32 13 13 - Concrete Paving.pdf

PDF 100 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

This is a standard specification document for concrete paving work applicable to Capital Region Water's infrastructure projects in Pennsylvania. The document outlines technical requirements and standards for concrete paving materials, installation methods, and quality assurance procedures that bidders must follow when submitting proposals for the 2027 Sewer System Improvements Project and related CRW capital improvement initiatives. The specifications establish uniform requirements across multiple CRW locations in Harrisburg, Pennsylvania, including the Administrative Offices, Advanced Wastewater Treatment Facility, and Dr. Robert E. Young Water Services Center. Sealed bids for projects incorporating these concrete paving specifications must be submitted online through the PennBid Procurement Portal, with the 2027 Sewer System Improvements Project (Contract No. 2026-12) accepting bids until October 27, 2026, at 10:00 a.m. EST. Bids shall be submitted on a unit price basis, and Capital Region Water intends to award contracts to the overall lowest responsible bidder as determined by its Board of Directors. No mandatory pre-bid meetings are specified for concrete paving work; however, interested bidders may request site visits to project locations.

Pricing for concrete paving work must comply with the technical specifications outlined in the document, including material costs, labor, equipment, and all miscellaneous materials necessary for proper installation and surface restoration. Capital Region Water has adopted a Minority Women and Disadvantaged Business Enterprise Plan to ensure equal opportunity participation in project-related construction contracts. Bidders possessing current contracts with the Commonwealth of Pennsylvania Department of General Services, COSTARS, or other competitively sourced cooperative purchasing agencies are encouraged to submit pricing utilizing these existing agreements and provide relevant contract documentation. Performance and payment bonds are required in accordance with contract documents for applicable projects, and bidders must submit anti-collusion affidavits. All bid documents are available at no cost through the PennBid Bonfire Hub website, with technical assistance available from PennBid representatives at 610-693-4769.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

32 13 13 – Concrete Paving

1.0 General

1.1 Section Includes

A. Roadways

B. Driveway

C. Curbs.

D. Walks.

1.2 References

A. The "PennDOT Sections" noted herein refer to sections contained in the current

Commonwealth of Pennsylvania Department of Transportation Specifications

Publication 408, as supplemented or revised. All work shall be completed in accordance with the applicable PennDOT Standards, supplements, and interims unless otherwise noted.

B. Commonwealth of Pennsylvania Department of Transportation (PennDOT)

Publication 408, latest edition:

1. PennDOT Section 350 – Subbase.

2. PennDOT Section 501 Reinforced or Plain Cement Concrete Pavements.

3. PennDOT Section 630 Plain Cement Concrete Curb.

4. PennDOT Section 676 Cement Concrete Sidewalks.

5. PennDOT Section 703 Aggregates.

6. PennDOT Section 704 Cement Concrete.

7. PennDOT Section 960 – Hot Thermoplastic Pavement Markings.

8. PennDOT Section 962 – Waterborne Pavement Markings.

C. Commonwealth of Pennsylvania Department of Transportation Standards for

Roadway Construction Publication 72M, latest edition.

D. Commonwealth of Pennsylvania Department of Transportation Bulletin 15.

E. Commonwealth of Pennsylvania, Pennsylvania Code, Title 67, Transportation, Department of Transportation, Chapter 459, Occupancy of Highways by Utilities, as supplemented or revised.

F. Commonwealth of Pennsylvania, Pennsylvania Code, Title 67, Transportation, Department of Transportation, Chapter 212, Official Traffic Control Devices

(PennDOT Publication 212).

1.3 Definitions

A. Cementitious Materials: Portland cement alone or in combination with one or more of blended hydraulic cement, fly ash and other pozzolans, and ground granulated blast-furnace slag.

1.4 Job Conditions

A. Protection:

1. The Contractor shall protect and maintain existing roadway foundation material during roadway construction. Replace material disturbed during construction as incidental to the Project. Replacement material must consist of a material that can be adequately compacted in place, in the opinion of the Engineer.

2. The Contractor shall protect and maintain existing sidewalk foundation material during construction of sidewalk and curb. Replace material disturbed during construction as incidental to the Project. Replacement material must consist of a material that can be adequately compacted in place, in the opinion of the Engineer.

3. The Contractor shall protect and maintain existing curb foundation and curb during construction of sidewalk and full depth reconstruction. Replace curb and material disturbed during construction as incidental to the Project. Replacement material must consist of a material that can be adequately compacted in place (in the opinion of the Engineer) and matches existing conditions (in the opinion of the

Owner).

