00 73 53 - Anti-Pollution Measures.pdf

PDF 77 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

This document is a specification file for anti-pollution measures related to Capital Region Water's (CRW) multiple procurement projects in Harrisburg, Pennsylvania. The file supports several concurrent bidding opportunities administered by CRW through the PennBid Procurement Portal, including projects for uniform rental and mat services, water system improvements, sewer system improvements, gate house VFD drive installation, photovoltaic module pre-purchase, and trenchless sewer and water maintenance services. Sealed bids for these various projects are due at different dates ranging from September 17, 2025, through May 1, 2026, with most bids opening online immediately after submission deadlines. The 2027 Sewer System Improvements Project (Contract No. 2026-12) specifically closes on October 27, 2026, at 10:00 a.m. EST, with bids on a unit price basis. A mandatory pre-bid meeting for the Gate House VFD Drive project is scheduled for September 5, 2025, at 9:00 a.m., with optional site visits available for other projects. CRW intends to award contracts to the overall lowest responsible bidder as determined by its Board of Directors in the best interest of the organization.

The procurement solicitations encourage bidders to leverage existing contracts from the Commonwealth of Pennsylvania's Department of General Services (COSTARS) and other cooperative purchasing agencies, with flexibility in contract sourcing. Capital Region Water has adopted a Minority Women and Disadvantaged Business Enterprise (MWDBE) Plan to ensure equal opportunity for participating businesses, requiring submission of MWDBE documentation for construction-related contracts. Performance and payment bonds are required for the photovoltaic modules contract and certain other projects, while anti-collusion affidavits are required for specific bids. No specific budget ranges or incumbent vendor information is disclosed in the available documentation. All bid documents and proposal packets are available at no cost through the PennBid Bonfire Hub website, and bidders can utilize the platform without initial or recurring costs. Contract terms vary by project, with the trenchless maintenance contract specified as a three-year period subject to work orders.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 73 53 – Anti-Pollution Measures

1.0 General

1.1 Document Includes

A. Duties and requirements of Contractor under various laws and regulations, supplementing the requirements contained in the General Conditions.

1.2 Related Documents

A. Document 00 72 00 – General Conditions.

1.3 Environmental Pollution

A. Contractor shall comply with all provisions of Federal and State statutes, rules and regulations dealing with the prevention of environmental pollution, and the preservation of public natural resources that affect the project pursuant to the provisions of Act No. 247 of the General Assembly of the Commonwealth of

Pennsylvania, approved October 26, 1972.

1.4 Stormwater Pollution Prevention

A. Any Contractor involved in an earthmoving activity is responsible for complying with the DEP Regulation Chapter 102, Erosion Control. The Contractor must develop, implement and maintain a soil erosion and sedimentation control plan and must have the plan available at the earthmoving site. If an erosion and sedimentation control plan is contained in the Contract Documents or is issued by the Engineer, it shall be used until such a time that the Contractor develops a new plan and obtains review comments by the County Conservation District and approval by the local political subdivision and the Engineer.

END OF DOCUMENT