added to the pipeline shall be kept for a period of time to match the pressure test.

c. Leakage is defined as the quantity of water that must be supplied into the newly laid pipe, or any valve section thereof, to maintain pressure within five (5) psig of the specified test pressure after the air in the pipeline has been expelled and the pipe filled with water.

d. The Contractor shall ensure that all piping inside chambers, valve pits, etc.

shows no leakage.

e. Leakage in Ductile Iron pipelines shall be acceptable when it is less than the amount calculated by the following formula:

𝐿 =

𝑆𝐷√𝑃

148,000

L = Allowable Leakage (gph).

S = Length of Pipeline Tested (ft.).

D = Nominal Diameter of Pipe (in.).

P = Average test pressure during test period (psig).

f. If pipe undergoing testing contains sections of various diameters, the

Contractor shall calculate allowable leakage from sum of computed leakage for each pipe size. The Contractor shall provide their calculations, in writing, to the

Engineer for review and approval.

g. Should any test of a section of pipeline disclose leakage greater than that permitted, the Contractor shall locate and shall immediately repair the defect at the Contractor’s expense. All visible leaks are to be repaired immediately regardless of the amount of leakage.

D. Fire Hydrant Testing Requirements:

1. After installation and after pressure testing the water main, the Contractor shall test the hydrant as follows:

a. Pressure Test:

i. Open the hydrant fully and fill with water; close all outlets.

ii. To prevent caps from being blown off dry-barrel hydrants and to prevent other possible damage, vent air from the hydrant by leaving one of the caps slightly loose as the hydrant is being filled. After all air has escaped, tighten the cap before proceeding.

iii. Apply line pressure.

iv. Check for leakage at flanges, nozzles and operating stems.

v. If leakage is noted, immediately repair or replace components or complete hydrant until no leaks are evident.

b. Drainage Test for Dry-Barrel Hydrants:

i. Follow the pressure test, close hydrant.

ii. Remove one nozzle cap and place pylon or hand over nozzle opening.

iii. Drainage rate should be sufficiently rapid to create a noticeable suction.

iv. After backfilling, operate the hydrant to flush out any foreign material.

v. Tighten nozzle caps, then back them off slightly so that they will not be excessively tight; leave tight enough to prevent removal by hand.

vi. If hydrant has a plugged drain connection, pump the barrel dry after each use.

3.3 Acceptance

A. Acceptance: Observation of successful testing of piping by the Resident Project

Representative and/or Engineer does not constitute acceptance of the system or any portion thereof. Upon completion of any determined portion of a total system, and successful testing thereof, the Engineer may recommend final acceptance to the

Owner. Only upon final inspection by the Owner and Engineer and upon written acceptance for same will the system or portion thereof be considered substantially completed. Upon such acceptance, the warranty period will commence. If, during the final inspection, any irregularities are observed, the condition must be immediately corrected at the Contractor's sole expense prior to acceptance.

END OF SECTION