1.5 Submittals

A. The Contractor shall submit under provisions of Section 01 33 00 – Submittal

Procedures.

B. Mix Design: The Contractor shall submit mix design for each mix to be used. Design shall indicate admixtures proposed for use. Mix design shall be reviewed and approved by Engineer prior to use.

C. Certificates: The Contractor shall furnish the Engineer and local authorities requiring same, certificates originated by the batch mixing plant certifying ready mixed concrete as manufactured and delivered to be in conformance with ASTM C94.

2.0 Products

2.1 Materials

A. Reinforced or Plain Cement Concrete Pavements: In accordance with PennDOT

Publication 408, Section 501.2.

B. Plain Cement Concrete Curb: In accordance with PennDOT Publication 408, Section

630.2.

C. Cement Concrete Sidewalks and Curb Ramps: In accordance with PennDOT Publication

408, Section 676.2.

D. Aggregate Subbase: Type C or better, No. 2A, Section 703.2, placement per Section

350.

E. Aggregate Subbase: No. OGS, Section 703.2, placement per Section 350.

F. Traffic Paint - State Routes: Conforming to PennDOT Sections 960 and 962.

3.0 Execution

3.1 Construction

A. General: The Contractor shall restore streets, shoulders, driveways, parking areas and other areas according to details shown on the Contract Drawings and the Restoration

Schedule, to the satisfaction of the Owner and other AHJs.

B. Temporary Surfacing:

1. The Contractor shall install temporary pavement as directed by the Engineer in the event where permanent pavement cannot be placed due to the weather limitations set forth herein for the placing of the permanent base and surface courses. The temporary surface shall be as specified in the Restoration Schedule. This shall be at no additional cost to the Owner.

2. Contractor shall be responsible for the removal and disposal of the temporary surfacing to the grade required for the placement of the final subbase, base, and surface at the specified depths. This is incidental to the Project.

C. The Contractor shall be responsible for the maintenance and protection of all surfacing, as well as manholes, frame and covers, valve boxes, and other facilities or structures located within the areas of the roadway reconstruction until such time that the permanent pavement or surface can be placed.

D. Prior to placement of final surfacing, the Contractor, Owner, and Engineer shall inspect all areas to be restored. The Contractor shall be responsible for any replacement of material, regrading, or addition of material deemed necessary by the Engineer in any areas found to be unacceptable for receipt of final surfacing.

E. The Contractor shall be responsible for any necessary adjustments to grade for manholes, frame and covers, and other facilities or structures prior to final surfacing.

All adjustments shall be to the satisfaction of, and in accordance with, the specifications of the utility owner.

F. Reinforced or Plain Cement Concrete Pavements: The Contractor shall provide in accordance with PennDOT Publication 408, Section 501.3.

G. Plain Cement Concrete Curb: The Contractor shall provide in accordance with PennDOT

Publication 408, Section 630.3.

H. Cement Concrete Sidewalks: The Contractor shall provide in accordance with PennDOT

Publication 408, Section 676.3.

I. Pavement Markings:

1. For State Routes, The Contractor shall match existing pavement marking material type. Apply in accordance with PennDOT Sections 960 and 962. Provide satisfactory barrier cones for at least 30 minutes, or until the paint is dry and tack free from vehicular traffic. Repaint marked or damaged areas. Pavement marking placement on the state highway shall conform to TC-8600, latest edition.

2. The City of Harrisburg requires that all pavement markings - of all types, and regardless whether longitudinal or transverse to the direction of travel - on City streets be hot thermoplastic, conforming to the requirements of PA DOT Pub. 408

Section 960.

3.2 MAINTENANCE

A. The Contractor shall continuously maintain temporary paving without additional compensation until it is replaced with permanent paving.

B. The Contractor shall maintain - without additional compensation - such Work of this

Section done under this Contract for a period of twenty-four (24) months for pavement within the City of Harrisburg and PennDOT rights-of-way after the date of Owner’s approval of the Final Completion Certificate issued by Engineer, including the repair or removal and replacement of such Work which has failed or has been damaged or wherever surface depressions have been developed. Materials and methods used to repair or replace such Work shall conform to the applicable requirements of this

Section.

C. Should Contractor fail to perform required maintenance or repairs within three days after written notice from Owner or Engineer, the Owner may perform such maintenance or repairs and deduct the cost thereof from any monies due or to become due Contractor.

3.3 Restoration Schedule

A. See Section 31 23 33 – Trenching and Backfilling for Utilities, and the Contract

Drawings.

END OF SECTION