33 05 05.36 - Vacuum Testing.pdf

PDF 184 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

This is a technical specification document for vacuum testing of sewage and stormwater manholes, prepared by Capital Region Water (CRW) in Pennsylvania for its 2027 Sewer System Improvements Project. The specification establishes comprehensive requirements for vacuum testing procedures that contractors must follow prior to backfilling newly constructed or repaired manholes. Testing must comply with ASTM C1244 standards and requires contractors to submit testing procedures, equipment lists, testing sequence schedules, water disposal provisions, and test gage calibration certifications prior to commencing work. The vacuum testing process involves drawing a vacuum to 10 inches of mercury and monitoring for pressure loss over specified durations based on manhole diameter, with test periods ranging from 60 seconds for 4-foot diameter manholes to 120 seconds for 8-foot diameter manholes. Acceptable performance requires that vacuum drop does not exceed 1 inch of mercury during the test period; manholes exceeding this threshold must be repaired and retested at no additional cost to the owner.

The specification requires contractors to provide qualified applicators and maintain specific equipment including vacuum pumps, vacuum lines, compression band seals, shutoff valves, stopwatches, plugs, and calibrated vacuum gages. All repair work and visible leak remediation must be completed at contractor expense regardless of leakage quantity until test criteria are met. The contractor bears responsibility for conducting repairs and retesting until results meet specification criteria, with no additional compensation provided by the owner. No specific pricing information, set-asides, incumbent vendor details, or funding sources are disclosed within this technical specification document.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 05 05.36 - Vacuum Testing

1.0 General

1.1 Summary

A. Section Includes: Vacuum testing of manholes.

B. Related Requirements:

1. Section 33 05 61 - Concrete Manholes: Requirements for sewage and stormwater manholes.

2. Section 33 31 11 – Public Sanitary Sewerage Gravity Piping: Pipe materials, manholes, and accessories normally encountered with gravity sewerage piping.

1.2 Reference Standards

A. ASTM International:

1. ASTM C1244 - Standard Test Method for Concrete Sewer Manholes by the

Negative Air Pressure (Vacuum) Test Prior to Backfill.

1.3 Submittals

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

B. Submit following items prior to start of testing:

1. Testing procedures.

2. List of test equipment.

3. Testing sequence schedule.

4. Provisions for disposal of flushing and test water.

5. Certification of test gage calibration.

C. Test and Evaluation Reports: The Contractor shall indicate results of manhole tests.

D. Qualifications Statement:

1. The Contractor shall submit qualifications for applicator.

2.0 Products

2.1 Vacuum Testing

A. Equipment:

1. Vacuum pump.

2. Vacuum line.

3. Vacuum Tester Base:

a. Compression band seal.

b. Outlet port.

4. Shutoff valve.

5. Stopwatch.

6. Plugs.

7. Vacuum Gage: Calibrated to 0.1 in. Hg.

3.0 Execution

3.1 Examination

A. Section 01 73 00 – Execution Requirements: Requirements for installation examination.

B. The Contractor shall verify that manholes are ready for testing.

C. The Contractor shall verify that manholes are backfilled.

3.2 Field Quality Control

A. Section 01 40 00 – Quality Requirements: Requirements for inspecting and testing.

B. Manhole Testing:

1. Repair both outside and inside of joint to ensure permanent seal.

2. Test manholes with manhole frame set in place.

3. The Contractor shall follow these steps and procedures for Vacuum Testing:

a. Comply with ASTM C1244.

b. Plug pipe openings; securely brace plugs and pipe.

c. Inflate compression band to create seal between vacuum base and structure.

d. Connect vacuum pump to outlet port with valve open, then draw vacuum to 10 in. Hg.

e. Close valve.

f. Manhole Test Duration in Seconds:

1) Manhole Diameter of 4 Feet: 60.

2) Manhole Diameter of 5 Feet: 75.

3) Manhole Diameter of 6 Feet: 90.

4) Manhole Diameter of 8 Feet: 120.

g. Record vacuum drop during test period.

h. If vacuum drop is greater than 1 in. Hg during testing period, repair and retest manhole.

i. If vacuum drop of 1 in. Hg does not occur during test period, manhole is acceptable; discontinue testing.

j. If vacuum test fails to meet 1-in. Hg drop in specified time after repair, repair and retest manhole.

4. If unsatisfactory testing results are achieved, the Contractor shall repair manhole and retest until result meets criteria, at no additional cost to the

Owner.

5. The Contractor shall repair visible leaks regardless of quantity of leakage at no additional cost to the Owner.

END OF SECTION

1.1 Summary
A. Section Includes: Vacuum testing of manholes.
B. Related Requirements:
2. Section 33 31 11 – Public Sanitary Sewerage Gravity Piping: Pipe materials, manholes, and accessories normally encountered with gravity sewerage piping.
1.2 Reference Standards
A. ASTM International:
1.3 Submittals
A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.
B. Submit following items prior to start of testing:
1. Testing procedures.
2. List of test equipment.
3. Testing sequence schedule.
4. Provisions for disposal of flushing and test water.
5. Certification of test gage calibration.
C. Test and Evaluation Reports: The Contractor shall indicate results of manhole tests.
D. Qualifications Statement:
1. The Contractor shall submit qualifications for applicator.
2.0 Products
1. Vacuum pump.
2. Vacuum line.
3. Vacuum Tester Base:
a. Compression band seal.
b. Outlet port.
4. Shutoff valve.
5. Stopwatch.
6. Plugs.
7. Vacuum Gage: Calibrated to 0.1 in. Hg.
3.0 Execution
3.1 Examination
A. Section 01 73 00 – Execution Requirements: Requirements for installation examination.
B. The Contractor shall verify that manholes are ready for testing.
C. The Contractor shall verify that manholes are backfilled.
3.2 Field Quality Control
A. Section 01 40 00 – Quality Requirements: Requirements for inspecting and testing.
B. Manhole Testing:
a. Comply with ASTM C1244.
f. Manhole Test Duration in Seconds:
1) Manhole Diameter of 4 Feet: 60.
2) Manhole Diameter of 5 Feet: 75.
3) Manhole Diameter of 6 Feet: 90.
4) Manhole Diameter of 8 Feet: 120.
h. If vacuum drop is greater than 1 in. Hg during testing period, repair and
retest manhole.
i. If vacuum drop of 1 in. Hg does not occur during test period, manhole
is acceptable; discontinue testing.
j. If vacuum test fails to meet 1-in. Hg drop in specified time after repair,
repair and retest manhole.
4. If unsatisfactory testing results are achieved, the Contractor shall repair manhole and retest until result meets criteria, at no additional cost to the Owner.
5. The Contractor shall repair visible leaks regardless of quantity of leakage at no additional cost to the Owner.