This is a technical specification document outlining closeout procedures for Capital Region Water's 2027 Sewer System Improvements Project, a general construction contract in Pennsylvania. The document establishes comprehensive requirements for project completion in two phases: substantial completion and final completion. For substantial completion, the contractor must submit maintenance manuals, project record documents, complete facility startup and testing, conduct inspections to create an initial punch list, obtain releases from authorities having jurisdiction, deliver tools and spare parts to the owner, remove temporary facilities, and perform final cleaning. The engineer will inspect the work and issue a Certificate of Substantial Completion on EJCDC C-625 form accompanied by the verified punch list, after which the contractor has a specified period to complete remaining items. For final completion, the contractor must submit written certification of compliance with contract documents, a final punch list confirming all items are completed, final payment requests with releases and insurance certificates, warranties and maintenance agreements, accounting statements for contract changes, affidavits of payment of debts and release of liens, and surety consent to final payment.

The closeout procedures require the contractor to perform final cleaning of contractor-soiled areas to the owner's satisfaction, including sweeping paved areas, raking landscaped surfaces, and removing all waste, surplus materials, rubbish, and construction facilities from the site. The engineer will conduct a final inspection to determine work completion and may require re-inspection at the contractor's expense if deficiencies are found. The contractor must submit product data for cleaning agents and obtain certificates of release from authorities having jurisdiction and utility companies. The document specifies that the contractor is responsible for all costs associated with remedying deficiencies and re-inspections, establishing clear accountability for work quality and timely completion throughout the project closeout process.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 77 00 - Closeout Procedures

1.0 General

1.1 Section Includes

A. Closeout procedures.

B. Final cleaning.

1.2 Submittals

A. Product Data: The Contractor shall submit product data for cleaning agents.

B. Contractor's List of Incomplete Items: The Contractor shall make an initial submittal at the time of Substantial Completion.

C. Closeout Submittals- The Contractor shall provide:

1. Certificates of Release: From authorities having jurisdiction.

2. Certificate of Insurance: For continuing coverage.

3. Submittals as required by various Specification Sections.

1.3 Closeout Procedures

A. Prerequisites to Substantial Completion: The Contractor shall complete following items before requesting Certification of Substantial Completion, either for entire Work or for portions of Work:

1. Submit maintenance manuals, Project record documents, and other similar final record data in compliance with this Section and the requirements of “Contractor

Requirements – Data Deliverables for Water and Sewer Infrastructure Construction

Projects”.

2. Complete facility startup, testing, adjusting, balancing of systems and equipment, demonstrations, and instructions to Owner's operating and maintenance personnel as specified in compliance with this Section.

3. Conduct inspection to establish basis for request that Work is substantially complete. Create comprehensive list (initial punch list) indicating items to be completed or corrected, value of incomplete or nonconforming Work, reason for being incomplete, and date of anticipated completion for each item. Include copy of list with request for Certificate of Substantial Completion.

4. Obtain and submit releases enabling Owner's full, unrestricted use of Project and access to services and utilities. Include certificate of occupancy, operating certificates, and similar releases from authorities having jurisdiction and utility companies.

5. Deliver tools, spare parts, extra stocks of material, and similar physical items to

Owner, at the location of the Owner’s choosing.

6. Discontinue or change over and remove temporary facilities and services from

Project Site, along with construction tools and similar elements.

7. Perform final cleaning according to this Section, and to the satisfaction of the

Owner.

B. Substantial Completion Inspection:

1. When Contractor considers Work to be substantially complete, submit to Engineer:

a. Written certificate that Work, or designated portion, is substantially complete.

b. List of items to be completed or corrected (initial punch list).

2. Upon receipt of request for Substantial Completion, Owner and Engineer will make inspection to determine whether Work or designated portion is substantially complete.

3. Should Engineer determine that Work is not substantially complete:

a. Engineer will promptly notify Contractor in writing, stating reasons for its opinion.

b. Contractor shall remedy deficiencies in Work and send second written request for Substantial Completion to Engineer.

c. Engineer will re-inspect Work.

d. Redo and Inspection of Deficient Work: Repeated until Work passes Engineer's inspection.

4. When Engineer finds that Work is substantially complete, Engineer will:

a. Prepare Certificate of Substantial Completion on EJCDC C-625 - Certificate of

Substantial Completion, accompanied by Contractor's list of items to be completed or corrected as verified and amended by Engineer and Owner (final punch list).

b. Submit preliminary Certificate to Owner for review.

c. Submit final Certificate to Owner and Contractor for their written acceptance of responsibilities assigned to them in Certificate.

5. After Work is substantially complete, Contractor shall:

a. Allow Owner occupancy of Project under provisions stated in Certificate of

Substantial Completion.

b. Complete Work listed for completion or correction within time period stipulated.

C. Prerequisites for Final Completion: Complete following items before requesting final acceptance and final payment:

1. When Contractor considers Work to be complete, submit written certification that:

a. Contract Documents have been reviewed.

b. Work has been examined for compliance with Contract Documents.

c. Work has been completed according to Contract Documents.

d. Work is completed and ready for final inspection.

2. Submittals- The Contractor shall submit following:

a. Final punch list indicating all items have been completed or corrected.

b. Final payment request with final releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations where required.

c. Specified warranties, workmanship/maintenance bonds, maintenance agreements, and other similar documents.

d. Accounting statement for final changes to Contract Sum.

e. Contractor's affidavit of payment of debts and claims on form in Section 00 65

19.16.

f. Contractor affidavit of release of liens on form in Section 00 65 19.16.

g. Consent of surety to final payment on form in Section 00 65 19.19.

3. The Contractor shall perform final cleaning for Contractor-soiled areas according to this Section, to the satisfaction of the Owner.

D. Final Completion Inspection:

1. After receipt of request for final inspection, Engineer will make inspection to determine whether Work or designated portion is complete.

2. Should Engineer or Owner consider Work to be incomplete or defective:

a. Engineer will promptly notify Contractor in writing, listing incomplete or defective Work.

b. Contractor shall remedy stated deficiencies and send second written request to

Engineer that Work is complete.

c. Engineer and Owner will re-inspect Work.

d. Redo and Inspection of Deficient Work: Repeated until Work passes Engineer's and Owner's inspection. Contractor shall reimburse Owner for the costs of

Engineer for re-inspections due to incomplete Work.

2.0 Products - Not Used.

3.0 Execution

3.1 Final Cleaning

A. Clean Site: sweep paved areas, rake clean landscaped surfaces.

B. Remove waste and surplus materials, rubbish, and construction facilities from Site.

C. The Contractor shall perform all final cleaning activities, which shall be to the satisfaction of the Owner.

END OF SECTION